Atch_9_Questions_ _Answers.pdf

PDF 144 KB Posted

Attached to
Painting IDIQ, Various Facilities Federal contract opportunity
Solicitation number
FA2521-15-R-0008
Issued by
Department of the Air Force Space Command

About this file

Attachment 9 - Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to Painting IDIQ, Various Facilities, newest first.
File Type Posted
Atch_5_Price_Schedule_-_Revision_1.xlsx XLSX spreadsheet
FA2521-15-R-0008-0003.pdf PDF
Atch_11_Site_Visit__Statement_of_Events.docx DOCX document
FA2521-15-R-0008-0002.pdf PDF
Atch_10_Installation_Access_List.docx DOCX document
FA2521-15-R-0008-0001.pdf PDF
Atch_9_Question_and_Answer_Template.docx DOCX document
Atch_6_Technical_Evaluation_Sample_Project_Form.docx DOCX document
Atch_4_GPP.pdf PDF
Atch_5_Price_Schedule.xlsx XLSX spreadsheet
Atch_3_Hazardous_Waste_Form.doc DOC document
Atch_2_Specifications_Addendum.pdf PDF
Atch_8_Davis_Bacon_Wage_Determination_8MAY15.pdf PDF
FA2521-15-R-0008 _Solicitation.pdf PDF
Atch_1_Specifications.pdf PDF
Atch_7_Past_Performance_Questionaire.docx DOCX document
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pg 1 of 1

FA2521-15-R-0008

QUESTIONS & ANSWERS

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) _Proposal Due Date__________________________

Question 1: On the solicitation form it gives a due date of July 15, 2015, however, on page 46 of the solicitation section L-II Proposal Preparation Instruction, it gives a date of July 10, 2015.

What is the due date?

Answer 1: The proposals are due on 15 Jul 15 at 2:00 PM EST. Amendment 0002 was issued to correct this in Section L-II.

RFP Section __________ Paragraph _________ SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) _Proposal Due Date__________________________

Question 2: _Since the walk through has been delayed from July 1 to July 8th, would the 45th Space Wing Contracting office consider moving the proposal due date to from

July 15th to July 22nd

Answer 2: No, there is no change in the proposal package due date. Complete proposals are due 15 Jul 15 at 2:00 PM EST.

RFP Section __52.228-1 BID GUARANTEE (SEP 1996) Paragraph ____b_____ SOW/Technical Specification/Drawings paragraph/page: FA2521-15-R-

0008,_Solicitation.pdf

Other (Specify) _Bid Bonds_________________________

Question 3: I’m in the process of obtaining the Bid Bond from my agent. Please clarify how performance and payment bonds will be issued after award. Are they on a task order basis or is there one bond to cover the total projected awards for the year?”

Answer 3: The bonds are per task order.