Attch_19_Part_3_Bldg_3270_Roof_Repair.pdf

PDF 133 KB Posted

Attached to
Repair/Replace Various Roofs
Solicitation number
FA4418-15-R-0017
Issued by

About this file

Attachment 19

View the file

Other files

File Type Posted
Site_Visit_Mtg_Mins.pdf PDF
21_-_Plan_Dwg_Sht_A-24_Bldg_3270.pdf PDF
18_-_Plan_Dwg_Sht_A-11_Bldg_3270.pdf PDF
7_-_Plan_Dwg_Sht_Bldg_419_Roof_Section.pdf PDF
5_-_Plan_Dwg_Sht_Bldg_419_Floor_Plan.pdf PDF
24_-_Plan_Dwg_Sht_A-38_Bldg_3270.pdf PDF
6_-_Plan_Dwg_Sht_Bldg_419_Roof_Framing.pdf PDF
1_-_Plan_Dwg_Sht_Bldg_31_Roof_Plan.pdf PDF
26_-_Plan_Dwg_Sht_A-41_Bldg_3270.pdf PDF
33_-_Plan_Dwg_Sht_A-48_Bldg_3270.pdf PDF
2_-_Plan_Dwg_Sht_Bldg_209_Mezzanine_Floor.pdf PDF
20_-_Plan_Dwg_Sht_A-14_Bldg_3270.pdf PDF
30_-_Plan_Dwg_Sht_A-45_Bldg_3270.pdf PDF
16_-_Plan_Dwg_Sht_A-8_Bldg_3270.pdf PDF
27_-_Plan_Dwg_Sht_A-42_Bldg_3270.pdf PDF
17_-_Plan_Dwg_Sht_A-9_Bldg_3270.pdf PDF
9_-_Plan_Dwg_Sht_Bldg_3305_Roof.pdf PDF
22_-_Plan_Dwg_Sht_A-36_Bldg_3270.pdf PDF
13_-_Plan_Dwg_Sht_A-2_Bldg_3270.pdf PDF
4_-_Plan_Dwg_Sht_Bldg_419_Elevations.pdf PDF
32_-_Plan_Dwg_Sht_A-47_Bldg_3270.pdf PDF
10_-_Plan_Dwg_Sht_Bldg_3371_Roof_Plan.pdf PDF
3_-_Plan_Dwg_Sht_Bldg_209_Mezzanine_Framing.pdf PDF
19_-_Plan_Dwg_Sht_A-12_Bldg_3270.pdf PDF
FA4418-15-R-0017-0001.pdf PDF
Q A_2.pdf PDF
31_-_Plan_Dwg_Sht_A-46_Bldg_3270.pdf PDF
8_-_Plan_Dwg_Sht_Bldg_419_Various_Sections.pdf PDF
29_-_Plan_Dwg_Sht_A-44_Bldg_3270.pdf PDF
25_-_Plan_Dwg_Sht_A-40_Bldg_3270.pdf PDF
14_-_Plan_Dwg_Sht_A-3_Bldg_3270.pdf PDF
23_-_Plan_Dwg_Sht_A-37_Bldg_3270.pdf PDF
12_-_Plan_Dwg_Sht_A-1_Bldg_3270.pdf PDF
28_-_Plan_Dwg_Sht_A-43_Bldg_3270.pdf PDF
15_-_Plan_Dwg_Sht_A-4_Bldg_3270.pdf PDF
Q A_1.pdf PDF
Attch_12_01_50_10_ENVIRONMENTAL.pdf PDF
Attch_18_Part_3_Bldg_31-209-419-3305-3371_Roof_Repair.pdf PDF
Attch_07_01_33_16_DESIGN_AFTER_AWARD.pdf PDF
Attch_21_Wage_Determination.pdf PDF
Attch_05_01_32_16_00_20_PROJ_SCHED_ _PROG_DOCS.pdf PDF
Attch_15_01_57_50_TEMPORARY_ENVIRONMENTAL_CONTROLS.pdf PDF
Attch_16_01_78_00_CLOSEOUT_SUBMITTALS.pdf PDF
Attch_10_01_45_00_QC_FOR_MINOR_CONSTRUCTION.pdf PDF
Attch_08_01_35_26_GOVERNMENTAL_SAFETY_REQUIREMENTS.pdf PDF
FA4418-15-R-0017.pdf PDF
Attch_17_01_78_23_OPERATION_AND_MAINTENANCE_DATA.pdf PDF
Attch_13_01_54_00_GREEN_PROCUREMENT.pdf PDF
Attch_09_01_42_00_SOURCES_FOR_REFERENCE_PUBLICATIONS.pdf PDF
Attch_14_01_57_20_WASTE_MANAGEMENT.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Roof Bldg 3270 Joint Base Charleston Project DKGV14-2027

