12-R-0004 _A7 _Demo_SOO.docx

DOCX document 26 KB Posted

Attached to
Base Widw Corrosion Control Painting Federal contract opportunity
Solicitation number
FA4610-12-R-0004
Issued by
Department of the Air Force Space Command

About this file

Attachment 7 12-R-0004 Demo SOO

View the file

Other files for this federal contract opportunity

Other files attached to Base Widw Corrosion Control Painting, newest first.
File Type Posted
FA4610-12-R-0004_Conformed_Copy.pdf PDF
FA4610-12-R-0004-0002 _Paint.pdf PDF
12-R-0004 _Corrosion-Paint _Q-n-A.docx DOCX document
12-R-0004_Painting_Presentation_(4_Jun_14).pdf PDF
12-R-0004_Minutes.pdf PDF
FA4610-12-R-0004-0001 _Paint.pdf PDF
FA4610-11-R-0004 _Paint.pdf PDF
12-R-0004 _A4 _CA140023.doc DOC document
12-R-0004 _A3_VAFB_Environmental_Compliance_Requirements.doc DOC document
12-R-0004 _A2 _Painting _Exhibit_A_Pricing_Schedule.xlsx XLSX spreadsheet
12-R-0004 _A6 _Facility_excellence.pdf PDF
12-R-0004 _A5 _Task_Ordr_Work_Sheet.xlsx XLSX spreadsheet
12-R-0004 _A1 _Painting_SOW.doc DOC document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Objectives Project Number/Title: Repaint Exterior, Fac# 13330 Date: 14 March 2014

SUMMARY OF WORK

1. Project Scope:

This project is located at Bldg 13330 on Vandenberg AFB, California. The contractor shall furnish all materials, equipment, labor and personnel necessary to plan, design, manage, and perform as required in accomplishing said Task Order in accordance with the Base Wide Paintand Corrropsopm Control specfication requirements. A complete and usable product shall be furnished to the Government upon completion of this Task Order.

2. Basis of Design:

Facility 13330 is located in the main cantonment area and is used as dinning facility. The building structure framing consist of stucco and split-faced block with metal flashing and guttering. Periodic maintenance and painting is required to prevent premature failure. Some exterior surfaces require minor surface repairs.

3. Principal Features of work:

0. The building will require minor stucco, minor bondo, and spot primer repairs prior to exterior protective coating. All paintable exterior wall/sidings, doors, doorframes, window frames, exterior appurtenances, and items associated with the facility’s exterior will be painted to the original existing color.

b. All surrounding block wall fences, trash recepitical, or adjacent facilities within 150 feet from building 13330 are to be cleaned, readied, and clear coat block sealed.

c. Repair and paint roof flashing and gutters with inhibiting primer and apply exterior finishing elastomeric paint.

d. Access to the facility will require coordination and scheduling with Facility 13330, Facility Manager (FM), building 11013. The contractor will be required to supply a proposed schedule of work that does not prevent paternt .

GUARDIANS OF THE HIGH FRONTIER

File details come from the government source that posted it. Updated .