Attachment 2 12-R-0004 Painting Exhibit A Pricing Schedule
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4610-12-R-0004_Conformed_Copy.pdf | ||
| FA4610-12-R-0004-0002 _Paint.pdf | ||
| 12-R-0004 _Corrosion-Paint _Q-n-A.docx | DOCX document | |
| 12-R-0004_Painting_Presentation_(4_Jun_14).pdf | ||
| 12-R-0004_Minutes.pdf | ||
| FA4610-12-R-0004-0001 _Paint.pdf | ||
| 12-R-0004 _A6 _Facility_excellence.pdf | ||
| 12-R-0004 _A5 _Task_Ordr_Work_Sheet.xlsx | XLSX spreadsheet | |
| 12-R-0004 _A1 _Painting_SOW.doc | DOC document | |
| FA4610-11-R-0004 _Paint.pdf | ||
| 12-R-0004 _A4 _CA140023.doc | DOC document | |
| 12-R-0004 _A7 _Demo_SOO.docx | DOCX document | |
| 12-R-0004 _A3_VAFB_Environmental_Compliance_Requirements.doc | DOC document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Basic Period
| SUBLINE ITEM | TASK | ESTIMATED WORKLOAD | UNIT OF MEASURE | UNIT PRICE | ESTIMATED AMOUNT |
| 0001AA | Exterior protective coating, spot prime and one coat of finish. Par: 1.2.9.1 | 880,000 | SF | ||
| 0001AB | Second coat of finish, exterior. Par: 1.2.9.2 | 70,000 | SF | ||
| 0001AC | Contaminant testing and reports. Par: 1.2.9.3 | 40 | EA | ||
| 0001AD | Power wash exterior surfaces, wastewater discharged to grade. Par: 1.2.9.4 | 437,870 | SF | ||
| 0001AE | Power wash exterior surfaces, full wastewater capture and containment./Disposal of wastewater at Vandenberg AFB IWTP/Disposal of wastewater at Vandenberg AFB CAP Par: 1.2.9.5 | 3,600 | SF | ||
| 0001AF | Wet scraping. Par: 1.2.9.6 | 2,020 | SF | ||
| 0001AG | Power tooling. Par: 1.2.9.7 | 43,500 | SF | ||
| 0001AH | Exterior bond prep. Par: 1.2.9.8 | 120,550 | SF | ||
| 0001AJ | Rust inhibiting primer. Par: 1.2.9.9 | 10,200 | SF | ||
| 0001AK | Block sealing. Par: 1.2.10 | 16,000 | SF | ||
| 0001AL | Elastomeric coating Par: 1.2.11 | 9,000 | SF | ||
| 0001AM | Coating, Rust Bond FC: 1.2.13.3 | 55,000 | SF | ||
| 0001AN | Coating, Carbomastic 15: 1.2.13.2 | 55,000 | SF | ||
| 0001AO | Coating, Carbomcrylic 3359DTM or Carbocrylic FC 1.2.13.3 | 55,000 | SF | ||
| 0001AP | Abrasive blast cleaning: Par 1.2.14 | 39,303 | SF | ||
| 0001AQ | Stucco repair. Par: 1.2.15 | 40 | EA | ||
| 0001AR | Basewide traffic striping. Par: 1.3.1 | 200,000 | LF | ||
| 0001AS | Parking lot striping. Par: 1.3.2 | 20,000 | LF | ||
| 0001AT | Directional arrows. Par: 1.3.3 | 50 | EA | ||
| 0001AU | Handicapped parking. Par: 1.3.4 | 30 | EA | ||
| 0001AV | Other traffic markings. Par: 1.3.5 | 15,000 | SF | ||
| 0001AW | Striping and marking of airfields & helipads. Par: 1.3.6 | 12,000 | SF | ||
| 0001AX | Interior protective coating, one coat of finish. Par: 1.4.3 | 60,000 | SF | ||
| 0001AY | Hospital interior, one coat of finish. Par: 1.4.4 | 1,000 | SF | ||
| 0001AZ | Bed and tape drywall surfaces. Par: 1.4.5 | 3,000 | SF | ||
| 0001BA | Apply texture, hand or machine. Par: 1.4.6 | 10,000 | SF | ||
| 0001BB | Prime interior walls. Par: 1.4.7 | 60,000 | SF | ||
| 0001BC | Patch holes in drywall up to one square foot each in size. Par: 1.4.8 | 160 | EA | ||