Solicitation FA4418-15-R-0017 Attachment #19 Page 1 of 3

Building 3270 Roof Repair Part 3 Statement of Work / Project Program

07/24/15

Table of Contents

CHAPTERS

1. PROJECT DESCRIPTION

2. ENGINEERING SYSTEMS REQUIREMENTS

B30 Roofing F20 Selective Building Demolition

1. PROJECT DESCRIPTION

Remove all existing single-ply membrane roofing, which covers an estimated area of 62,045 SF, down to the roof deck, and replace it with a modified bitumen roof system. Drainage should be toward existing roof drains and scuppers. Make repairs to the existing standing seam metal roofing, as necessary, which covers an estimated area of 2,320 SF.

2. ENGINEERING SYSTEMS REQUIREMENTS

B30 ROOFING

Provide a complete new insulated roof system design and construction services for the entire facility roof system, and including all necessary ancillary and incidental work necessary for a complete, new, watertight roof system installation.

B3010 ROOF COVERINGS

Remove all the existing single-ply membrane roofing and flashing down to the deck. Properly dispose of the demolished materials in a landfill not on the military installation.

The existing roof deck is presumed to be metal.

Assume the project will require the replacement of approximately 10% of the existing metal roof deck, which should be included in your roofing price as a separate line item.

For reroofing, construction of the roof system shall be multi-ply modified bitumen with reflective granule surface.

Slope the new roof system for drainage toward existing roof drains and scuppers.

Provide all new insulation, roof membrane, membrane flashing, sheet metal flashing materials, and accessories and incidental work necessary for a complete, new, watertight modified bitumen roof system installation.

Insulation system above roof deck shall be minimum R-20 where over environmentally interiors, but no less than that required by ASHRAE 90.1, Chapter 5 for project climate zone.

Make repairs to the existing standing seam metal roofing, as necessary, in order to preclude water infiltration by replacing panels or by soldering minor holes.

B3020 PERFORMANCE REQUIREMENTS

The installed roof system shall be watertight; free of defects in materials and workmanship; free of damage, including blisters, delamination, cuts, scratches, abrasions, and patchwork; provide for

Project DKGV14-2027

Solicitation FA4418-15-R-0017 Attachment #19 Page 2 of 3 positive drainage of the roof surface area; and suitable for the climatic and service conditions of the installation.

Provide roof system with solar reflectance, thermal emittance and total thermal performance as prescribed by ASHRAE 90.1, Chapter 5 for project climate zone and as required by other project sustainability goals.

B3030 WIND UPLIFT AND FIRE RESISTANCE REQUIREMENTS

The roof system shall be designed and attached to resist wind uplift pressures calculated in accordance with ASCE 7. Uplift resistance shall be validated by applicable Factory Mutual (FM) uplift testing, or calculations based on standard engineering practice and applicable recommendations of FM.

Sheet metal perimeter and flashing components shall be designed, attached, and installed to provide for wind resistance equivalent to or greater than that required for the roof membrane system, and in accordance with FM, NRCA, or other applicable industry standard recommendations.

The roof system shall provide Class A or Class B fire resistance, as tested by standard ASTM, FM, or UL procedures.

B3040 ROOF WARRANTY

Provide a manufacturer no-dollar-limit 20-year water-tightness warranty for the portion of the roof system that is covered by modified bitumen roofing, including flashings, in accordance with referenced requirements of Standard Design-Build Template PTS B30. Metal roofing repairs will be exempted from this manufacturer’s warranty requirement.

Manufacturer's warranty shall provide for full removal and replacement of failed, defective, and damaged roof system materials or installation workmanship in the event of water intrusion into or through the roof system, and repair of defects such as blistering, delamination, open seams, cracking, splitting, and excessive weathering. Warranty for corrective action shall not be limited in dollar value.

