This document is Exhibit I: Transition Plan Requirements for the Florida Department of Corrections (FDC) Invitation to Negotiate (ITN-25-068) for the Operation and Management of Contractor-Operated Correctional Facilities. The exhibit details 12 specific project management deliverables that a contractor must submit throughout the transition process, including a Project Management Plan, Project Schedule, Project Kickoff Meeting, RAID Logs, Status Reports, Meeting Agendas and Summaries, Readiness Plan, Communications Management Plan, Requirements Management Plan, Lessons Learned Documentation, Project Retrospective, and Project Closure Report. These deliverables are designed to ensure comprehensive project management, with specific submission timelines ranging from 5 to 15 business days after contract execution, and are tied to financial consequences for Service Area Three.

The deliverables follow best practices outlined in Rule Chapter 74-1, Florida Administrative Code, and require the use of Microsoft Office tools like Word, Excel, and Project. The contractor must utilize project management methodologies from the Project Management Institute (PMI) and IT Infrastructure Library (ITIL), and provide detailed documentation for each deliverable. Key requirements include developing comprehensive communication plans, managing stakeholder expectations, tracking project risks and issues, conducting lessons learned meetings, and creating retrospective and closure reports. The documents emphasize the importance of proactive project management, continuous communication, and systematic documentation to ensure a smooth transition and successful implementation of the correctional facility management contract.

View the file

Other files

File Type Posted
Attachment F - 2024-2025 4-Week Master Menu Spreadsheets 10.1 Final.pdf PDF
ITN-25-068 Contractor Operated CF MH Final.pdf PDF
Attachment L - Reference Questionnaire.pdf PDF
Exhibit J - Transition Schedule Requirements - Moore Haven.pdf PDF
Attachment G - December 2024 Alphabetical State Drug Formulary.pdf PDF
FORM 2 - Notice of Conflict of Interest.pdf PDF
FORM 12 - REPLY BOND FORM.docx DOCX document
Attachment A Draft Moore Haven OM Contract Revised Final.pdf PDF
FORM 9 - PUR 7801 (Vendor Certification Form).docx DOCX document
FORM 1 - Contact Information.pdf PDF
Attachment A Draft Moore Haven OM Contract Final.pdf PDF
Exhibit I - Transition Plan Requirements - Moore Haven.pdf PDF
Attachment M - Business Associate Agreement for HIPPA.pdf PDF
Attachment C Price Sheet - Moore Haven.xlsx XLSX spreadsheet
Exhibit M - 2026-27FY IWTF Program Request and Budget Narrative Request Template.xlsx XLSX spreadsheet
FDC ITB-25-068 Addendum 1 QA Final.pdf PDF
Attachment B Inventory - Moore Haven - Feb 2025.pdf PDF
FORM 3 - Statement of No involvement.pdf PDF
Attachment J - Confidentiality and Non-Disclosure Agreement.pdf PDF
FORM 7 - Pass Fail Requirement Certification and Non-Collusion Certification.pdf PDF
FORM 5 - Subcontracting.pdf PDF
Attachment E - Operating Per Diem Revised.pdf PDF
FORM 4 - Business Experience.pdf PDF
FORM 10 - pur 2024 use of coercion forced labor combined final.docx DOCX document
Attachment E - Operating Per Diem.pdf PDF
FORM 8 - PUR1355 Foreign Country of Concern Attestation.docx DOCX document
FORM 11 - DRUG FREE WORKPLACE.pdf PDF
Exhibit K - Quarterly Performance Measures and Deliverables - Moore Haven.xls XLS spreadsheet
Attachment H - Current Facility Program Plan - Moore Haven.pdf PDF
FORM 6 - Mandatory Responsiveness Requiements.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit I

FDC ITN-25-068

TRANSITION PLAN REQUIREMENTS

FDC-ITN-25-068

Operation and Management of Contractor-Operated Correctional Facilities Page 1 of 7

PROJECT MANAGEMENT DELIVERABLES

All references to a Contractor “Project,” “Project Manager,” or “Project Management Plan” (PMP) in this document will be applicable to the transition plan. The Project Management Office (PMO) Manager, Project Manager, or their designees, will use the following criteria to determine when each deliverable is considered complete and acceptable. The Contractor Project Manager will submit all deliverables listed below electronically. All deliverables will be reviewed based on the criteria defined in the Contract and its associated documents.

All deliverables for this section will be tied to financial consequences for Service Area Three, as defined in the Contract.

Best practices for project management are found in Rule Chapter 74-1, Florida Administrative Code (F.A.C.) and shall be followed regardless of a project’s IT categorization.

DELIVERABLE

NUMBER DELIVERABLE DESCRIPTION

Deliverable 1

PROJECT MANAGEMENT PLAN DELIVERABLE

Due: Within ten (10) Business Days of Contract execution.