| 0001BD | Wallpaper removal. Par: 1.4.9 | 1,400 | SF | ||
| 0001BE | Epoxy coating. Par: 1.5.1 | 10,000 | SF | ||
| 0001BF | Urethane coating: Par. 1.5.2 | 10,000 | SF | ||
| 0001BG | Nonskid coating. Par: 1.5.3 | 3,000 | SF | ||
| 0001BH | Concrete floor layout and painting. Par: 1.5.4 | 600 | LF | ||
| 0001BJ | Work other than normal duty hours: Par. 1.6 | 4,000 | SF | ||
| 0001BK | Non priced items: Para. 1.7 | 10,000 | SF | ||
| Basic Period Estimated Total | $ - 0 |
&"Times New Roman,Regular"FA4610-12-R-0004 Attachment 2 Exhibet A, Pricing Schedule
Option 1
| SUBLINE ITEM | TASK | ESTIMATED WORKLOAD | UNIT OF MEASURE | UNIT PRICE | ESTIMATED AMOUNT |
| 1001AA | Exterior protective coating, spot prime and one coat of finish. Par: 1.2.9.1 | 760,000.00 | SF | ||
| 1001AB | Second coat of finish, exterior. Par: 1.2.9.2 | 30,000.00 | SF | ||
| 1001AC | Contaminant testing and reports. Par: 1.2.9.3 | 20 | EA | ||
| 1001AD | Power wash exterior surfaces, wastewater discharged to grade. Par: 1.2.9.4 | 437,870.00 | SF | ||
| 1001AE | Power wash exterior surfaces, full wastewater capture and containment./Disposal of wastewater at Vandenberg AFB IWTP/Disposal of wastewater at Vandenberg AFB CAP Par: 1.2.9.5 | 3,600.00 | SF | ||
| 1001AF | Wet scraping. Par: 1.2.9.6 | 1,600.00 | SF | ||
| 1001AG | Power tooling. Par: 1.2.9.7 | 8,000.00 | SF | ||
| 1001AH | Exterior bond prep. Par: 1.2.9.8 | 100,000.00 | SF | ||
| 1001AJ | Rust inhibiting primer. Par: 1.2.9.9 | 6,000.00 | SF | ||
| 1001AK | Block sealing. Par: 1.2.10 | 16,000.00 | SF | ||
| 1001AL | Elastomeric coating Par: 1.2.11 | 8,000.00 | SF | ||
| 1001AM | Coating, Rust Bond FC: 1.2.13.1 | 51,200.00 | SF | ||
| 1001AN | Coating, Carbomastic 15: 1.2.13.2 | 51,200.00 | SF | ||
| 1001AO | Coating, Carbomcrylic 3359DTM or Carbocrylic FC 1.2.13.3 | 51,200.00 | SF | ||
| 1001AP | Abrasive blast cleaning: Par 1.2.14 | 39,303.00 | SF | ||
| 1001AQ | Stucco repair. Par: 1.2.15 | 40 | EA | ||
| 1001AR | Basewide traffic striping. Par: 1.3.1 | 130,944.00 | LF | ||
| 1001AS | Parking lot striping. Par: 1.3.2 | 6,000.00 | LF | ||
| 1001AT | Directional arrows. Par: 1.3.3 | 22 | EA | ||
| 1001AU | Handicapped parking. Par: 1.3.4 | 8 | EA | ||
| 1001AV | Other traffic markings. Par: 1.3.5 | 7,000.00 | SF | ||
| 1001AW | Striping and marking of airfields & helipads. Par: 1.3.6 | 12,000.00 | SF | ||
| 1001AX | Interior protective coating, one coat of finish. Par: 1.4.3 | 56,484.00 | SF | ||
| 1001AY | Hospital interior, one coat of finish. Par: 1.4.4 | 1,000.00 | SF | ||
| 1001AZ | Bed and tape drywall surfaces. Par: 1.4.5 | 1,304.00 | SF | ||
| 1001BA | Apply texture, hand or machine. Par: 1.4.6 | 4,691.00 | SF | ||
| 1001BB | Prime interior walls. Par: 1.4.7 | 41,948.00 | SF | ||
| 1001BC | Patch holes in drywall up to one square foot each in size. Par: 1.4.8 | 160 | EA | ||
| 1001BD | Wallpaper removal. Par: 1.4.9 | 2,723.00 | SF | ||
| 1001BE | Epoxy coating. Par: 1.5.1 | 7,000.00 | SF | ||
| 1001BF | Urethane coating: Par. 1.5.2 | 7,000.00 | SF | ||
| 1001BG | Nonskid coating. Par: 1.5.3 | 3,000.00 | SF | ||
