CAPE CANAVERAL AIR FORCE STATION
Statement of Work
For
IDIQ Demolition, CCAFS, PAFB and Annexes
DATE: 21 March 2018
STATEMENT OF WORK
IDIQ Demolition at CCAFS, PAFB and Annexes
1. OVERVIEW
a. The work to be accomplished under the contract is located at various locations at Cape Canaveral Air Force Station (CCAFS), and Patrick Air Force Base (PAFB), and Annexes, Florida. The work involves the demolition of multiple facilities and their associated structures, pavement, utilities, fencing and site restoration.
b. The contractor shall provide all planning, including work plans and testing, labor, materials, equipment, design and supervision necessary for the Demolition and/or deconstruction of Buildings/ Facilities/ Infrastructure under the demolition contract.
All work shall be done in accordance with the requirements contained in the original contract specifications and any drawings that will be attached as required.
c. No alterations, additions, or deletions shall be made unless approval by the
Contracting Officer is obtained. The contractor shall thoroughly review the request for constructability and advice of possible problem areas prior to negotiations.
d. All work must be IAW Demolition Specifications unless expressed written permission is received from the Contracting Officer for any deviations. Under no circumstances is the Contractor to begin any work on the Delivery Order until the Contracting Officer issues a "Notice to Proceed".
e. Verify all quantities and dimensions. Note any deficiencies in the Government and customers drawings to the Contracting Officer prior to execution.
f. The Air Force is committed to effective environment compliance and stewardship activities for the Air Force lands to maintain access to the air, land, and water needed to maintain and improve Air Force mission capability. This commitment is accomplished by complying with federal, state, and local environmental statutes and regulations.
Compliance is accomplished under many Air Force programs.
2. SCOPE
The work under this contract consists of furnishing all labor, materials, equipment, and performing all operations in connection with the Building Demolition Contract.
Demolition and/or deconstruction work includes removal, transportation and disposal of all items to be demolished, as well as restoration of site demolition as indicated in specifications.
3. DESCRIPTION OF WORK
A. Demolition and/or deconstruction of indicated facility structures in its entirety including support structures, utilities, and site restoration. Foundations/footers shall be demolished 5’ below grade or as directed by the Government.
B. Coordinate with 45 CES environmental prior to construction start and ensure all environmental checks are completed prior to demolition beginning.
C. Where utilities are present - Disconnect and cap utilities and communication conduit as recommended by the Government or 5 feet from building perimeter if not specified.
D. Where electrical connections are present - Remove all electrical connections back to transformer. Coordinate outage and remove wires to low voltage side of transformer.
E. Contractor shall back fill with compactable materials all holes and other depressions resulting from demolition and/or deconstruction of buildings. Material shall be compacted per demolition specifications.
F. Site restoration: seeding and sodding is required for disturbed areas per direction from
Contracting Officer.
G. Demo Location(s) may require special clearance to access; the General Contractor, assigned to that specific project will escort and obtain work clearance.
NOTE: The above general outline of features of the work does not in any way limit the responsibility of the contractor to perform all work and furnish all labor, materials, and equipment required by the plans and specifications.
4. SALVAGE AND DISPOSAL RECORD KEEPING
Contractor shall maintain and submit weekly and at the completion of the project to the contracting officer a Disposal Log of all materials removed from the job site. This inventory shall include waste materials disposed in landfills and materials reused on the job, sold for salvage and recycled. At a minimum the Contractor shall identify the type of materials, material weight, disposition (landfill or recycle), receiving facility (name, address and phone number). Contractor will take possession of all recyclable material and provide the Government with weight slips for such material.
5. SITE INSPECTION
Contractors are expected to visit the areas of work and verify all conditions and dimensions prior commencement of any demolition work.
6. STORM PROTECTION
Should warnings of high winds or lightning be issued, the contractor shall take every practical precaution to minimize danger to persons, to the work, and to adjacent property.
These precautions shall include closing all openings, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.
7. INTERFERENCE WITH STATION OPERATIONS
Permission to interrupt any utility, communication, operational or traffic service or pattern shall be requested in writing at least 3 working days prior to the date of the desired interruption. The Contractor shall receive approval in writing from the Contracting Officer before the requested interruption may be put into effect. Any power outage shall be approved by the Contracting Officer in writing.
8. SAFETY
The Contractor shall perform all excavation according to Occupational Safety and Health Administration 1926 Subpart P.
9. SCHEDULING
The Contractor shall submit a schedule of proposed work to the Contracting Officer using AF Form 3064 for approval. The schedule shall show the proposed activities, including locations where work is planned and planned shutdown of equipment. All work sequencing and phasing is subject to the approval of the Contracting Officer.
10. SUBMITTALS
Five (5) copies of submittal information (or electronic PDF files of the submittal package) for all listed items must be submitted on AF Form 3000. Material submittals must be submitted as a complete package for each specification section, ready for the Contracting Officer's approval (Page 110-111 Demolition Specifications).
11. COORDINATION
Contractor shall organize weekly construction status meeting at location and time recommended by Contracting Officer.