Minimum Acceptance Criteria:

A Microsoft Word 2016 (or newer) document shall be provided. The deliverable shall meet the requirements of Rule Chapter 74-1.004, F.A.C., Project Category

4. All PMP subsidiary plans contained in Rule Chapter 74-1.004, F.A.C., Project Category 4 are required.

The Contractor shall provide overall project management support for the activities, deliverables, and work products identified in the Contract, including the day-to-day management and administrative support of its staff and activities to successfully achieve the Solution goals. The Department will maintain project management responsibilities for the Project and State staff. The Contractor shall provide project management tools/templates, for FDC approval, and work closely with the Department’s Project Manager and PMO to assist in establishing and operating the PMO for the Project.

The Contractor’s Project Management approach shall have a foundation in established methodologies and standards, such as those found in the Project Management Institute's (PMI) Project Management Body of Knowledge (PMBOK®) and IT Infrastructure Library (ITIL®) wherever applicable.

The Contractor shall provide highly qualified project management staff to manage the work planning effort, maintain the project schedule, proactively manage all aspects of project performance, and be actively engaged in the project’s day-to-day operations. In addition, the Contractor shall apply methods and tools such as, but not limited to, forecasting, metrics, analyses, modeling, and scorecards/dashboards to measure and assess performance efficiency, progress, productivity, and quality. The Contractor shall provide any tools necessary to

Operation and Management of Contractor-Operated Correctional Facilities Page 2 of 7 support the management of its staff and the execution of each project management process.

Deliverable 2 PROJECT SCHEDULE DELIVERABLE

Due: Initial schedule for FDC approval is due within ten (10) Business Days of Contract execution.

Minimum Acceptance Criteria:

The initial Project Schedule must assume a Service Commencement Date of February 1, 2021. During the course of transitioning, the Contractor shall keep the Department apprised of any risks it determines are endangering completion of the transition by this date and the Department may, if determined reasonable in the Department’s sole discretion, approve the Contractor’s modification to the Project Schedule to a later Service Commencement Date. The Contractor shall then submit an updated Project Schedule to the Department for its approval within five (5) Business Days after the Department’s approval of the new date. If such modification necessitates changes to the Project Management Plan, the Contractor shall also submit an updated Project Management Plan to the Department for approval within five (5) Business Days after the Department’s approval of the new date.

Once approved, the schedule will be baselined and updated every week and sent to the FDC Project Manager by 12:00 PM Eastern Time (ET) Fridays. Create and maintain a Microsoft Project 2016 (or newer) schedule to incorporate all project activities to the agreed upon Work Breakdown Structure (WBS) level. The schedule must include at a minimum: 1) task durations, 2) start and finish dates (baseline and actual), 3) predecessors and successors, 4) resources, 5) deliverables and milestones, and 6) must calculate CPI and SPI earned value metrics. The deliverable shall meet the requirements of Rule Chapter 74-1.004, F.A.C., Project Category 4 and the schedule criteria defined in Exhibit K, FDC PMO Transition Schedule Requirements.

The Contractor shall be responsible for developing and managing a comprehensive, fully resource-loaded project schedule in Microsoft Project that details the Contractor’s implementation approach and includes tasks to be performed by FDC project team and Contractor staff. The project schedule must adhere to the standards defined in the Project Management Plan and must be constructed and maintained in a format compatible with integration into the Schedule Management Plan. The Contractor is responsible for confirming and monitoring that Microsoft Project calculates the critical path as expected.

The Contractor shall be responsible for monitoring and updating the project schedule continuously, and revising and developing further detail, as appropriate.

Changes made to the project schedule to reflect performance delays by the Contractor or its Subcontractors shall not be interpreted to relieve Contractor from contractual accountability for on-time performance of the Implementation Services.

Operation and Management of Contractor-Operated Correctional Facilities Page 3 of 7

The Project Schedule shall include major deliverables and detailed project activities in discrete work packages for assignment to Project Team members. The project schedule shall track and report progress on these activities and deliverables, including, but not limited to, expected results, timeliness of achieving solution deliverables and other significant events.

Earned Value (EV) analysis shall be used to measure the project's progress at any given point in time, forecast completion dates and cost, and analyze variances in the schedule and budget as the project progresses.

The Contractor shall conduct a weekly EV analysis to identify planned versus actual variances and include any variances in appropriate reporting. The Contractor’s analysis shall include the EV measures being captured in the project schedule to present a comprehensive analysis. The analysis shall include explanations of variances of EV measures outside of agreed upon targets, effects on other areas, and corrective actions to achieve realignment.

Deliverable 3 PROJECT KICKOFF MEETING DELIVERABLE

Due: Within five (5) Business Days of contract execution.

