Atch_2_Specifications_Addendum.pdf

PDF 185 KB Posted

Attached to
Painting IDIQ, Various Facilities Federal contract opportunity
Solicitation number
FA2521-15-R-0008
Issued by
Department of the Air Force Space Command

About this file

Attachment 2 Specifications Addendum

View the file

Other files for this federal contract opportunity

Other files attached to Painting IDIQ, Various Facilities, newest first.
File Type Posted
Atch_5_Price_Schedule_-_Revision_1.xlsx XLSX spreadsheet
FA2521-15-R-0008-0003.pdf PDF
Atch_9_Questions_ _Answers.pdf PDF
Atch_11_Site_Visit__Statement_of_Events.docx DOCX document
FA2521-15-R-0008-0002.pdf PDF
Atch_10_Installation_Access_List.docx DOCX document
FA2521-15-R-0008-0001.pdf PDF
Atch_9_Question_and_Answer_Template.docx DOCX document
Atch_6_Technical_Evaluation_Sample_Project_Form.docx DOCX document
Atch_4_GPP.pdf PDF
Atch_5_Price_Schedule.xlsx XLSX spreadsheet
Atch_3_Hazardous_Waste_Form.doc DOC document
Atch_8_Davis_Bacon_Wage_Determination_8MAY15.pdf PDF
FA2521-15-R-0008 _Solicitation.pdf PDF
Atch_1_Specifications.pdf PDF
Atch_7_Past_Performance_Questionaire.docx DOCX document
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Maintain Paint, Various Facilities SXHT 14-1015

PROJECT TABLE OF CONTENTS

DIVISION 09 - FINISHES

09 67 23.15 CHEMICALLY RESISTANT ELECTROSTATIC DISSIPATIVE (ESD)

RESINOUS FLOORING

09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1 6/12/2015

SECTION TABLE OF CONTENTS

DIVISION 09 - FINISHES

SECTION 09 67 23.15

CHEMICALLY RESISTANT ELECTROSTATIC DISSIPATIVE (ESD) RESINOUS FLOORING

08/10

PART 1 GENERAL

1.1 DESCRIPTION

1.2 REFERENCES

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Test Reports

1.4.1.1 Joint Sealant

1.4.1.2 Thin Film ESD Flooring System

1.4.1.3 Moisture Reducing System (MRS) (Bid option)

1.4.1.4 Primer

1.4.1.5 Urethane Topcoat

1.4.1.6 Daily Inspection Report

1.4.2 Certificates

1.4.2.1 Work Plan

1.4.2.2 Inspector Qualifications

1.4.2.3 Flooring System Applicator Qualifications

1.4.2.4 Joint Sealant

1.4.2.5 Thin Film Flooring System

1.4.2.6 Warranty

1.4.3 Product Data

1.4.3.1 Joint Sealant

1.4.3.2 Thin Film Flooring System

1.4.3.3 Water-Based Alkaline Degreaser

1.5 DELIVERY, STORAGE, AND HANDLING

1.6 COATING HAZARDS

1.7 JOB SITE REFERENCES

1.8 PATCH TEST DEMONSTRATION

1.9 GOVERNMENT RIGHT'S TO INSPECT

1.10 PROTECTION AGAINST DAMAGE

PART 2 PRODUCTS

2.1 GENERAL REQUIREMENTS

2.2 COLORS

2.3 MARKING COATING PRODUCTS

2.4 JOINT SEALANT

2.5 THIN FILM FLOORING SYSTEM

2.5.1 Primer Coat

2.5.2 Urethane Topcoat

2.6 PREAPPROVED MATERIALS

2.7 Polypropylene Slip Resistant Additive

PART 3 EXECUTION

3.1 ACCESS TO SURFACES FOR PREPARATION AND COATING

SECTION 09 67 23.15 Page 1

3.2 DISTURBANCE OR REMOVAL OF COATINGS CONTAINING HAZARDOUS MATERIALS

3.3 COATING SAMPLE COLLECTION

3.4 PRODUCT MIXING

3.5 POT LIFE

3.6 AMBIENT CONDITIONS

3.7 TILE AND TILE ADHESIVE REMOVAL

3.8 JOINT MATERIAL REMOVAL, RE-SAW CUTTING, CRACK CHASING

3.9 GROUNDING

3.10 DEGREASING

3.11 COATING SYSTEM REMOVAL

3.12 SURFACE PREPARATION

3.13 JOINT TREATMENT

3.13.1 Install Backer Rod

3.13.2 Sealant Application

3.14 PRE-APPLICATION TESTING FOR CONTAMINATION

3.15 COATING APPLICATION

3.15.1 Moisture Reducing System (Priced as option)

3.15.2 Primer Application

3.15.3 Non-Skid Grit Broadcast

3.15.4 Application of Topcoats

3.15.4.1 First Topcoat

3.15.4.2 Second Topcoat

3.15.4.3 Markings, Striping, and Labeling

3.15.4.4 Striping and Grounding Rod Markings

3.15.4.5 Labeling

3.16 CURING

3.17 FIELD TESTS AND INSPECTION

3.17.1 Coating Inspector

3.17.2 Inspection

3.17.2.1 Daily Inspection Report

3.17.2.2 Inspection Logbook

3.17.2.3 Inspection Equipment

3.17.3 Testing for Moisture

3.17.4 Adhesion Testing

3.17.5 Conductivity

3.17.6 Testing for Contamination

3.17.7 Amine Blush Test

3.18 FINAL CLEANUP

-- End of Section Table of Contents --

SECTION 09 67 23.15 Page 2

SECTION 09 67 23.15

CHEMICALLY RESISTANT ELECTROSTATIC DISSIPATIVE (ESD) RESINOUS FLOORING

08/10

PART 1 GENERAL

1.1 DESCRIPTION

The thin film Electro-Static Dissipative (ESD) flooring system is appropriate for use in: aircraft maintenance hangars, equipment maintenance shops, and all other industrial floors where resistance to abrasion and fuel is required. An ESD flooring system should be selected for facilities that require the engineered control of electrostatic discharges (ESD) to prevent damage to electrically sensitive equipment and analytic processes, as well as to prevent fire or explosion when handling flammable liquids, powders, and gases.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C679 (2003; E 2009; R 2009) Tack-Free Time of Elastomeric Sealants

