EXHIBIT M - P683 Parking Garage_Final Specifications.pdf
PDF 6 MB Posted
- Solicitation number
- N6945026R0005
About this file
This document is a comprehensive technical specification for the construction of a P683 Parking Garage Facility at Naval Air Station Jacksonville, Florida, prepared by NAVFAC Southeast. The specification details the complete design requirements and construction standards across 49 divisions of work, encompassing structural, architectural, mechanical, electrical, and site infrastructure systems. Work Order No. 1817922 serves as the project identifier, with the facility designed to support military operations through a modern multi-level parking structure incorporating concrete construction, metal railings, roofing systems, fire suppression, plumbing, HVAC, electrical distribution, lighting controls, telecommunications, and comprehensive security and safety systems. The design team includes architects, structural engineers, and mechanical/electrical specialists from NAVFAC Southeast, with acceptance authority vested in Robert Craft as Design Production Director. Key construction materials specified include reinforced cast-in-place concrete with specific compressive strength requirements (4000 psi minimum), precast prestressed concrete members, steel doors and frames, aluminum-framed entrances, modified bituminous membrane roofing, and extensive electrical and mechanical systems requiring UL listings and FM Global approvals. The specification emphasizes quality assurance through third-party testing and inspection, manufacturer certifications, field testing protocols, and performance warranties extending to 20 years for roofing and flashing systems. All submittals require government approval, with specific classifications identifying drawings, product data, test reports, and certifications needed before fabrication and installation proceed.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO. 1817922
APPROPRIATION: MCON
PARKING
At
NAS Jacksonville, FL
SUBMITTED BY:
NAVFAC Southeast, Planning Design and Construction P.O. Box 30, Building 903 NAS Jacksonville, FL 32212
PREPARED BY:
Architectural: Robert Lopez, R.A., NAVFAC SE, DC Interior Design: Misty Sieracki, RID NAVFAC SE, DC Structural: Juan Tablada, P.E., NAVFAC SE, DC Mechanical: NAVFAC SE, DC Electrical: NAVFAC SE, DC Fire Protection: NAVFAC SE, DC Civil: NAVFAC SE, DC Landscape Arch:
, P.E., Santiago Santamaria, Jesse Rodak, P.E., Andre Gandionco, P.E., Judd Lee, PLA NAVFAC SE, DC
Design Manager (DM):
David Walter, P.E. Date:
ACCEPTED BY:
For Commander, NAVFAC Southeast: ___________________________________
Robert Craft, R.A.
Design Production Director, PDC4A Date: , 2025
CRAFT.ROBERT.C.1
407806294
Digitally signed by
CRAFT.ROBERT.C.1407806294
Date: 2025.12.16 08:31:26 -05'00'
WALTER.DAVID.C.14
02520635
Digitally signed by
WALTER.DAVID.C.1402520635
Date: 2025.12.16 08:09:10 -05'00'
P683 Parking Garage Facility eProject No. 1817922 NAS Jacksonville, FL
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/24 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24 SUMMARY OF WORK
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 9: 08/24 CAST-IN-PLACE CONCRETE
03 45 33 05/16, CHG 1: 11/21 PRECAST PRESTRESSED STRUCTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 05 23.16 08/18 STRUCTURAL WELDING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
05 52 00 08/23 METAL RAILINGS
05 52 20 08/23 BARRIER CABLE SYSTEMS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 14 00 08/23 FLUID-APPLIED WATERPROOFING
07 17 00 02/16 BENTONITE WATERPROOFING
07 18 00 03/17 TRAFFIC COATINGS
07 22 00 08/23 ROOF AND DECK INSULATION
07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS
07 52 00 05/12, CHG 5: 11/19 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 08/23 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DIVISION 09 - FINISHES
DOCUMENT PROJECT Page 1
09 22 00 08/24 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/24 GYPSUM BOARD
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 14 53 02/15, CHG 1: 05/17 TRAFFIC SIGNAGE