| 1001BH | Concrete floor layout and painting. Par: 1.5.4 | 600.00 | LF | ||
| 1001BJ | Work other than normal duty hours: Par. 1.6 | 3,400.00 | SF | ||
| 1001BK | Non priced items: Para. 1.7 | 7,000.00 | SF | ||
| Estimated Total | $ - 0 |
&"Times New Roman,Regular"FA4610-12-R-0004
Option 2
| SUBLINE ITEM | TASK | ESTIMATED WORKLOAD | UNIT OF MEASURE | UNIT PRICE | ESTIMATED AMOUNT |
| 2001AA | Exterior protective coating, spot prime and one coat of finish. Par: 1.2.9.1 | 760,000.00 | SF | ||
| 2001AB | Second coat of finish, exterior. Par: 1.2.9.2 | 30,000.00 | SF | ||
| 2001AC | Contaminant testing and reports. Par: 1.2.9.3 | 20 | EA | ||
| 2001AD | Power wash exterior surfaces, wastewater discharged to grade. Par: 1.2.9.4 | 437,870.00 | SF | ||
| 2001AE | Power wash exterior surfaces, full wastewater capture and containment./Disposal of wastewater at Vandenberg AFB IWTP/Disposal of wastewater at Vandenberg AFB CAP Par: 1.2.9.5 | 3,600.00 | SF | ||
| 2001AF | Wet scraping. Par: 1.2.9.6 | 1,600.00 | SF | ||
| 2001AG | Power tooling. Par: 1.2.9.7 | 8,000.00 | SF | ||
| 2001AH | Exterior bond prep. Par: 1.2.9.8 | 100,000.00 | SF | ||
| 2001AJ | Rust inhibiting primer. Par: 1.2.9.9 | 6,000.00 | SF | ||
| 2001AK | Block sealing. Par: 1.2.10 | 16,000.00 | SF | ||
| 2001AL | Elastomeric coating Par: 1.2.11 | 8,000.00 | SF | ||
| 2001AM | Coating, Rust Bond FC: 1.2.13.1 | 51,200.00 | SF | ||
| 2001AN | Coating, Carbomastic 15: 1.2.13.2 | 51,200.00 | SF | ||
| 2001AO | Coating, Carbomcrylic 3359DTM or Carbocrylic FC 1.2.13.3 | 51,200.00 | SF | ||
| 2001AP | Abrasive blast cleaning: Par 1.2.14 | 39,303.00 | SF | ||
| 2001AQ | Stucco repair. Par: 1.2.15 | 40 | EA | ||
| 2001AR | Basewide traffic striping. Par: 1.3.1 | 130,944.00 | LF | ||
| 2001AS | Parking lot striping. Par: 1.3.2 | 6,000.00 | LF | ||
| 2001AT | Directional arrows. Par: 1.3.3 | 22 | EA | ||
| 2001AU | Handicapped parking. Par: 1.3.4 | 8 | EA | ||
| 2001AV | Other traffic markings. Par: 1.3.5 | 7,000.00 | SF | ||
| 2001AW | Striping and marking of airfields & helipads. Par: 1.3.6 | 12,000.00 | SF | ||
| 2001AX | Interior protective coating, one coat of finish. Par: 1.4.3 | 56,484.00 | SF | ||
| 2001AY | Hospital interior, one coat of finish. Par: 1.4.4 | 1,000.00 | SF | ||
| 2001AZ | Bed and tape drywall surfaces. Par: 1.4.5 | 1,304.00 | SF | ||
| 2001BA | Apply texture, hand or machine. Par: 1.4.6 | 4,691.00 | SF | ||
| 2001BB | Prime interior walls. Par: 1.4.7 | 41,948.00 | SF | ||
| 2001BC | Patch holes in drywall up to one square foot each in size. Par: 1.4.8 | 160 | EA | ||
| 2001BD | Wallpaper removal. Par: 1.4.9 | 2,723.00 | SF | ||
| 2001BE | Epoxy coating. Par: 1.5.1 | 7,000.00 | SF | ||
| 2001BF | Urethane coating: Par. 1.5.2 | 7,000.00 | SF | ||
| 2001BG | Nonskid coating. Par: 1.5.3 | 3,000.00 | SF | ||
| 2001BH | Concrete floor layout and painting. Par: 1.5.4 | 600.00 | LF | ||
| 2001BJ | Work other than normal duty hours: Par. 1.6 | 3,400.00 | SF | ||
| 2001BK | Non priced items: Para. 1.7 | 7,000.00 | SF | ||