ASTM C884/C884M (1998; R 2010) Thermal Compatibility between Concrete and Epoxy-Resin Overlay

ASTM D1308 (2013) Effect of Household Chemicals on Clear and Pigmented Organic Finishes

ASTM D2240 (2005; R 2010) Standard Test Method for Rubber Property - Durometer Hardness

ASTM D2370 (1998; R 2010) Tensile Properties of Organic Coatings

ASTM D2621 (1987; R 2011) Infrared Identification of Vehicle Solids from Solvent-Reducible Paints

ASTM D2697 (2003; R 2014) Volume Nonvolatile Matter in Clear or Pigmented Coatings

ASTM D3335 (1985a; R 2014) Low Concentrations of Lead, Cadmium, and Cobalt in Paint by Atomic Absorption Spectroscopy

ASTM D3718 (1985a; R 2010) Low Concentrations of Chromium in Paint by Atomic Absorption Spectroscopy

SECTION 09 67 23.15 Page 3

ASTM D3925 (2002; R 2010) Sampling Liquid Paints and Related Pigmented Coatings

ASTM D412 (2006a; R 2013) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension

ASTM D4541 (2009; E 2010) Pull-Off Strength of Coatings Using Portable Adhesion Testers

ASTM D6237 (2009) Painting Inspectors (Concrete and Masonry Substrates)

ASTM D638 (2010) Standard Test Method for Tensile Properties of Plastics

ASTM D7234 (2012) Standard Test Method for Pull-Off Adhesion Strength of Coatings on Concrete Using Portable Pull-Off Adhesion Testers

ASTM F1869 (2011) Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI

ANSI/ESD S 7.1 (2006) Resistance Characteristics of Materials - Floor Materials

ANSI/ESD STM 97.1 (2006) Resistance in Combination with a Person

ANSI/ESD STM 97.2 (2006) Voltage Measurement in Combination with a Person

INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)

ICRI 03732 (1997) Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC-TU 2/NACE 6G197 (1997) Design, Installation, and Maintenance of Coating Systems for Concrete Used in Secondary Containment

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

FED-STD-595 (Rev C; Notice 1) Colors Used in Government Procurement

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.1000 Air Contaminants

29 CFR 1910.134 Respiratory Protection

29 CFR 1926.59 Hazard Communication

SECTION 09 67 23.15 Page 4

29 CFR 1926.62 Lead

UNIFIED FACILITIES CRITERIA (UFC)

UFC 3-575-01 (2012) Lightning And Static Electricity Protection Systems

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Some, or all, submittal requirements may be waived at the discretion of the Contracting Officer, depending on the requirements unique to a particular project. Contractor requests to waive any submittal requirements must be submitted to the Government in writing for approval.

Contractor shall submit all listed documents, except to the extent that a waiver is granted by the Contracting Officer. Provide required submittals to Government within seven (7) days after receiving Notice-To-Proceed, and obtain Contracting Officer's approval prior any construction activity.

Government's approval of submittals is administrative in nature and shall not be construed as a waiver or change of any specified requirements. It is the responsibility of the Contractor and their quality control personnel to ensure submittals meet the requirements of this standard.

SD-01 Preconstruction Submittals

Plan for Ensuring Compliance;G

Grounding System Plan;G

Striping and Marking Plan;G

SD-04 Samples

Joint Sealant; G

Thin Film Flooring System; G

Polypropylene Beads; G

Colors; G

SD-06 Test Reports

Joint Sealant; G

Thin Film Flooring System; G

Moisture Reducing System (MRS); G

Primer; G

Urethane Topcoat; G

SECTION 09 67 23.15 Page 5

Polypropylene Beads; G

Patch Test Demonstration; G

Daily Inspection Report; G

Adhesion Testing; G

MVE Testing Results; G

Conductivity Testing Report; G

SD-07 Certificates

Work Plan; G

Flooring System Applicator Qualifications; G

Joint Sealant; G

Thin Film Flooring System; G

Warranty; G

SD-08 Manufacturer's Instructions

Joint Sealant; G

Thin Film ESD Flooring System; G

Water-Based Alkaline Degreaser; G

SD-11 Closeout Submittals

Inspection Logbook; G

1.4 QUALITY ASSURANCE

1.4.1 Test Reports

1.4.1.1 Joint Sealant

Submit test results that confirm sealant complies with the requirements of Table 1a. Samples must have been tested within the last three years.

1.4.1.2 Thin Film ESD Flooring System

Submit test results that confirm the ESD thin film flooring system complies with the requirements of Table Ib. Samples must have been tested within the last three years.

1.4.1.3 Moisture Reducing System (MRS) (Bid option)

Submit test results that confirm the MRS complies with the systems listed in Table II. Obtain Government and manufacturers approval if proposing to apply product other than that which is preapproved.

SECTION 09 67 23.15 Page 6

1.4.1.4 Primer

Submit test results that confirm the primer complies with the requirements of Table 1c. Samples must have been tested within the last three years.

1.4.1.5 Urethane Topcoat

Submit test results that confirm the urethane topcoat complies with the requirements of Table 1d. Samples must have been tested within the last three years.

1.4.1.6 Daily Inspection Report

Submit one copy of the daily inspection report to the Contracting Officer within 12 hours of the date recorded.