10 44 16 11/19 FIRE EXTINGUISHERS
10 53 13.00 25 07/12 OVERHEAD SUPPORTED CANOPIES
DIVISION 14 - CONVEYING EQUIPMENT
14 24 23 05/16 HYDRAULIC PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 12 00 05/11 STANDPIPE SYSTEMS
21 13 16 08/20 DRY PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 30 00 04/08, CHG 1: 08/13 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 05/24 PLUMBING, GENERAL PURPOSE
22 14 29.00 02/23 SUMP PUMPS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 02/25 HVAC AIR DISTRIBUTION
23 81 00 05/24 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 08/24 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS
DIVISION 26 - ELECTRICAL
26 05 13 08/25 MEDIUM-VOLTAGE CABLES
26 05 13.00 10 11/23 MEDIUM-VOLTAGE CABLES
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,
MEDIUM-VOLTAGE TRANSFORMERS
26 13 00 05/21, CHG 1: 05/22 SF6/HIGH-FIREPOINT FLUIDS INSULATED
PAD-MOUNTED SWITCHGEAR
26 20 00 05/25 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 32 15 05/24 ENGINE-GENERATOR SET STATIONARY
DOCUMENT PROJECT Page 2
15-2500 KW, WITH AUXILIARIES
26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES AND
BY-PASS/ISOLATION SWITCH
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 05/25 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 10 00 02/21 SITE CLEARING
31 11 00 11/18 CLEARING AND GRUBBING
31 31 16.13 08/22, CHG 1: 11/23 CHEMICAL TERMITE CONTROL
31 32 19.16 02/21 GEOTEXTILE SOIL STABILIZATION
31 63 16 11/20 AUGERED CAST-IN-PLACE PILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.71 11/22 COLD MILLING ASPHALT PAVING
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 20 05/22 BASE COURSE FOR RIGID AND SUBBASE FOR
FLEXIBLE PAVING
32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE
PAVING
32 12 13 05/24 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 15 00 05/17 AGGREGATE SURFACING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 32 23.13 02/20 SEGMENTAL CONCRETE BLOCK RETAINING WALL
32 84 24 08/11, CHG 1: 05/17 IRRIGATION SPRINKLER SYSTEMS
32 92 23 04/06, CHG 1: 08/21 SODDING
32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 01 30.16 11/21, CHG 1: 02/24 TV INSPECTION OF SEWER LINES
33 11 00 02/18, CHG 2: 11/23 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 52 10 11/18, CHG 1: 11/20 FUEL SYSTEMS PIPING (SERVICE STATION)
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 49 -
DOCUMENT PROJECT Page 3
49 99 99 ATTACHMENTS
-- End of Project Table of Contents --
DOCUMENT PROJECT Page 4
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 76 PAGES
P683 Parking Garage Facility
01 11 00 SD-01 Preconstruction Submittals
1.8 GSalvage Plan
02 41 00 SD-01 Preconstruction Submittals
1.2.2 GDemolition Plan
GDeconstruction Plan 1.11Existing Conditions
SD-07 Certificates
1.7 GNotification
SD-11 Closeout Submittals Receipts
03 30 00 SD-01 Preconstruction Submittals Concrete Curing Plan
1.6.5 GQuality Control Program
1.6.6 GQuality Control Personnel
Certifications 1.6.6Quality Control Organizational
Chart
1.6.8 GLaboratory Accreditation
3.3.10Maturity Method Data
SD-02 Shop Drawings 1.6.2.1Formwork
1.6.2.2 GReinforcing Steel
SD-03 Product Data
2.4.5 SJoint Sealants
2.4.4 SJoint Filler
2.1Formwork Materials
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 76 PAGES
03 30 00 SRecycled Aggregate Materials
2.3.1 SCementitious Materials
2.4.6Vapor Retarder 2.4.1Concrete Curing Materials
2.6 SReinforcement
2.4.3.1Liquid Chemical Floor Hardeners and Sealers 2.3.4Admixtures 2.6.2Mechanical Reinforcing Bar
Connectors 2.2.2Waterstops
1.8.1 SLocal/Regional Materials
2.2.3Biodegradable Form Release
Agent Pumping Concrete Finishing Plan
2.4.2Nonshrink Grout SD-05 Design Data
1.6.1.1 GConcrete Mix Design
SD-06 Test Reports
1.6.1.1 GConcrete Mix Design
1.6.4.1Fly Ash 1.6.4.1Pozzolan 1.6.4.2Slag Cement 1.6.4.3Aggregates
3.14.3.3 GCompressive Strength Tests
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 76 PAGES
03 30 00 3.14.3.5Unit Weight of Structural Concrete
Chloride Ion Concentration 3.14.3.4Air Content 3.14.3.1Slump Tests 2.3.2Water