Minimum Acceptance Criteria:

Contractor must conduct a project kickoff meeting with FDC and appropriate stakeholders. Agenda will be developed in MS Word format by the Contractor with approval from FDC. Approved agenda must be distributed to all attendees no later than twenty-four (24) hours prior to the meeting. Contractor is responsible for submitting meeting minutes in MS Word format to the project manager within three

(3) days of the meeting. Meeting minutes must include: list of invitees, role, actual attendance (indicate attendance by phone or in person), any decisions made, decisions needed, action items (including date assigned, date due, and owner).

Deliverable 4 PROJECT MANAGEMENT TRACKING (RAID) LOGS (I.E. RISKS, ISSUES, ACTION ITEMS, DECISIONS, AND CHANGE REQUESTS)

DELIVERABLE

Due: Initial log due within fifteen (15) Business Days of Contract execution.

Minimum Acceptance Criteria:

The log must be submitted in Microsoft Excel format. The Contractor shall identify, assess, document and recommend mitigation strategies by updating the logs at a minimum of bi-weekly to reduce project risks and issues. The deliverable shall meet the requirements of Rule Chapter 74-1, F.A.C., Project Category 4.

The Contractor is responsible for project status reporting. The FDC project team requires weekly status reports to be provided to reflect the major activities for the reporting period. As part of the Contractor’s approach to status reporting, FDC requires weekly participation in status meetings with the FDC Project Team.

Project management intends to use the status reports and meetings to verify progress of project activities and to detect potential problems or delays. Topics to be covered include, but are not limited to:

Operation and Management of Contractor-Operated Correctional Facilities Page 4 of 7

• Departures from the project schedule with explanations of causes, effects on other areas, and corrective actions to achieve realignment;

• Changes to project objectives, Scope, schedule, or budget;

• Critical path analysis;

• Tasks completed since the last report;

• Tasks that were delayed and reasons for delay, with expected revised completion dates;

• Updates for previously delayed tasks;

• Planned activities for the next reporting period;

• Contractor staff planned to join or leave the project;

• Summary of major concerns or issues encountered, proposed resolutions, and actual resolutions;

• Any other topics that require attention from the FDC Project Manager; and

• Additional items defined in the PMP.

Deliverable 5 PROJECT STATUS REPORTS DELIVERABLE

Due: Within ten (10) Business Days of Contract execution and by 12:00 PM, ET, each Friday thereafter.

Minimum Acceptance Criteria:

The Contractor shall provide a weekly Project Status Reports and conduct monthly Project Reviews with the FDC Project Manager, PMO Manager, and others as identified, detailing the previous period’s achievements and progress on upcoming and existing activities; changes; identified risks and recommendations to mitigate risk, communicate forecasts; and assess project progress. These meetings may be in person or conference call at the discretion of the project manager.

A Microsoft Word 2016 (or newer) document shall be provided as written status reports beginning within ten (10) business days of the contract signing and weekly thereafter, until completion of the Project. Status reports are due via email to the FDC Project Manager by 12:00 PM, ET, each Friday (unless instructed otherwise in writing by the FDC Project Manager) and shall include:

• A narrative description of significant project activities that have been conducted or are underway

• The progress-to-date on project activities

• An explanation of any tasks/activities that are behind schedule and a plan to bring them current

• Notification of issues or risks that have been encountered and their resolution or plan for future resolution

• Goals or upcoming deadlines

The Project Manager will provide a template for the Contractor to ensure all data elements are provided.

Deliverable 6 PROJECT MEETING AGENDAS AND SUMMARIES DELIVERABLE

Due: Twenty-four (24) hours prior to each meeting and within three (3) business days of each meeting.

Operation and Management of Contractor-Operated Correctional Facilities Page 5 of 7

Minimum Acceptance Criteria:

Contractor will develop agendas for any ad-hoc meetings in MS Word format and obtain approval from FDC. Approved agenda must be distributed to all attendees no later than twenty-four (24) hours prior to the meeting. Contractor is responsible for submitting meeting minutes in MS Word format to the project manager within three (3) business days of the meeting. Meeting minutes must include: list of invitees, role, actual attendance (indicate attendance by phone or in person), any decisions made, decisions needed, action items (including date assigned, date due, and owner).

Deliverable 7 READINESS PLAN DELIVERABLE

Due: This deliverable shall be due as part of the Project Management Plan.

Minimum Acceptance Criteria:

The Contractor shall deliver a detailed organizational readiness strategy and associated plans that outline a readiness methodology, approach, activities, dependencies, and assumptions for key stakeholders to support a successful transition from current to future technologies and processes. This deliverable shall be due with the Project Management Plan. The deliverable shall meet the requirements of Rule Chapter 74-1, F.A.C., Project Category 4.