Provide minimum one-year contractor warranty against defects in installation workmanship in accordance with referenced requirements of Standard Design-Build Template PTS B30.

Contractor warranty shall provide for full removal and replacement of failed or defective workmanship and damaged materials, including sheet metal flashings and repairs to metal roofing.

B3050 ROOF SPECIFICATION AND DETAILING

All work, materials, installation and details shall be in accordance with Standard Design-Build Template PTS B30 and comply with all applicable Unified Facilities Guide Specification (UFGS) materials and installation requirements. UFGS's are referenced in PTS B30 and are available at www.ccb.org . Provide for complete rough carpentry, roof insulation, roof covering, sheet metal flashing, and other components necessary to complete the installation.

Utilize the applicable UFGS for development of the roof membrane specification. Edit for application to the specific project and compliance with the RFP. Provide complete rough carpentry, roof insulation, and sheet metal flashing specification sections coordinated and compatible with the membrane specification.

All details shall be in accordance with recommendations and guidelines of the National Roofing Contractors Association (NRCA) Roofing and Waterproofing Manual and Construction Details and as required by the RFP.

The roof system shall comply with the applicable requirements of the International Building Code.

http://www.ccb.org/

Project DKGV14-2027

Solicitation FA4418-15-R-0017 Attachment #19 Page 3 of 3

Refer to UFC 3-110-03, Roofing, and UFC 3-100-10, Architecture for additional technical requirements for the roof system to be installed.

B3060 ROOF DESIGNER REQUIREMENTS

Provide materials specification, installation requirements, and system detailing to include all flashings, penetrations, closures, corners, intersections, terminations, transitions, interfaces, joint, and lap conditions to provide for a watertight installation.

The Contractor shall utilize the services of a Registered Roof Consultant (RRC) certified by the Roof Consultants Institute, or a Registered Professional Architect or Professional Engineer either of which is knowledgeable and experienced in roof investigation, inspection, and design and specializes in roof design and roof consulting services. Consultant shall be thoroughly familiar with the field conditions and prepare the design or provide design review and approval prior to design acceptance by the Contracting Officer. The consultant shall validate in writing familiarity with field conditions and that the design for the project is complete, in accordance with the RFP, and provides for a complete and effective roof system solution and design.

B3070 QUALITY CONTROL PROGRAM

Contractor shall establish a quality control program to assure adherence to the RFP design and construction requirements and to report on the installation quality

F20 SELECTIVE BUILDING DEMOLITION

F2020 HAZARDOUS COMPONENT ABATEMENT

A survey for asbestos-containing material needs to be performed prior to performing demolition of any existing roofing materials. Ozone-depleting substances may be involved when removing and resetting rooftop HVAC units in support of the roofing replacement.

Prior to the start of the work, the contractor is required to use a SCDHEC-licensed hazardous materials inspector to inspect the work area, along with the designer of record and government representative, to address existing potentially hazardous components as part of the work. The contractor is required to provide a list of hazardous components, locations and quantities that must be addressed as part of the work.

Remove and dispose of the following hazardous materials: asbestos, ozone depleting substances.

Private Qualified Person (PQP) The Contractor is required to hire a PQP to ensure compliance with the approved work plans and perform independent inspections, testing and verification of the hazardous components work including: asbestos and ozone-depleting substances.

Asbestos Removal and disposal of asbestos-containing materials requires a license from SCDHEC, which the contractor shall be responsible for obtaining prior to beginning work on the project, and the use of properly trained and credentialed workers and supervision.

Ozone Depleting Substances (ODS) Remove and reset air conditioning equipment, which contains ODS.

Disposal All waste materials shall become the property of the Contractor and shall be transported, disposed of or recycled in accordance with:

-- End of Section --

CHAPTERS
1. PROJECT DESCRIPTION
2. ENGINEERING SYSTEMS REQUIREMENTS
1. PROJECT DESCRIPTION
2. ENGINEERING SYSTEMS REQUIREMENTS
Contractor shall establish a quality control program to assure adherence to the RFP design and construction requirements and to report on the installation quality
F20 Selective Building Demolition
F2020 Hazardous Component Abatement
Private Qualified Person (PQP)
Asbestos
Ozone Depleting Substances (ODS)
Disposal