SD-07 Certificates 2.6.1Reinforcing Bars 1.9Welder Qualifications 1.6.3.1VOC Content for Form Release
Agents, Curing Compounds, and Concrete Penetrating Sealers
1.6.3.2Safety Data Sheets 1.8.2Forest Stewardship Council
(FSC) Certification 1.6.6.2Field Testing Technician and
Testing Agency SD-08 Manufacturer’s Instructions
2.4.3.1Liquid Chemical Floor Hardeners and Sealers
2.4.5 SJoint Sealants
2.4.1Curing Compound
03 45 33 SD-02 Shop Drawings
2.1.1.2 GDrawings of Precast Members
2.1.1.2 GDrawings of Precast Prestressed
Concrete Members
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 76 PAGES
03 45 33 SD-03 Product Data 2.2.9.1Inserts 2.2.10Bearing Pads
SD-05 Design Data
2.1.1.2 GDesign Calculations
1.4.3 GConcrete Mix Design
SD-06 Test Reports
1.4.3 GConcrete Mix Design
2.2.2.1Fly Ash 2.2.2.2Pozzolan 2.2.2.4Ground Granulated
Blast-Furnace Slag 2.2.4Aggregates
Concrete and Aggregate Quality Control Testing
SD-07 Certificates 2.3Quality Control Procedures
3.12 GConstruction Records
Erector's Post Audit Declaration SD-11 Closeout Submittals
1.4.4Batch Ticket
2.2.1 SRecycled Content for Fly Ash and
Pozzolan
2.2.1 SRecycled Content for Ground Iron
Blast-Furnace Slag 2.2.1Recycled Content for Silica Fume
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 76 PAGES
04 20 00 SD-02 Shop Drawings
3.3.2.1 GCut CMU
3.4.1.1 GDetail Drawings
SD-03 Product Data
1.5.1 GHot Weather Procedures
1.5.2 GCold Weather Procedures
GCement
2.4.1.1 GCementitious Materials
SD-05 Design Data
2.1.2 GMasonry Compressive Strength
3.2.5 GBracing Calculations
SD-06 Test Reports Field Testing of Mortar
3.6.1.1Field Testing of Grout Prism Tests
SD-07 Certificates 1.3.1Special Masonry Inspector
Qualifications 2.2.2.2Concrete Masonry Units (CMU)
Precast Concrete Units 2.4.1.1Cementitious Materials 2.4.1.3Admixtures for Masonry Mortar 2.4.2.2Admixtures for Grout 2.6.2Anchors, Ties, and Bar
Positioners 2.6.3Joint Reinforcement
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 76 PAGES
04 20 00 SD-08 Manufacturer’s Instructions 2.4.1.3Admixtures for Masonry Mortar 2.4.2.2Admixtures for Grout
SD-10 Operation and Maintenance Data
3.8Take-Back Program 05 05 20 SD-01 Preconstruction Submittals
1.5.1.1 GInstaller Qualifications
1.5.1.2 GPost-Installed Anchor Special
Inspector Qualifications SD-03 Product Data
2.1.1.3 GMechanical Anchors in Concrete
2.1.1.4 GAdhesive Anchor System in
Concrete
3.1.3 GNon-Shrink, Non-Metallic Grout
SD-06 Test Reports
3.3.4 GPost-Installed Anchor Special
Inspections Report SD-07 Certificates
2.1.1.1 GPost-Installed Anchor
Certification
SD-08 Manufacturer’s Instructions
2.1.1.2 GManufacturer's Printed
Installation Instructions
3.1.3 GNon-Shrink, Non-Metallic Grout
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 76 PAGES
05 05 20 1.5Manufacturer's Material Safety Data Sheets
05 05 23.16 SD-01 Preconstruction Submittals
3.2 GWelding Quality Assurance Plan
SD-03 Product Data
1.3 GWelding Procedure Qualifications
1.3.4Welder, Welding Operator, and
Tacker Qualification 1.3.2Previous Qualifications
1.3.3 GPre-Qualified Procedures
2.2Welding Electrodes and Rods
SD-06 Test Reports 3.3Nondestructive Testing 3.2Weld Inspection Log
SD-07 Certificates 1.3.1Certified Welding Procedure
Specifications (WPS) 1.3.1Certified Brazing Procedure
Specifications (BPS) 1.3.1Certified Procedure Qualification
Records (PQR) 1.3.1Certified Welder Performance
Qualifications (WPQ) 1.3.1Certified Brazer Performance
Qualifications (BPQ) 1.3.5Certified Welding Inspector
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 76 PAGES
05 05 23.16 1.3.5Nondestructive Testing Personnel
05 50 13 SD-02 Shop Drawings
2.4 GExpansion Joint Covers
2.5 GBollards/Pipe Guards
2.6 GAngles and Plates
SD-03 Product Data Corner Guards
2.4 GExpansion Joint Covers
GDownspout Terminations
2.1 SRecycled Content
SD-04 Samples
2.4Expansion Joint Covers SD-07 Certificates
2.1 GCertificates of Compliance
05 52 00 SD-02 Shop Drawings
1.2.1 GFabrication Drawings
1.5.1 GFabrication Drawings
3.2 GIron and Steel Hardware
3.2 GSteel Shapes, Plates, Bars and
Strips SD-03 Product Data
2.2.6 GConcrete Inserts
2.2.7 GMasonry Anchorage Devices
2.1.3 GProtective Coating
2.2.9 GSteel Railings and Handrails
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 76 PAGES
05 52 00 2.2.10 GAluminum Railings and Handrails SD-05 Design Data
GDesign Calculations For Connections
SD-07 Certificates
1.4.2 GWelder Qualification
SD-08 Manufacturer’s Instructions 3.2Installation Instructions
05 52 20 SD-02 Shop Drawings
1.2.1 GFabrication Drawings
1.5.1 GFabrication Drawings
GSteel Shapes, Plates, Bars and Strips
SD-03 Product Data GConcrete Inserts GMasonry Anchorage Devices
Hardware Data Sheets (see D. Hardware Data Sheets note below) G
2.1.1 GProtective Coating
1.2.1 GAnchorage and Fastening
Systems SD-05 Design Data
GDesign Calculations For Connections
SD-06 Test Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 76 PAGES
05 52 20 GMill Test Reports SD-08 Manufacturer’s Instructions
3.2Installation Instructions Operation and Maintenance Manual
06 10 00 SD-03 Product Data 1.8Fire-retardant Treatment 2.3.2Adhesives
SD-06 Test Reports 1.4.2Preservative-treated
SD-07 Certificates 1.10.1Certificates of Grade 1.7Preservative Treatment
07 14 00 SD-03 Product Data 2.1Fluid-Applied Membrane 2.2Membrane Primer 2.8Elastomeric Sheet 2.10Flexible Foam-Backed
Elastomeric Sheet 3.3Solvent 3.4.1Moisture Meter 2.11Protection Board 2.7Bond Breaker
SD-06 Test Reports
3.4.3 GFlood Testing
GElectronic Leak Testing
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 76 PAGES
07 14 00 SD-11 Closeout Submittals 1.6Warranty 3.6Information Card 3.5Maintenance and Repair Training
07 17 00 SD-03 Product Data
2.1 GBentonite Materials
2.1.3 GBentonite Panels
1.3 GAccessories
SD-08 Manufacturer’s Instructions 3.2Application 3.3Protection
3.5 GCorrections
07 18 00 SD-02 Shop Drawings 2.2Traffic Coating
SD-03 Product Data 2.2Traffic Coating
SD-04 Samples 2.2Traffic Coating
SD-08 Manufacturer’s Instructions 3.5Traffic-Coating Application
SD-09 Manufacturer’s Field Reports
3.6.2Traffic Coating Inspection Report SD-10 Operation and Maintenance Data
2.2Traffic Coating
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 76 PAGES
07 22 00 SD-02 Shop Drawings
1.3 GInsulation Board Layout
SD-03 Product Data
2.1 GInsulation
1.4 GCover Board
2.4 GFasteners
2.1.3 SRecycled Content For Insulation
SD-05 Design Data
1.7 GWind Resistance
SD-06 Test Reports
1.8.1 GFlame Spread Rating
SD-07 Certificates
1.6 GInstaller Qualifications
1.6 GCertificates Of Compliance For
Felt Materials SD-08 Manufacturer’s Instructions
2.4 GFasteners
2.1 GInsulation
07 42 13 SD-01 Preconstruction Submittals
1.5.3 GQualification of Manufacturer
1.5.4 GQualification of Installation
Contractor
1.8 GWarranty
SD-02 Shop Drawings
1.5.1.1 GInstallation Drawings
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 76 PAGES
07 42 13 2.1Recycled Content;
2.2.1 GWall Panels
2.2.2Factory Color Finish 1.5.5Closure Materials 2.5.4.4Pressure Sensitive Tape 2.5.4.1Sealants and Caulking 1.5.3.1Galvanizing Repair Paint 1.5.3.1Enamel Repair Paint
Aluminized Steel Repair Paint 1.5.5Accessories 2.5Accessories
SD-04 Samples
2.2.1 GWall Panels
1.5.3.1 GFasteners
2.5.3 GMetal Closure Strips
GColor chart SD-05 Design Data
1.5.1.2 GWind load design analysis
SD-06 Test Reports
3.7.2 GLeakage Tests
1.3.2 GWind Load Tests
2.2.2.6 GCoating
2.2.2.6 GChalking
SD-07 Certificates
1.5.3.1 GCoil Stock
1.5.3.1 GFasteners
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 76 PAGES
07 42 13 1.5.3.1 GGalvanizing Repair Paint
1.5.3.1 GEnamel Repair Paint
SD-08 Manufacturer’s Instructions
3.3 GInstallation
SD-09 Manufacturer’s Field Reports
3.8.1 GManufacturer's Field Reports
SD-11 Closeout Submittals
1.8 GWarranty
1.5.6 GMaintenance Instructions
1.8.120 year 'No Dollar Limit' warranty for labor and material 07 52 00 SD-02 Shop Drawings
1.4.6 GRoof Plan
1.4.6Field Inspection and Existing
Conditions Report SD-03 Product Data
2.2 GModified Bitumen Sheets
2.4 GCold-Applied Membrane
Adhesive
2.6 GPrimer
2.8 GFasteners And Plates
1.8 GWarranty
SD-05 Design Data
1.4.5 GWind Uplift Calculations
SD-07 Certificates
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 76 PAGES
07 52 00 1.4.1Qualification of Manufacturer 1.4.2Qualification of Applicator 1.4.3Qualification of Engineer of
Record
1.4.5 GWind Uplift Resistance
1.4.4 GFire Resistance
SD-08 Manufacturer’s Instructions
3.3.5 GModified Bitumen Membrane
Application
3.3.6 GFlashing
3.3.3.1 GCold Adhesive Applied Modified
Bitumen Membrane 2.6Primer 2.8.1Fasteners
1.6 GCold Weather Installation
SD-11 Closeout Submittals 1.8Warranty 3.8Information Card 3.7Instructions To Government
Personnel 07 60 00 SD-02 Shop Drawings
2.2.1 GExposed Sheet Metal
3.1.13 GGutters
3.1.14 GDownspouts
3.1.20 GExpansion Joints
3.1.17 GSplash Pans
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 76 PAGES
07 60 00 GBase Flashing
3.1.9 GCounterflashing
3.1.21 GFlashing at Roof Penetrations
and Equipment Supports
2.2.11 GReglets
3.1.15 GScuppers
3.1.22 GCopings
3.1.12 GDrip Edges
3.1.16 GConductor Heads
3.1.18 GEave Flashing
2.1 SRecycled Content
SD-03 Product Data
2.2.8 GCool Roof
SD-04 Samples
1.4.2 GFinish Samples
SD-07 Certificates
2.2.7.1 GWarranty on Finishes
SD-08 Manufacturer’s Instructions
1.4.3 GInstructions for Installation
SD-10 Operation and Maintenance Data
1.4.3 GCleaning and Maintenance
07 84 00 SD-02 Shop Drawings
2.1 GFirestopping System
SD-03 Product Data
2.2 GFirestopping Materials
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 76 PAGES
07 84 00 SD-06 Test Reports
3.3 GInspection
SD-07 Certificates 1.5.2Inspector Qualifications 2.2Firestopping Materials
1.5.1 GInstaller Qualifications
07 92 00 SD-03 Product Data
2.1 GSealants
2.2 GPrimers
2.3 GBond Breakers
2.4 GBackstops
3.1 GField Adhesion
SD-07 Certificates
2.1 GSealants
2.2 GPrimers
2.3 GBond Breakers
08 11 13 SD-02 Shop Drawings
2.1 GDoors
2.1 GDoors
2.4 GFrames
2.4 GFrames
2.2Accessories
SD-03 Product Data
2.1 GDoors
2.4 GFrames
2.2Accessories
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 76 PAGES
08 41 13 SD-01 Preconstruction Submittals
1.2.1 GSample Warranty
1.2.1 GList of Product Installations
SD-02 Shop Drawings
3.3 GInstallation Drawings
2.2 GFabrication Drawings
SD-03 Product Data
1.2.1 GManufacturer's Catalog Data
2.2.3 GFinish
2.1.1.2 SRecycled Content of Aluminum
Material SD-04 Samples
1.2.1 GFinish and Color Samples
SD-06 Test Reports
1.2.1 GCertified Test Reports
3.4.2Deflection
SD-08 Manufacturer’s Instructions 3.3Manufacturer's Instructions
SD-11 Closeout Submittals 3.6Manufacturer's Product Warranty
08 71 00 SD-02 Shop Drawings
1.3 GManufacturer's Detail Drawings
1.5 GHardware Schedule
2.3.7 GKeying System
SD-03 Product Data
2.3 GHardware Items
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 76 PAGES
08 71 00 SD-08 Manufacturer’s Instructions 3.1Installation
SD-10 Operation and Maintenance Data
1.5 GHardware Schedule
SD-11 Closeout Submittals
1.6.1Key Bitting 08 81 00 SD-02 Shop Drawings
Drawings showing complete details of the proposed setting methods, mullion details, edge blocking, size of openings, frame details, materials, and types and thickness of glass.
SD-03 Product Data Performance Documentation for all glass types
1.3Glazing Accessories 2.3.3.1Sealants
SD-04 Samples 2.3.2Glazing Compound 2.3.6Tape
Sealant SD-08 Manufacturer’s Instructions
2.3Setting and Sealing Materials 3.2Glass Setting
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 76 PAGES
08 91 00 SD-02 Shop Drawings 1.4Wall Louvers
SD-03 Product Data 2.2Metal Wall Louvers
Door Louvers SD-04 Samples
1.5 GWall Louver Samples
1.5 GDoor Louver Samples
09 22 00 SD-02 Shop Drawings
2.1 GMetal Support Systems
SD-03 Product Data 2.1Metal Support Systems
09 29 00 SD-03 Product Data 2.1.1Gypsum Board 2.1.1.2Exterior Gypsum Soffit Board 2.1.6Accessories
2.1.1 SRecycled Content for Gypsum
Board SD-07 Certificates
2.1 GAsbestos Free Materials
SD-08 Manufacturer’s Instructions
2.1Safety Data Sheets SD-10 Operation and Maintenance Data
2.1Manufacturer Maintenance Instructions
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 76 PAGES
09 90 00 SD-02 Shop Drawings 3.9Piping Identification
SD-03 Product Data
2.1 GCoating
2.1Product Data Sheets
Sealant SD-04 Samples