The Contractor shall deliver a detailed organizational readiness strategy and associated plans that outline a readiness methodology, approach, activities, dependencies, and assumptions for key stakeholders to support a successful transition from current to future technologies and processes. The readiness strategy must be aligned with the Contractor’s methodology and timeline. The Readiness Strategy shall be based on: 1) a comprehensive assessment of the State’s capacity for, and tolerance of, change, 2) a stakeholder analysis, and 3) an assessment of the overall change risk.

The Contractor shall, at a minimum perform the following organizational readiness services:

• Identify, assess, and support stakeholders;

• Plan, support execution, and identify measures to assess effectiveness of readiness initiatives (updating documentation as appropriate);

• Develop a readiness assessment and measurement plan for end users;

• Develop an approach to obtain and monitor leadership and executive sponsorship buy-in; and

• Identify and document the impact of business process redesign on the State.

Deliverable 8 COMMUNICATIONS MANAGEMENT PLAN DELIVERABLE

Due: This deliverable shall be due with the Project Management Plan.

Minimum Acceptance Criteria:

The Contractor shall develop a Communications plan that defines all communication touchpoints between the Project and all impacted stakeholders.

The deliverable shall meet the requirements of Rule Chapter 74-1.004, F.A.C., Project Category 4.

Operation and Management of Contractor-Operated Correctional Facilities Page 6 of 7

The Contractor shall develop a Communications Management Plan that defines all communication touchpoints between the Project and all impacted stakeholders.

The Contractor shall perform the following communications-related Services:

• Develop and support execution of a communications plan;

• Develop and support a calendar of scheduled communications, integrated with implementation, training, and rollout events;

• Identify and track opportunities for communication to relevant partners;

• Develop materials appropriate for each communication event. Materials will vary based on the communication channel but may include presentations and documents developed in Microsoft PowerPoint presentations, Microsoft Word, Microsoft Publisher, and similar tools; and

• Work with assigned FDC staff to incorporate applicable policies, procedures, and specific staff roles into the materials.

All communication materials must be reviewed and approved by the project team prior to the start of delivery. The Contractor shall provide all electronic source documents and graphics used in the development and presentation of communication materials across all delivery channels.

The Contractor shall implement methods to assess and measure the effectiveness of communication events and identify specific recommendations for adjustments, as appropriate. The Contractor shall, throughout the project, improve the approach, methods, procedures, and communication material based on lessons learned throughout execution of the Communications Plan to make sure the end users are receiving communications that enable them to execute tasks within the solution on go-live. The Communications Plan must be updated, as necessary, throughout the project.

Deliverable 9 REQUIREMENTS MANAGEMENT PLAN DELIVERABLE

Due: This deliverable shall be due as part of the Project Management Plan.

Minimum Acceptance Criteria:

The Contractor is responsible for managing all business requirements and validating that they are ultimately met during implementation. The Contractor Project Manager will work with the FDC Project Manager to develop and administer a plan to effectively manage requirements throughout the Transition Project. The Contractor must utilize sound methodologies and employ sufficient tools, including a Requirements Traceability Matrix (RTM), to appropriately identify, approve, document, and implement requirements throughout the requirements management process.

The Contractor shall deliver a Requirements Management Plan that describes the processes and tools used to facilitate the analysis, progressive elaboration, documentation, and control of Business Requirements throughout the Project.

The Contractor must facilitate the finalization of the Business Requirements, which builds upon requirements confirmation, fit/gap analysis, and gap resolution.

Operation and Management of Contractor-Operated Correctional Facilities Page 7 of 7

Contractor must facilitate and lead a business requirements confirmation activity and work collaboratively with the project staff to understand the expectations of the project team for each requirement. The confirmation activities shall include the validation of the phasing of business requirements and acceptance criteria for each phase. Business requirements may be added, split, changed, or deleted during confirmation activities.

The expected result of these activities is a confirmed set of Business Requirements.

Deliverable 10 LESSONS LEARNED DELIVERABLE

Due: Lessons learned deliverable will be due ten (10) Business Days following the close of the transition project.

Minimum Acceptance Criteria:

Lessons learned meeting, the creation of a lessons learned document and action plan. The Contractor shall complete a lessons learned meeting and create a lessons learned document and action plan for implementing the lessons learned.

Lessons learned deliverable will be due ten (10) days following the close of each quarter.

Deliverable 11 PROJECT RETROSPECTIVE DELIVERABLE

Due: The project retrospective meeting shall be conducted within 15 Business Days of project completion.

Minimum Acceptance Criteria:

The Contractor shall facilitate an in-person project retrospective meeting.

Deliverable 12 THE PROJECT CLOSURE REPORT DELIVERABLE

Due: This deliverable is due within five (5) Business Days of the project retrospective or the end of the warranty period, whichever comes later.

Minimum Acceptance Criteria:

The Contractor shall the complete project closure services by creating a lessons learned document and action plan for implementing the lessons learned based on the project, retrospective, and applicable warranty period. The report will be in MS Word format and delivered to the Project Manager.