1.4.2 Certificates

1.4.2.1 Work Plan

Submit schedule to complete work within approximately twelve (12) consecutive days. Submit a written plan describing in detail all phases of coating operations. Address work sequencing, surface preparation, flooring system application, recoat and cure time projections, as well as how each step will be controlled, tested, and evaluated. Address safety measures, work scheduling around weather, and record keeping. Assign one supervisor to the job who is to remain at the site throughout all phases of work and who is to act as the contractor's primary point of contact. Identify this person in the submitted schedule.

1.4.2.2 Inspector Qualifications

Submit the name, address, telephone number, FAX number, and e-mail address of the QC Specialist/Inspector. The Coating Inspector(s) shall be an independent third party, hired directly by the prime construction Contractor, as an integral part of the prime construction Contractor's Quality Control Organization. Each assigned inspector shall be a NACE Level 3 Certified Coating Inspector. The inspector(s) shall have no business relationships (Government, partner, operating officer, distributor, salesman, technical representative, or inspector) with any sub-contractors involved in this project; or with any Manufacturers, suppliers, or installers for any material or equipment provided as part of this project.

1.4.2.3 Flooring System Applicator Qualifications

Minimum requirements for the installation contractor are as follows:

Completed three or more jobs within the past two years applying the specified materials to concrete surfaces in which the total area exceeds 200,000 square feet. Submit documentation listing location of work, point of contact at job site, total square footage of applied materials, listing of both materials and equipment used, and validation from coating manufacturer documenting quality of materials purchased per job for work totaling 200,000 square feet within the past two years. In addition to the above requirements, be certified by the material manufacturer(s) to install the submitted coatings and sealant. Submit copy of certificates.

SECTION 09 67 23.15 Page 7

1.4.2.4 Joint Sealant

Submit literature documenting the past performance of the sealant's use in aircraft maintenance shops. Minimum requirements are two or more maintenance shops with joint work totaling 10,000 linear feetwhere the sealant has performed for two years with less than 1 percent combined sealant failures and defects. List location of shops, total linear feet of sealant applied per shop, shop point of contact, date sealant was applied, and the name of the installed sealant material.

1.4.2.5 Thin Film Flooring System

Submit literature documenting the past performance of the coating system's use in aircraft maintenance shops and over floors with high rates of Moisture Vapor Emission (MVE). Minimum requirements are two or more aircraft maintenance shops totaling 34,000 square feet where the coating system has performed for two years with less than 0.05 percent combined premature coating failures, material defects and surface discoloration; no more than 0.03 percent discoloration from aviation chemicals, tire plasticizers, and UV exposure. Provide a minimum of two additional case histories where successful installation occurred on floor slabs with no less than 3.5 pounds moisture per 24 hours, 1000 square feet. List location of shops, total coated area per shop, shop point of contact, date coating system was applied, successful installation to concrete with high MVE, and the names of the installed coating materials.

1.4.2.6 Warranty

Contractor shall provide the Government with a single-source, unconditional three-year labor and materials warranty fully covering any defects in material or workmanship. Warranty period shall be on a per task order basis and starts upon Government acceptance of completed work. It shall be the Contractor's responsibility to negotiate, obtain and benefit from any warranties that may be available to the Contractor from the product Manufacturers, subcontractors, or other suppliers that are used on the project.

In the event that warranty requirements conflict with other contract documents, the warranty provision that is most favorable to the Government shall prevail.

Contractor shall be responsible for the satisfactory repair of all defects discovered during the warranty period. Warrantable defects include, but are not limited to: Any form of disbondment (i.e., blistering, peeling, or flaking); discoloration; premature loss of gloss or color; or any other deterioration or change in condition that has a significant adverse impact on the performance, serviceability, or appearance of the coating, or on any other product or service furnished by the Contractor on the project.

Contractor shall make repairs within 120 days after notification by the Government, unless the Government's operations or schedule limit access to the work areas and require that the repair work be deferred. At the Government's sole discretion, repair work may be deferred for a period up to 18 months.

Contractor shall be responsible for all defects discovered and reported within the warranty period, regardless of whether they can be repaired during the warranty period. Inspection and repairs shall be made in the presence of the Government. Repair and warranty work shall be subject to the requirements of the applicable specification. Contractor shall submit

SECTION 09 67 23.15 Page 8 a Written Repair Plan to the Government for making repairs in accordance with the requirements of this Technical Guideline and any written recommendations or instructions provided by the Manufacturer. All costs associated with warranty repairs shall be borne by the Contractor.

1.4.3 Product Data

1.4.3.1 Joint Sealant

Submit manufacturer's printed instructions to include detailed application procedures, minimum and maximum application temperatures, and curing procedures. In accordance with 29 CFR 1926.59, include Material Safety Data Sheets (MSDS) for the sealant to be used at the job site.

1.4.3.2 Thin Film Flooring System

Submit manufacturer's printed instructions to include detailed mixing, minimum and maximum application temperatures, acceptable atmospheric and/or interior climatic conditions, application procedures, curing procedures, and procedures for maintenance cleaning of flooring system. Provide explicit instructions detailing surface preparation, recoat windows and remedial actions in case recoat windows are missed, and, if applicable, solvent-wiping between coats with acceptable types and grades of solvents.

In accordance with 29 CFR 1926.59, include MSDSs for the coatings to be used at the job site.

Also include complete instructions for surface preparation and application prepared by the coating manufacturer, any brochures, Manufacturer's Product Data Sheets, and bulletins describing coating properties.

1.4.3.3 Water-Based Alkaline Degreaser

Submit manufacturer's printed instructions to include detailed mixing, rate of dilution, application procedures, and rinsing procedures. In accordance with 29 CFR 1926.59, include MSDSs for the water-based alkaline degreaser to be used at this job site.

1.5 DELIVERY, STORAGE, AND HANDLING

Store coatings and sealant in spaces with temperatures from 40 degrees F to 75 degrees F. Inspect materials on site for damage prior to use. Return to manufacturer packaged materials in dented, rusty, or leaking containers. Conduct testing by manufacture of returned materials with an expired shelf life and if compliant, reissue a shelf life extension.

1.6 COATING HAZARDS

Ensure that employees are trained in all aspects of the safety plan.

Follow the coating manufacturer's written safety precautions throughout mixing, application, and curing of coatings. Comply with respiratory protection requirements in 29 CFR 1910.134 and safe levels of airborne contaminants in 29 CFR 1910.1000.

1.7 JOB SITE REFERENCES

Make available to the Contracting Officer at least one copy each of ASTM D7234, ASTM D6237, SSPC-TU 2/NACE 6G197, and ICRI 03732, including replica standards ICRI 03732 CSP 1 through CSP 9, at the job site.

SECTION 09 67 23.15 Page 9

1.8 PATCH TEST DEMONSTRATION

Prior to the submitted flooring system's approval, apply the complete coating system to a 15 foot by 15 foot (4.6 meters by 4.6 meters) square section of concrete, and include at least 10 linear feet (3 meters) of expansion joint and a grounding point in the center. The test will include all phases of coating system application: surface preparation (cleaning, scarification); seam repair; and application of each coat. Each coat will be cured for the recommended time and evaluated for application properties, curing, and film properties. The total system will be cured 10 days prior to test and evaluation. After 10 days of curing, the final coat will be evaluated for:

Adhesion between coats and to the substrate surface;

Film properties;

Color;

Reflectance;

Chemical resistance spot test;

Conductivity;

Grit concentration (particles/square foot).

Slip Resistance (Suitable for expected operations, approved by Contracting Officer)

If adhesion testing produces cohesive failures within the concrete, no less than 40 mils concrete removed over 95 percent of each pull-off coupon, and/or adhesion more than400 psi, patch test adhesion is acceptable. If concrete surface preparation was insufficient, apply an additional coating system patch to properly prepared concrete followed by the above adhesion testing. If the coated area fails any one of the criteria evaluated for, the coating system should be rejected. Apply a patch of the new coating system and subject patch to the above requirements prior to approval. If customer dislikes non-skid grit application, adjustments to the specifications can be made. Grit coarser than #36 alumina is not recommended.

1.9 GOVERNMENT RIGHT'S TO INSPECT

The Government reserves the right, but has no duty, to assign field representatives, including a NACE Certified Coating Inspector, to monitor any or all of the work and enforce the requirements of the specifications as deemed necessary. The Government shall have the authority to stop work due to any non-conforming work.

Schedule and coordinate work with the Government to allow for timely and unobstructed inspections by the Government. Provide safe access for the Government to conduct inspections, including use of the Contractor's scaffolding, rigging, lifts, lighting, ventilation, or other equipment necessary to safely access work areas.

Any inspections or waiver of inspections by the Government shall not relieve the Contractor of full responsibility for quality control and compliance with these specifications.

The Contractor shall be responsible for the satisfactory repair of any areas found to be defective, regardless of whether any inspections were performed by the Government.

SECTION 09 67 23.15 Page 10

1.10 PROTECTION AGAINST DAMAGE

Coordinate with and obtain approval from the Government regarding which items are to be removed and which may remain in place with suitable protection.

Protect from damage any hardware remaining affixed to the floor, such as studs or inserts.

Securely store removed items, including hardware, and reinstall to fully operational condition prior to completion of the work. Mark, map, photograph, and detail items as necessary to ensure replacement of each item in the original location and position.

Protect all adjacent facilities, equipment, vehicular traffic, property, and any other areas, items or surfaces that are not specified to receive coatings, from any damage due to Contractor's operations. Protection shall include specific measures to prevent any damage caused by surface preparation and coating activities.

Give special attention to the protection of electric motors, centrifugal blowers, HVAC, electrical equipment, mechanical equipment, hydraulic components, enclosures, cabling and other sensitive or fragile equipment and surfaces.

If damage should occur, make repairs that are satisfactory to the Government in a timely manner.

PART 2 PRODUCTS

2.1 GENERAL REQUIREMENTS

Furnish only new, freshly stocked, materials and products obtained directly from the Manufacturer, or their authorized distributors. Leftover stock materials and products from prior projects shall not be used. Upon request, provide receipts or other evidence satisfactory to Government to prove compliance with this requirement.

Supply multi-component products in prepackaged kits so that the contents of the individual containers in the kit can be combined to provide a properly proportioned mix of the final product. The kits may be provided in various sizes to accommodate the typical mix quantity requirements.

Products shall be suitable for application without requiring any alteration or modification at the jobsite. Ensure all products are within shelf life at time of use.

Products, including pigments added for color, shall not contain asbestos, lead, cadmium, chromium (no more than 0.01 percent by weight of mixed paint), or other regulated substance that, when removed, would result in hazardous waste or regulated abatement operations.

2.2 COLORS

Submit color proofs of selected colors using actual paint material. Obtain Government approval of all color proofs prior to application of finish coats.

For all markings, including striping and labeling, the following Federal

SECTION 09 67 23.15 Page 11

Standard Colors shall be used:

White - 37925 Red - 31136 Yellow - 33655 Black - 37038

2.3 MARKING COATING PRODUCTS

Coating used for striping and labeling must be compatible with the reflective coating systems. Traffic marking paints are not acceptable.

Striping coatings should be chemical-resistant. Moisture-cured urethane marking coatings are acceptable.

2.4 JOINT SEALANT

Formulate the joint sealant to exhibit the properties as listed in Table Ia.

2.5 THIN FILM FLOORING SYSTEM

A three-coat industrial flooring system consisting of optional MRS, primer, a two component aliphatic urethane intermediate coat that incorporates grit to provide slip resistance, and one additional urethane topcoat. Apply the coating system at a Dry Film Thickness (DFT) ranging from 12 to 21.4 mils and contain a broadcast of aluminum oxide non-skid grit. Formulate the complete flooring system to exhibit the properties as listed in Table Ib.

Additional requirements for primer coat and urethane topcoat are listed in the following sub-paragraphs.

2.5.1 Primer Coat

In addition to the requirements of the thin film flooring system, formulate the primer coat to exhibit the properties as listed in Table Ic.

2.5.2 Urethane Topcoat

In addition to the requirements of the thin film flooring system, formulate the urethane top coat to exhibit the properties as listed in Table Id.

2.6 PREAPPROVED MATERIALS

Table II contains a listing of vendors with "preapproved materials."

SECTION 09 67 23.15 Page 12

Table II

Preapproved Materials*

Manufacturer Products

General Polymers 154 Caldwell Drive Cincinnati, OH 1-800-543-7694

MRS: FasTop MVT (Bid Option)

Primer: 3524

Intermediate: 4618E

Topcoat: 4618E

Sika Industrial Flooring 201 Polito Avenue Lyndhurst, NJ 07071 1-800-933-7452

MRS: EpoCem 81 (Bid Option)

Primer: Sikafloor 100 ESD

Intermediate: Sikafloor 200 ESD Polyol Topcoat: Sikafloor 340 ESD Polyol

(*) Other products may meet specification requirements, Up to specification's date of issue, preapproved materials met specification requirements. It is the user's responsibility to confirm preapproved material formulations have not changed and specification requirements will be met.

(1) ECO-CRE primer is to be used on floors with heavy Skydrol use.

(2) Polyspec T-2235SL sealant may be used.

Table III

ESD Floor Coating Criteria

Property Value Test method

Point to Point (Minimum) 1 megaohm EOS/ESD - DS 7.1 at 100V

Point to Point (Minimum) 1 gigaohm

Point to Ground (Minimum)

1 megaohm EOS/ESD - DS 7.1 at 100V

Point to Ground (Minimum)

1 gigaohm

Body Voltage Generation (Maximum)

1 KV AATCC/ANSI 134 for maximum and minimum voltage

Static Decay 1 second Federal Test Method Standard 101 C Method

SECTION 09 67 23.15 Page 13

2.7 Polypropylene Slip Resistant Additive

Polypropylene grit shall be Hercoflat 1200, or Government approved equal, and premixed into the first urethane coat before application.

Coordinate and select grit size and distribution according to the specific operational requirements of each area. Confirm, and obtain Government approval of the degree of slip-resistance provided during the mock-up and patch testing process. Submit sample of polypropylene beads to government for approval. Submit documentation from floor coating manufacturer that the intended rate of polypropylene bead inclusion will not alter the ESD properties of the final floor installation.

PART 3 EXECUTION

3.1 ACCESS TO SURFACES FOR PREPARATION AND COATING

Ancillary items such as cables, conduits, brackets, panels, or other minor equipment that conceal surfaces scheduled for preparation and coating shall be partially or completely removed, as appropriate, and reinstalled after coating. Do not disassemble or remove any structural members or components, unless required by other sections of the contract documents.

Coordinate with and obtain approval from the Government regarding which items require removal for access. This requirement is in addition to any removal that may be required for protection of items not to be prepared or coated. Use qualified technicians to remove any appurtenances from structural framing prior to starting any preparation or coating work.

Securely store any removed items, including hardware, and reinstall to fully operational condition prior to completion of the work. Mark, map, photograph, and detail items as necessary to ensure replacement of each item in the original location and position.

3.2 DISTURBANCE OR REMOVAL OF COATINGS CONTAINING HAZARDOUS MATERIALS

The contractor shall be responsible for testing of existing surfaces, worker exposures, emissions, and waste streams to confirm the presence or absence of any hazardous or regulated materials in all work areas.

Implement appropriate processes and controls to ensure compliance with any federal, state, and local regulations that may apply.

Surfaces scheduled for surface preparation and over-coating may include areas that contain lead. Develop and submit a plan for ensuring compliance with Section 02 83 13.00 30 Lead in Construction, and 29 CFR 1926.62.

3.3 COATING SAMPLE COLLECTION

The Contracting Officer and QC Manager shall witness all material sampling.

Notify the Contracting Officer a minimum of three days in advance of sampling. Obtain liquid samples of each component of primer and topcoat by random selection from sealed containers and in accordance with ASTM D3925.

Samples may be either individual cans of liquid material or 1.0 quart quantities of properly mixed, extracted, and sealed liquid material.

Identify samples by designated name, specification number, batch number, project contract number, sample date, intended use, and quantity involved.

When the applied coating system has met the requirements defined in the

SECTION 09 67 23.15 Page 14

Article entitled "ADHESION TESTING," return coating to the installation contractor for proper disposal.

3.4 PRODUCT MIXING

Mix all products in strict accordance with manufacturer's written instructions. Provide all equipment required or recommended by product instructions. Keep copies of product data sheets with mixing instructions available at mixing station.

Thoroughly blend individual components prior to mixing multi-component products. Do not mix partial kits, or alter mix ratios of multi-component products.

Mix materials in same temperature and humidity conditions specified in paragraph Handling, Delivery, and Storage. Allow mixed material to stand for the required induction time based on its temperature.

Use products as packaged without any jobsite alteration or modification, unless required by the manufacturer's published product instructions. Do not add thinners, solvents, pigments, or other additives to any product unless required by the manufacturer's published instructions or this specification.

Coating materials shall be thoroughly mixed prior to application with a mechanical mixing instrument that will not induce air into the coating, such as a Jiffy Mixer, manufactured by the Jiffy Mixer Company, Inc., San Francisco, CA, or approved equal. The mixer shall be powered by an air motor or an explosion-proof electric motor.

Coating materials shall be agitated as necessary during application to maintain uniform suspension of solids. Continuous rapid agitation shall be avoided. Ensure compliance with any required induction times prior to application of products.

All mixing operations shall be performed over an impervious surface with provisions to prevent runoff to grade of any spilled material.

The mixed coating material shall be strained through a 30- to 60-mesh screen prior to application.

Maintain a written daily batch log to record the batch numbers and product information for all coating materials. As a minimum, the log shall include: date product was used, the Manufacturer, product identification, quantity used, description of item or area where applied, and batch number. Submit written log to the Government, or their designated representative, on a weekly basis.

When requested by the Government, provide batch samples of any materials that are used throughout the progression of the work.

3.5 POT LIFE

Apply mixed multi-component products within stated pot life for each product. Add all required solvent at time of mixing. Do not add solvent to extend pot life. Usable pot life depends on the temperature of the material at the time of mixing and the sustained temperature at the time of application. Other factors such as the shape of the container and volume of mixed material may also affect pot life. High humidity at time of mixing

SECTION 09 67 23.15 Page 15 and application shortens pot life of the polyurethane topcoat material.

3.6 AMBIENT CONDITIONS

Ambient conditions shall comply with the Coating Manufacturer's requirements and as specified herein. In cases of a conflict, the more stringent requirement shall apply.

No coating shall be applied when the temperature or humidity is outside limits recommended by the coating manufacturer. No coatings shall be applied to wet or damp surfaces.

Application of the first coat to bare concrete shall be when the concrete surface temperature is constant or falling (typically afternoon). Surface temperatures for the first coating to bare concrete shall be at least 10 degrees F above the dew point and not falling during application and throughout initial care. Do not apply coating to bare concrete when there is potential for surface temperature to increase during application or initial cure.

The air temperature shall be between 60 degrees F (16 degrees C) and 100 degrees F (38 degrees C).

Surface temperatures must be between 60 degrees F (16 degrees C) and 100 degrees F (38 degrees C). Surface temperatures shall be at least 8 degrees F (3 degrees C) above the dew point and not falling during coating application and throughout initial cure.

No coating shall be applied when the relative humidity is above 85 percent or as specified in the Coating Manufacturer's product data sheet.

3.7 TILE AND TILE ADHESIVE REMOVAL

Remove 100 percent of tile employing one or more of the following techniques: chipping, scraping, sanding, scarification, high-pressure water, and various hand tools. Remove 100 percent of the tile adhesive using solvents and power scrubbing. Remove residual contamination using hot potable water under a minimum of 4,000 psi. Resulting surfaces shall appear clean and display the gray color of concrete.

3.8 JOINT MATERIAL REMOVAL, RE-SAW CUTTING, CRACK CHASING

Remove 100 percent of the existing material in all joints including material bonded to joint walls and base. Rigid material may require the use of saw cutting equipment to remove. Joints may be widened up to 1/8 inch when re-saw cutting. Chase concrete cracks identified for repair and open to a minimum depth of 1/2 inch below crack surface with smooth vertical walls.

3.9 GROUNDING

Install a grounding system, using copper tape, embedded #18 bare copper wire (embedded in cut channels), or other suitable method to ensure that each 1,000 square foot of coated surface area is directly connected to a facility grounding point. Install grounding points as required. Existing metal floor joints, equipment bases and steel columns or posts may potentially be used as grounding points if they have been electrically tested to verify continuity with an earth ground. Submit a detailed grounding system plan, including product mfg. requirements, connection

SECTION 09 67 23.15 Page 16 details, and drawings or sketches that illustrate the exact placement of the system and how connections will be made. The submittal shall include the product manufacturer's written concurrence with the grounding system plan. The coating system shall be applied in direct, uninterrupted, contact with the properly prepared grounding points. The connection of the grounding system to the ground connection points shall be performed by a licensed electrical engineer.

3.10 DEGREASING

On both coated and uncoated concrete, degrease entire floor by scrubbing using a solution of hot potable water, 120 degrees F to 170 degrees F, and a concentrated water-based alkaline degreaser. Perform two complete degreasing cycles on the entire floor surface. Allow solution to soak into surfaces prior to scrubbing and remove using hot potable water under a minimum of 4,000 psi. Rinsing is complete when the rinse water appears clear. If the industrial detergent is not biodegradable, collect all rinse water and dispose as hazardous waste. Squeegees and shop vacuums may be used to collect pooling rinse water. Fans may be used to aid drying of floor surfaces.

3.11 COATING SYSTEM REMOVAL

Remove 100 percent of the existing coating system employing one or more of the following techniques: shot blasting, chipping, scraping, sanding, scarification, high pressure water blasting, and various hand tools. The use of impact tools such as scabblers may be used to remove unsound epoxy mortar flooring systems. In general, a coating system cannot be completely removed by shot blasting and, to attain 100 percent coating removal, and requires a combination of the above techniques.

3.12 SURFACE PREPARATION

Shot blast entire floor to produce a level of coarseness similar to ICRI 03732 CSP 3. Overlap each pass of shot blasting by 1/4 inches to 1/2 inches. Add new shot to shot blasting equipment prior to blasting.

Prepare surfaces inaccessible to shot blasting, base of perimeter walls and under secured equipment, using diamond disk grinding and/or light scarification to produce a level of coarseness similar to ICRI 03732 CSP 2 and/or ICRI 03732 CSP 4, respectively. Resulting surfaces shall appear clean and contain the appropriate level of surface coarseness. If the resulting level of cleanliness cannot be determined, place numerous drops of water on surfaces that appear contaminated. If the water drops soak into concrete, the surfaces are free of hydrocarbon contamination (oils, grease, skydrol). If the water drops bead up and do not flatten out, surfaces require additional degreasing as detailed in the Article entitled "DEGREASING." Shot blasting coarse concrete and/or broom finished concrete can produce a level of coarseness similar to ICRI 03732CSP 5: employ a best effort attempt to minimize over shot blasting of coarse concrete. If coarse concrete is encountered, shot blasting to a level of coarseness similar to ICRI 03732 CSP 5 is acceptable: however, extremely coarse concrete can require resurfacing prior to the flooring system's installation. Sweep, vacuum, and run a high powered magnet over all surfaces to be coated, including joints.

3.13 JOINT TREATMENT

Use the "Conventional Sealed Joint" as detailed in Figure 1 of SSPC-TU 2/NACE 6G197 to seal joints. Employ measures to reduce

SECTION 09 67 23.15 Page 17 contamination from equipment and foot traffic. Limit floor access to essential contractor personnel. Confirm joint surfaces are sufficiently clean.

3.13.1 Install Backer Rod

Install a continuous length of round, closed-cell polyethylene backer rod into each joint using a backer rod tool. For 1/2 inch, 3/8 inch, and 1/4 inch wide joints, place backer rod to a depth of 3/8 inch (depth equals the distance from the concrete's surface to the highest point on the backer rod). For joints greater than or equal to 3/4 inch width, place backer to a depth of 5/8 inch below the concrete's surface. Fit backer rod tight between joint walls (30 percent compression). Remove and reinstall all backer rod that is installed using either the incorrect size (loose fit) or at the incorrect depth. Following backer rod installation, apply painter's tape to surfaces adjacent joints to protect from sealant.

3.13.2 Sealant Application

Apply sealant directly into joints using a bulk-caulking gun. At room temperature, the resulting sealant application shall exhibit a concave recess between 1/8 inch to 1/16 inch below the concrete's surface. Remove and reapply cured sealant remaining either flush or greater. Following sealant application, remove painter's tape and sealant drips on concrete surfaces. Cure sealant a minimum of 24 hours, prior to the application of coatings.

3.14 PRE-APPLICATION TESTING FOR CONTAMINATION

Spot check surfaces for oil/grease contamination using the water break test. At a rate of 5 tests per 1000 square feet, place one to two drops of water onto surfaces and observe for beading. Test all other surfaces that show visible signs of potential contamination. Apply additional degreasing techniques to surfaces displaying water beading in accordance with the Article entitled "DEGREASING."

3.15 COATING APPLICATION

Coat prepared and approved surfaces before the occurrence of any contamination.

All surfaces shall comply with the specified level of cleanliness at the time of coating application.

Vacuum flooring space one additional time immediately prior to coating application and mark all joints.

Apply and cure all products in strict accordance with manufacturer's written instructions, using good practices and technique as required to achieve optimal results.

Only utilize methods and application equipment that are recommended by the Manufacturer in writing.

The application and handling characteristics of all products will vary. To obtain optimum performance, adequate written instructions from the manufacturer are essential and must be closely followed in conjunction with the requirements defined herein.

SECTION 09 67 23.15 Page 18

Solvents used for cleanup shall be as recommended on the product data sheet and must be a product provided by the Manufacturer unless alternate written recommendations are provided in writing by the product Manufacturer.

The first coat application to bare concrete surfaces shall only be applied after the concrete surface has reached its maximum daily temperature, which usually occurs in the early afternoon. Do not apply coatings to bare concrete surfaces when the temperature is expected to increase. This is to help prevent pin-holing caused by expansion of air in the porous concrete surface.

3.15.1 Moisture Reducing System (Priced as option)

Apply moisture reducing system to flooring space according to manufacturers instructions. Strict adherence to minimum thickness is required for successful coating performance.

3.15.2 Primer Application

Apply primer to flooring space at 7.0 mils to 15.0 mils Dry Film Thickness (DFT). If the prepared concrete resembles an ICRI 03732 CSP 3 surface, apply the primer at a minimum of 7.0 mils DFT. If the prepared concrete resembles an ICRI 03732 CSP 5 surface, apply the primer at a maximum of

15.0 mils DFT. The previously applied sealant may be lightly coated.

3.15.3 Non-Skid Grit Broadcast

Broadcast non-skid grit at a rate of 1.5 pounds per 100 square feet into the first urethane top coat and backroll. Map floor into 600 square foot sections where 9.0 pounds of non-skid grit is pre-weighed, placed into clean buckets and used in its entirety per marked 600 square foot section.

3.15.4 Application of Topcoats

Apply two coats of urethane topcoat to the epoxy primer and broadcast non-skid grit directly into the first urethane topcoat.

3.15.4.1 First Topcoat

Apply a full coat of the urethane topcoat at a spreading rate from 2.5 to

3.2 mils Dry Film Thickness (DFT). Stripe coat perimeter edges and around equipment footings. Monitor and record a minimum of one Wet Film Thickness (WFT) reading per 600 square feet of floor surface. Sealant is to be lightly coated. Monitor and record a minimum of one WFT reading per 600 square feet of floor surface prior to broadcasting non-skid grit. When the correct WFT has been applied per 600 square feet of area, immediately and evenly broadcast non-skid grit directly into the second topcoat of urethane and backroll in two directions. Test the adhesion of the thin film flooring system in accordance with the article entitled "ADHESION TESTING".

3.15.4.2 Second Topcoat

Apply a second coat of the urethane topcoat at a spreading rate of 2.5 to

3.2 mils DFT. Stripe coat perimeter edges and around equipment footings.

Monitor and record a minimum of one WFT reading per 600 square feet of floor surface prior to broadcasting non-skid grit. When the correct WFT has been applied per 600 square feet of area, immediately and evenly broadcast non-skid grit directly into the second topcoat of urethane and backroll in

SECTION 09 67 23.15 Page 19 two directions. Test the adhesion of the thin film flooring system in accordance with the Article entitled "ADHESION TESTING."

3.15.4.3 Markings, Striping, and Labeling

Marking coatings must be compatible with the reflective coating systems or ESD/conductive systems. Traffic marking paints are not acceptable.

Markings coatings should be chemical-resistant, but moisture-cured urethane marking coatings generally are acceptable.

When the second topcoat is within its recoat window, apply the yellow and black striping at a minimum thickness of 3.0 to 4.0 mils DFT, completely hiding the top coat, in one coat. If insufficient hiding occurs, apply one additional coat. Use solvent resistant tape to protect the floor coating against stripe coat bleed. A thin clear coat of urethane may be required to prevent stripe coat bleed prior to the full application of the colored stripe coat. If the final coat has dried more than 48 hours, buff the area to be marked with No. 1 steel wool or No. 100 sandpaper to provide a good bond. Wipe areas clean before coating. Apply grounding rod markings using similar procedures.

3.15.4.4 Striping and Grounding Rod Markings

Replacement of striping, labeling, and marking is considered part of the flooring system and is not a separate cost item. Mark, map, measure, photograph, and detail all striping, labeling and markings as necessary to ensure replacement of each in their original location and position, with matching colors and sizing, and consistent with the requirements for each particular facility. Submit documentation and photos of striping, labeling, and marking locations prior to surface preparation activities.

Unless specified otherwise, grounding rod markings shall be according to UFC 3-575-01. Submit detailed striping and marking plan, including sketches of layout, marking sizes, marking products, and application details for Government approval.

3.15.4.5 Labeling

Replace existing aluminum caution placards with stenciling that match existing size, wording and color. See Government drawings for caution placard details.

3.16 CURING

Cure installed materials to display performance equal to manufacturer's product literature. Remove and reapply improperly cured material.

3.17 FIELD TESTS AND INSPECTION

3.17.1 Coating Inspector

Immediately report to the Government any deviation from the specified requirements.

Provide multiple inspectors if necessary to ensure adequate quality control coverage of all work being performed. Maintain a ratio of production workers to inspectors that is less than 12:1.

The Coating Inspector(s) shall be considered a QC Specialist. The Coating Inspector's primary responsibility shall be to assure compliance with

SECTION 09 67 23.15 Page 20 specified requirements. The Coating Inspector(s) shall be present full-time during all pre-preparation testing, surface preparation, paint application, initial cure of the paint, paint repair work, and project completion activities. The Coating Inspector(s) shall provide complete documentation of conditions and occurrences on the jobsite, facilitate timely reporting of any technical issues to Government Representative and be aware of conditions and occurrences that are potentially detrimental to the performance of the coating system. There will be no other duties required of the coating inspector.

3.17.2 Inspection

Document weather conditions, job site occurrences, and report conditions and occurrences potentially detrimental to the flooring system. Prepare a project reference sheet outlining all requirements, tests, test methods, and evaluation criteria, and hold regular meetings with contractor personnel, including shot blasting operators and applicators, to review requirements/evaluation criteria for upcoming work prior to execution. At the start of coating operations and every 1.0 hour following until daily work is complete, record air temperature, substrate temperature, and relative humidity. Following the application of each coat, inspect surfaces for improperly cured material, blisters, inadequate and/or excessive coating thickness, and other defects. Document each inspection, test, non-compliant area, and location of each non-compliant area. List method of evaluation, evaluation criteria, areas requiring rework, and all other pertinent observations.

3.17.2.1 Daily Inspection Report

Submit to the Contracting Officer the daily inspection reports completed each day when performing work under this Section. Use Appendix X1 "Inspection Checklist" of ASTM D6237 to monitor daily activity and to assist in preparing the daily inspection report. Note each non-compliant issue and each issue identified for rework. Use of forms containing entry blocks for all required data is encouraged. The data shall be legible and presented in a professional format. Submit report within 12 hours of the report date.

3.17.2.2 Inspection Logbook

Record all daily activity related to this section in the Inspection Logbook, including the daily inspection reports, as well as all other pertinent observations and information. Use hard or spiral bound book with consecutively numbered pages. Prior to final payment, submit original Inspection Logbook to the Contracting Officer upon completion of project.

3.17.2.3 Inspection Equipment

Use equipment in good condition, operational within its design range, and calibrated as required by the specified standard for use with each device.

3.17.3 Testing for Moisture

Test moisture vapor emission (MVE) levels after surface preparation and prior to application of any coatings, including Test Patch, in accordance with ASTM F1869. Each kit shall be applied directly to uncoated concrete for a continuous period of 60 to 72 hours. Testing shall be on prepared surfaces at least 96 hours after any wet processes (i.e; degreasing), and no more than 36 hours prior to initial coating application. Apply three

SECTION 09 67 23.15 Page 21

Moisture Vapor Emission (MVE) Test Kits in each test area, with at least one test area to be located in the center and one near each side of the floor slab. Test a minimum of five areas (3 test kits in each area) for floors up to 10,000 square feet. For floors larger than 10,000 square feet, test one area (3 kits) for every additional 2000 square feet of surface area. Report the concrete's rate of moisture vapor emission in each test area as the average of the three rates.

Acceptable Moisture Vapor Emission (MVE) is less than 3.5 pounds moisture per 24 hours, 1000 square feet, per ASTM F1869. If a concrete floor has a rate of Moisture Vapor Emission (MVE) that exceeds 3.5 pounds moisture per 24 hours, 1000 square feet (ASTM F1869), apply a Moisture Reducing System (MRS) prior to the application of the flooring system (BID OPTION). The MRS shall be compatible with the submitted flooring system and approved in writing by the manufacturer of the thin film flooring system. Apply the MRS to prepared concrete and reduce the rate of MVE to less than 3.0 pounds moisture per 24 hours per 1000 square feet before proceeding with the application of the floor coating system.

In addition to MVE testing, measure concrete moisture content (MC) using an electronic moisture meter, such as Tramex Concrete Encounter CME4, or Government approved…