2.2 GColor
SD-07 Certificates
1.5.4.2 GQualification Testing
SD-08 Manufacturer’s Instructions Application Instructions
2.1Mixing 1.7.1Manufacturer's Safety Data
Sheets SD-10 Operation and Maintenance Data
2.1 GCoatings
10 14 00.10 SD-02 Shop Drawings
3.1 GApproved Detail Drawings
SD-03 Product Data
2.1Modular Exterior Signage System 3.1Installation
1.2 GExterior Signage
1.2.1Wind Load Requirements
SD-04 Samples
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 76 PAGES
10 14 00.10 1.2 GExterior Signage SD-10 Operation and Maintenance Data
3.1.2 GProtection and Cleaning
10 14 00.20 SD-02 Shop Drawings
1.4.2 GDetail Drawings
SD-03 Product Data
2.1 GStair Signage
2.2 GExit Door Tactile Sign
2.3 GDoor Tags
SD-04 Samples
1.4.1 GInterior Signage
GSoftware
2.1 GStair Signage
2.2 GExit Door Tactile Sign
2.3 GDoor Tags
SD-10 Operation and Maintenance Data
3.1 GApproved Manufacturer's
Instructions
3.1.2 GProtection and Cleaning
10 14 53 SD-03 Product Data
2.1Traffic Sign Posts FHWA Acceptance Letter
2.4Traffic Sign Retroreflective Sheeting
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 76 PAGES
10 14 53 SD-04 Samples 2.6.2Flexible Posts
10 44 16 SD-02 Shop Drawings
2.1.1 GFire Extinguishers
Part 2 GAccessories Part 2 GCabinets
1.5 GSchedule
SD-03 Product Data
2.1.1 GFire Extinguishers
Part 2 GAccessories Part 2 GCabinets
SD-07 Certificates 2.1.1Fire Extinguishers Certifications 1.4Manufacturer's Warranty with
Inspection Tag 10 53 13.00 25 SD-02 Shop Drawings
1.3.1Shop Drawings 2.2Shop Drawings
SD-03 Product Data 1.3.2Product Data
SD-04 Samples 2.3Finishes
SD-05 Design Data 1.3.3Calculations
SD-07 Certificates 1.3.4Letter of Compliance
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 76 PAGES
14 24 23 SD-02 Shop Drawings
2.1 GElevator
1.2.1 GElevator Components
1.2.2 GElevator Components
1.2.1 GElevator Machine
1.2.1 GElevator Controller
1.3.4 GWiring Diagrams
SD-03 Product Data
2.1 GElevator
1.2.1 GElevator Components
1.2.2 GElevator Components
1.2.2 GData Sheets
2.5.2 GElevator Microprocessor
Controller SD-05 Design Data
1.2.3.3Emergency Power Systems 1.2.3.2Heat Loads 1.2.3.1Reaction Loads
SD-07 Certificates
1.3.2 GPrice Lists
1.4Warranty 1.3.1.1Endorsement Letter 1.2.4Welders' Qualifications
2.5.2.3 GElevator Controller Certification
SD-10 Operation and Maintenance Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 76 PAGES
14 24 23 2.1 GElevator
1.2.5 GMaintenance Control Program
(MCP)
2.5.2.2 GSoftware and Documentation
21 12 00 SD-02 Shop Drawings
1.4.4 GStandpipe System
SD-03 Product Data
2.1.1 GPipe and Fittings
2.1.1 GMechanical Couplings
2.1.2 GPipe Hangers and Supports
2.1.3 GValves
2.1.7 GFire Department Connections
2.2.1 GBuried Pipe and Fittings
SD-06 Test Reports
3.7.1 GPreliminary Tests
3.7.2 GAcceptance Tests
SD-07 Certificates
1.6.1 GQualifications of Installer
SD-10 Operation and Maintenance Data
GAlarm Valves GBackflow Preventer
SD-11 Closeout Submittals
1.6.2 GSystem As-Built Drawings
21 13 16 SD-01 Preconstruction Submittals
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 76 PAGES
21 13 16 1.2.4 GQualified Fire Protection Engineer (QFPE)
1.4.2.1 GSprinkler System Designer
1.4.2.2 GSprinkler System Installer
1.4.2.3 GNitrogen Generation System
Commissioning Technician SD-02 Shop Drawings
1.2.1.1 GShop Drawing
SD-03 Product Data
2.2.1 GPipe
2.3.1.2 GFittings
2.3.3 GValves
2.10.5 GRelief Valves
2.9 GSprinklers
2.3.2 GPipe Hangers and Supports
2.6.1 GSprinkler Alarm Switch
2.6.3 GValve Supervisory (Tamper)
Switch
2.8 GFire Department Connection
2.7 GBackflow Prevention Assembly
2.7.1 GHose Valve
2.6.2 GHigh/Low-Nitrogen Pressure
Supervisory Switch
1.4.2.3 GNitrogen Generation System
2.1.2 GNameplates
2.4 GDry Pipe Valve
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 76 PAGES
21 13 16 SD-05 Design Data
1.2.1.2 GHydraulic Calculations
SD-06 Test Reports
3.7.1 GTest Procedures
SD-07 Certificates
3.7.2.1 GVerification of Compliant
Installation
3.7.2.2 GRequest for Government Final
Test SD-10 Operation and Maintenance Data
3.9 GOperating and Maintenance
(O&M) Instructions
