Attch_02_01_11_00_SUMMARY_OF_WORK.pdf

PDF 67 KB Posted

Attached to
Repair/Replace Various Roofs Federal contract opportunity
Solicitation number
FA4418-15-R-0017
Issued by
Department of the Air Force Air Mobility Command

About this file

Attachment 2

View the file

Other files for this federal contract opportunity

Other files attached to Repair/Replace Various Roofs, newest first.
File Type Posted
Site_Visit_Mtg_Mins.pdf PDF
2_-_Plan_Dwg_Sht_Bldg_209_Mezzanine_Floor.pdf PDF
33_-_Plan_Dwg_Sht_A-48_Bldg_3270.pdf PDF
20_-_Plan_Dwg_Sht_A-14_Bldg_3270.pdf PDF
30_-_Plan_Dwg_Sht_A-45_Bldg_3270.pdf PDF
13_-_Plan_Dwg_Sht_A-2_Bldg_3270.pdf PDF
4_-_Plan_Dwg_Sht_Bldg_419_Elevations.pdf PDF
32_-_Plan_Dwg_Sht_A-47_Bldg_3270.pdf PDF
10_-_Plan_Dwg_Sht_Bldg_3371_Roof_Plan.pdf PDF
29_-_Plan_Dwg_Sht_A-44_Bldg_3270.pdf PDF
23_-_Plan_Dwg_Sht_A-37_Bldg_3270.pdf PDF
15_-_Plan_Dwg_Sht_A-4_Bldg_3270.pdf PDF
28_-_Plan_Dwg_Sht_A-43_Bldg_3270.pdf PDF
12_-_Plan_Dwg_Sht_A-1_Bldg_3270.pdf PDF
14_-_Plan_Dwg_Sht_A-3_Bldg_3270.pdf PDF
6_-_Plan_Dwg_Sht_Bldg_419_Roof_Framing.pdf PDF
5_-_Plan_Dwg_Sht_Bldg_419_Floor_Plan.pdf PDF
24_-_Plan_Dwg_Sht_A-38_Bldg_3270.pdf PDF
3_-_Plan_Dwg_Sht_Bldg_209_Mezzanine_Framing.pdf PDF
31_-_Plan_Dwg_Sht_A-46_Bldg_3270.pdf PDF
8_-_Plan_Dwg_Sht_Bldg_419_Various_Sections.pdf PDF
25_-_Plan_Dwg_Sht_A-40_Bldg_3270.pdf PDF
7_-_Plan_Dwg_Sht_Bldg_419_Roof_Section.pdf PDF
21_-_Plan_Dwg_Sht_A-24_Bldg_3270.pdf PDF
26_-_Plan_Dwg_Sht_A-41_Bldg_3270.pdf PDF
16_-_Plan_Dwg_Sht_A-8_Bldg_3270.pdf PDF
27_-_Plan_Dwg_Sht_A-42_Bldg_3270.pdf PDF
9_-_Plan_Dwg_Sht_Bldg_3305_Roof.pdf PDF
17_-_Plan_Dwg_Sht_A-9_Bldg_3270.pdf PDF
22_-_Plan_Dwg_Sht_A-36_Bldg_3270.pdf PDF
Q A_1.pdf PDF
Attch_12_01_50_10_ENVIRONMENTAL.pdf PDF
Attch_18_Part_3_Bldg_31-209-419-3305-3371_Roof_Repair.pdf PDF
Attch_07_01_33_16_DESIGN_AFTER_AWARD.pdf PDF
Attch_21_Wage_Determination.pdf PDF
FA4418-15-R-0017.pdf PDF
Attch_04_01_30_00_ADMINISTRATIVE_REQUIREMENTS.pdf PDF
Attch_20_Green_Procurement.pdf PDF
Attch_11_01_50_00_TEMP_CONSTRUCTION_FAC_ _CONTROLS.pdf PDF
Attch_01_Table_of_Contents.pdf PDF
Attch_06_01_33_00_SUBMITTAL_PROCEDURES.pdf PDF
Attch_03_01_14_00_WORK_RESTRICTIONS.pdf PDF
Attch_19_Part_3_Bldg_3270_Roof_Repair.pdf PDF
Attch_08_01_35_26_GOVERNMENTAL_SAFETY_REQUIREMENTS.pdf PDF
Attch_13_01_54_00_GREEN_PROCUREMENT.pdf PDF
Attch_14_01_57_20_WASTE_MANAGEMENT.pdf PDF
Attch_05_01_32_16_00_20_PROJ_SCHED_ _PROG_DOCS.pdf PDF
Attch_16_01_78_00_CLOSEOUT_SUBMITTALS.pdf PDF
Attch_15_01_57_50_TEMPORARY_ENVIRONMENTAL_CONTROLS.pdf PDF
Attch_10_01_45_00_QC_FOR_MINOR_CONSTRUCTION.pdf PDF
Show all 50

Repair/Replace Various Roofs has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JBCGS SECTION 01 11 00

SUMMARY OF WORK

06/15

PART 1 GENERAL

1.1 Submittals

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Utility Outage Requests; G

Road Closure Requests; G

Air Force Work Clearance Permit; G

Contractor's Proposed Laydown Area Plan; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Location

The work shall be located on Joint Base Charleston, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

Building(s) may be occupied during performance of work under this Contract.

Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 PROJECT ENVIRONMENTAL GOALS

Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporates the principles of sustainability. Specifically:

a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.

b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.

1179187112C Typewritten Text Solicitation FA4418-15-R-0017

1179187112C Typewritten Text Attachment #2

c. Use environmentally preferable products and decrease toxicity level of materials used.

d. Use renewable energy and material resources.

e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended. Consider the durability, maintainability, and flexibility of building systems.

f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.

g. Reduce construction waste through reuse, recycling, and supplier take-back.

1.5 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.6 ON-SITE PERMITS

Obtain a work clearance/digging permit prior to start of excavation. .

The Contractor is responsible for marking and verifying all utilities.

Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.6.1 NOTIFICATIONS

Notify the Contracting Officer at least 72 hours prior to starting excavation work.

1.6.2 OUTAGE REQUESTS

Utility outages and road closures required during the prosecution of work shall be arranged for the convenince of the Government. Utility outages and connections shall be scheduled outside regular working hours. Utility outage, and road closure requests shall be submitted to the Contracting Officer for coordination and Government approval at least 21 days prior to the desired outage or closure date. Requests shall clearly identify the need for the outage or closure, the requested date(s) for the outage or closure, the expected length of the outage or closure and proposed backup dates.

1.7 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.

The salvaged property shall be segregated, itemized, delivered, and off-loaded at a Government designated storage area located on Joint Base Charleston.

Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --