About this file
This document is Exhibit L of the Wisconsin eGovernment Program's Project Development & Approval Process, outlining the standardized procedures for eGovernment projects between Wisconsin state agencies, the Department of Administration (DOA), Tyler Wisconsin, and the Department of Enterprise Technology (DET). The process requires agencies to have signed Interagency Agreements with Tyler Wisconsin and DOA before proceeding with any eGovernment projects, and involves multiple stakeholders including agency program and IT staff, Tyler Wisconsin's General Manager, State Contract Administrators, and DOA Enterprise Banking Services Contract Managers.
The document establishes a 12-step project approval and management process covering professional services, functional specifications, customer support services, and technical implementation. Key components include project prioritization assessments, Statement of Work (SOW) development with specified payment terms and acceptance testing details, and mandatory project management plans with technical architecture reviews. The process includes specific thresholds for project scope changes requiring eGovernment team review: 50% increase for low-effort projects, 30% for medium-effort projects, and 20% for high-effort projects. High-effort projects require additional DOA Contract Administrator review before final approval, and all project artifacts including proposals, monthly reports, and statements of work must be maintained on the eGovernment SharePoint site for DOA Secretary's Office review.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Wisconsin eGov Program Project Development & Approval Process Rev. 8/26/2022 (updated 03/27/2023)
Project Approval Process
Step Action Description Output Responsible parties
An agency must have a signed Interagency Agreement (IA) between agency/Tyler Wisconsin/DOA before proceeding with an eGovernment project.
Agency, Tyler Wisconsin General Manager, State Contract Admin
1 Project Exploration Discussion
High-level project discussion. Focus on defining agency needs and the constituent/business expectations with limited technical discussion.
Meeting minutes with action items and/or project request form
Tyler Wisconsin and Agency program and IT staff
2 Project Priority Assessment
Completion of the project prioritization questionnaire
Priority score Agency
3 Payment If the proposed project includes use of Business Case Agency and, if
Processing non-US Bank payment processing or Exception Request applicable, DOA US Bank application, the Agency Form for Enterprise Enterprise Banking must complete and submit a Business Banking Services Services Contract Case Exception Request to the Enterprise Banking Services Contract (505ENT-M21-
ENTBANKING-01).
Contract (Form is available here)
Manager.
4 eGov Approval Includes discussion on high level project Monthly General Tyler Wisconsin adds request to the monthly eGov meeting agenda.
Agency staff attend meeting to present new project request and answer any questions, with support by Tyler Wisconsin staff. Tyler Wisconsin staff may present change request items on behalf of the agency staff, if both parties agree.
description, review of the project Manager’s report prioritization questionnaire and service and eGov Team request attachment. If approved, proceed to Step #5.
approval item
5 SOW
Development
Includes professional services and functional specifications; customer services or support; type of professional services; and funding;
payment terms; acceptance testing details.
SOW Tyler Wisconsin, Agency with input from DOA and IT, as applicable.
Exhibit L DocuSign Envelope ID: 34C546DD-39AB-4A20-97CE-513CD30C0357DocuSign Envelope ID: F543BDE8-BF67-4723-AD26-48BFD880864A https://vendornet.wi.gov/Contract.aspx?Id=3b10c549-c3cd-ea11-8121-0050568c7f0f https://vendornet.wi.gov/Contract.aspx?Id=3b10c549-c3cd-ea11-8121-0050568c7f0f https://vendornet.wi.gov/Contract.aspx?Id=3b10c549-c3cd-ea11-8121-0050568c7f0f
Exhibit L Wisconsin eGov Program
Project Development & Approval Process Rev. 8/26/2022 (Updated 03/27/2023)
6 SOW Review High Effort Only. SOW reviewed by DOA Contract Administrator prior to sign-off by Agency and Tyler Wisconsin.
SOW DOA Contract Administrator
7 Approve SOW Complete and vetted SOW signed. Approved SOW with approved fee (if applicable)
Agency and Tyler Wisconsin
8 Upload SOW Upload the fully executed SOW to the eGov SharePoint site1
SOW Tyler Wisconsin, eGov Contract Administrator
9 Project Management Plan
Develop project management plan Project Management Plan
Tyler Wisconsin with agency input
10 Technical Plan Review
Technical plan, as a component of the project plan, which includes high level architecture overview.
Project Management Plan
Agency (including internal IT if applicable), Tyler Wisconsin, and DET input for high-effort projects for DET hosted agencies
After the project management and technical plan is established, if it is determined that the work effort increases by 50% for low effort projects, 30% for medium effort projects, and 20% for high effort projects from what the eGov team initially approved, the project status will be brought to the eGov team for discussion. The project team should be prepared to discuss what impact moving forward will have on other projects and other resource constraints or impacts.
(Note, this does not apply to projects that are exclusively funded by the participating agency)
11 Project Management Plan Review
Agency reviews the overall project management plan.
Approved Project Management Plan
Tyler Wisconsin, Agency
12 Project Management
Approved project is developed and managed in accordance with Master, IA, eGov prioritization, and the SOW.
Completed project Agency and Tyler Wisconsin, in accordance with terms of SOW.
1Special note: eGov program artifacts, including project proposals, monthly reports, and statements of work should be kept on this site for review by the DOA Secretary’s Office.
DocuSign Envelope ID: 34C546DD-39AB-4A20-97CE-513CD30C0357DocuSign Envelope ID: F543BDE8-BF67-4723-AD26-48BFD880864A
| 2023-04-26T07:41:16-0700 | |
| Digitally verifiable PDF exported from www.docusign.com |
File details come from the government source that posted it. Updated .