1.6 GSpare Parts
SD-11 Closeout Submittals
3.9As-built drawings 21 30 00 SD-01 Preconstruction Submittals
1.3Fire Pump Installation Related Submittals
1.7.1 GFire Protection Specialist
SD-02 Shop Drawings
3.3.1 GInstallation Drawings
3.11.2 GAs-Built Drawings
3.3.2 GPiping Layout
3.3.2 GPump Room
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 76 PAGES
21 30 00 2.1 GCatalog Data 1.6Spare Parts 3.8.2Preliminary Tests
3.8 GField Tests
1.7.6 GManufacturer's Representative
3.11.1 GField Training
Army Final Acceptance Test 3.8.3Navy Formal Inspection and
Tests SD-06 Test Reports
3.8.2Preliminary Tests
3.8.3 GNavy Formal Inspection and
Tests SD-07 Certificates
1.7.1Fire Protection Specialist 1.7.2Qualifications of Welders 1.7.3Qualifications of Installer 1.7.4Preliminary Test Certification 1.7.5Final Test Certification
SD-10 Operation and Maintenance Data
3.11.1 GOperating and Maintenance
Instructions
2.14Flow Meter 22 00 00 SD-02 Shop Drawings
3.6.1 GPlumbing System
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 76 PAGES
22 00 00 SD-03 Product Data GBackflow Prevention Assemblies
2.7 GPumps
1.6.1Welding
GVibration-Absorbing Features 3.6.1Plumbing System
SD-06 Test Reports 3.6Tests, Flushing and Disinfection
GTest of Backflow Prevention Assemblies
SD-07 Certificates 1.4Materials and Equipment 2.1.1Bolts
SD-10 Operation and Maintenance Data
3.6.1 GPlumbing System
22 14 29.00 SD-02 Shop Drawings
2.1 GConnection Diagrams
2.1 GControl Diagrams
2.1 GInstallation Drawings
SD-03 Product Data
2.1 GManufacturer's Catalog Data
2.1 GPump Performance Curve
3.3 GSpare Parts List
3.3 GSpecial Tools
2.2.1 GWet-Pit Sump Pumps
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 76 PAGES
22 14 29.00 GSubmersible Pumps GAccessories
2.2.1.10 GFloatless Electrode Level
Controls
SD-06 Test Reports
3.2.2 GHydrostatic Leak
3.2.2 GStatic Heads
3.2.2 GPump Flow Capacity
SD-07 Certificates 2.2.1.6Manufacturer's Certification of
Bearing Life SD-08 Manufacturer’s Instructions
2.1Manufacturer's Installation Instructions
2.1Vibration Specifications 23 05 93 SD-01 Preconstruction Submittals
1.3.3 GRecords of Existing Conditions
1.5.1 GIndependent TAB Agency and
Personnel Qualifications
1.5.3.1 GTAB Design Review Report
SD-02 Shop Drawings
1.3.3 GTAB Schematic Drawings and
Report Forms SD-03 Product Data
1.3 GEquipment and Performance
Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 76 PAGES
23 05 93 1.5.1.3 GTAB Related HVAC Submittals SD-06 Test Reports
3.3.5 GCompleted Pre-Final DALT
Report
3.3.8 GCertified Final DALT Report
1.5.3.2 GPrerequisite HVAC Work
Checkout List
1.5.3.2 GPrerequisite HVAC Work
Checkout List
1.5.3.2 GPrerequisite HVAC Work
Checkout List
3.7 GProportional Balancing
3.7 GSeason 1
3.7 GSeason 2
SD-07 Certificates
1.5.1 GIndependent TAB Agency and
Personnel Qualifications
1.5.3.1 GDALT and TAB Submittal and
Work Schedule
1.5.3.2 GTAB Pre-Field Engineering
Report
1.5.5 GInstrument Calibration
Certificates
3.7 GDALT and TAB Procedures
Summary
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 76 PAGES
23 05 93 3.7 GCompleted Pre-Final DALT Work Checklist
3.3.2 GAdvance Notice of Pre-Final
DALT Field Work
3.7 GProportional Balancing
3.7 GSeason 1
3.7 GSeason 2
23 07 00 SD-02 Shop Drawings
3.2.2.4 GMICA Plates
2.3Pipe Insulation Systems 3.2Pipe Insulation Systems
Duct Insulation Systems 3.3Equipment Insulation Systems
2.3.1 SRecycled content for insulation
materials SD-03 Product Data
2.3 GPipe Insulation Systems
3.2 GPipe Insulation Systems
GDuct Insulation Systems
3.3 GEquipment Insulation Systems
SD-04 Samples
2.2.1.1 GThermal Insulation
GDisplay Samples SD-07 Certificates
2.2.1 SIndoor air quality for adhesives
SD-08 Manufacturer’s Instructions
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 76 PAGES
23 07 00 2.3 GPipe Insulation Systems
3.2 GPipe Insulation Systems
GDuct Insulation Systems
3.3 GEquipment Insulation Systems
23 23 00 SD-02 Shop Drawings
2.3 GRefrigerant Piping System
SD-03 Product Data 2.3Refrigerant Piping System
Spare Parts 1.3.1Qualifications 3.5Refrigerant Piping Tests 3.1Verification of Dimensions
SD-06 Test Reports 3.5Refrigerant Piping Tests
SD-07 Certificates 2.1Service Organization
SD-10 Operation and Maintenance Data
1.5 GMaintenance
3.4 GOperation and Maintenance
Manuals
3.4 GDemonstrations
23 30 00 SD-02 Shop Drawings
1.4.2 GDetail Drawings
SD-03 Product Data Duct Connectors
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 76 PAGES
23 30 00 GGravity Backdraft and Relief Dampers
2.9.4.2Registers and Grilles 2.9.5Louvers 2.10.1.1In-Line Centrifugal Fans
GRoom Fan-Coil Units 1.4.3Test Procedures
1.2.1.2 GDiagrams
2.9.1 SIndoor Air Quality for Duct
Sealants SD-06 Test Reports
3.11 GPerformance Tests
GDamper Acceptance Test
SD-07 Certificates Bolts Ozone Depleting Substances Technician Certification
SD-08 Manufacturer’s Instructions 3.2Manufacturer's Installation
Instructions 3.13.2Operation and Maintenance
Training SD-10 Operation and Maintenance Data
3.13.1 GOperation and Maintenance
Manuals
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 35 OF 76 PAGES
23 30 00 2.10.1.1 GIn-Line Centrifugal Fans GRoom Fan-Coil Units
SD-11 Closeout Submittals
3.12 SIndoor Air Quality During
Construction 23 81 00 SD-03 Product Data
3.7.1Spare Parts Posted Instructions
2.5.1Coil Corrosion Protection 3.6System Performance Tests
3.4 GTraining
1.5Inventory 2.2.2.5Environmental Data 2.1Supplied Products 2.2Manufacturer's Standard Catalog
Data Humidifier
SD-06 Test Reports
3.5 GRefrigerant Tests, Charging, and
Start-Up
3.6 GSystem Performance Tests
SD-07 Certificates 3.7.2Service Organizations
SD-10 Operation and Maintenance Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 36 OF 76 PAGES
23 81 00 GOperation and Maintenance Manuals
SD-11 Closeout Submittals
2.2.2.3 SOzone Depleting Substances
23 82 00.00 20 SD-03 Product Data 2.1Unit Heaters
Infrared Heaters SD-10 Operation and Maintenance Data
2.1Unit Heaters Infrared Heaters
25 05 11 SD-01 Preconstruction Submittals GAccount Lock Exception Request
3.2.3.2 GMultiple Ethernet Connection
Device Request
1.9.1.6 GContractor Computer
Cybersecurity Compliance Statements
1.9.5 GContractor Temporary Network
Cybersecurity Compliance Statements
1.7.2 GCybersecurity Interconnection
Schedule
1.7.1 GProposed STIG and SRG
Applicability Report
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 37 OF 76 PAGES
25 05 11 GPre-Construction Control System Inventory Report
SD-02 Shop Drawings
1.7.3 GNetwork Communication, Ports, Protocols and Services Report
1.7.6 GCybersecurity Network (Riser)
Diagram SD-03 Product Data
1.7.8 GControl System Cybersecurity
Documentation
SD-06 Test Reports
3.14.1 GControl System Cybersecurity
Testing Procedures
3.14.3 GControl System Cybersecurity
Testing Report SD-07 Certificates
1.8 GSoftware Licenses
SD-11 Closeout Submittals
3.4.5.5 GPassword Change Summary
Report
3.3.5 GEnclosure Keys
1.7.5 GSoftware and Configuration
Backups
3.5.3 GAuditing Front End Software
3.5.4.1 GDevice Audit Record Upload
Software
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 38 OF 76 PAGES
25 05 11 3.9 GSystem Maintenance Tool Software
3.11.2 GControl System Scanning Tools
1.7.7 GSTIG, SRG and Vendor Guide
Compliance Result Report GFinal Control System Inventory
Report 26 05 13 SD-01 Preconstruction Submittals
1.4.1 GList of Splices and Terminations
to be Installed by Splicer/Terminator
SD-02 Shop Drawings
3.1.3 GPulling Plan
SD-03 Product Data GMultiple-Conductor Shielded
Cables GMultiple-Conductor Nonshielded
Cables
2.1.2 GSingle-Conductor Shielded
Cables GSingle-Conductor Nonshielded
Cables
2.3.1 GGround Conductors
GCable Cleats GFlexible and Portable Cable
2.5.1 GCable Supports and Fittings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 39 OF 76 PAGES
26 05 13 3.1.5.3 GCable Grips
2.5.2 GCable Tags
2.5.3 GFireproof Tape
GSplices
2.4.2 GTerminations
GMetal-Clad and Armored Cable GJumper Cables
3.1.8 GCable Identification
SD-05 Design Data
3.1.2 GCable Pulling Calculations
GCleat Manufacturer's Calculations
SD-06 Test Reports
1.6 GFactory Inspection and Tests
3.3 GField Acceptance Testing
3.3.1 GWire And Cable Test Record
Form
3.1.1 GPhase Rotation…