Exhibit I DB Contract Performance Schedule.pdf

PDF 241 KB Posted

Attached to
Construction Management Support Services Federal contract opportunity
Solicitation number
15B700
Issued by
Department of Justice Bureau of Prisons Central Office

View the file

Other files for this federal contract opportunity

Other files attached to Construction Management Support Services, newest first.
File Type Posted
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Exhibit M - CM-1.docx DOCX document
Exhibit K - Cost Component Report.PDF PDF
Exhibit H Design Review Report.pdf PDF
Exhibit F.2 - Wkly Status Rpt.pdf PDF
Exhibit F.1 Monthly Report.PDF PDF
CM SOW 13 051123.pdf PDF
Solicitation.pdf PDF
Questionnaires.docx DOCX document
Exhibit C Cost Proposal Form.pdf PDF
Instructions to Offerors.pdf PDF
Exhibit N - CM-2.docx DOCX document
Exhibit L - FCI Leavenworth Site Plan.pdf PDF
Exhibit J 01 45 29 Testing Laboratory Services.pdf PDF
Exhibit G - Sr Program Manager Report.pdf PDF
Exhibit E Procedures Manual.PDF PDF
Exhibit B 01 32 13 Scheduling of Work.pdf PDF
Exhibit D CM Guidelines.pdf PDF
Exhibit C Cost Proposal Form.xls XLS spreadsheet
Exhibit A CMSS Staffing Schedule.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish Baseline Start

1 DESIGN / BUILD CONTRACT PERFORMANCE PERIOD 702 days Mon 8/7/23 Tue 4/14/26 Fri 7/28/23

2 DESIGN / BUILD CONTACT AWARD 1 day Mon 8/7/23 Mon 8/7/23 Fri 7/28/23

3 DESIGN / BUILD CONTRACT NTP 10 days Tue 8/8/23 Mon 8/21/23 Fri 8/11/23

4 DESIGN REQUIREMENTS REVIEW MEETING 2 days Tue 9/5/23 Wed 9/6/23 Mon 8/28/23

5 Contractor Submits Written Summary of Issues/ Decisions 0 days Wed 9/13/23 Wed 6/12/24 Tue 9/5/23

6 EARLY SITEWORK PACKAGE (OPTIONAL) 35 days Tue 8/22/23 Mon 10/9/23 Mon 8/14/23

7 Develop Early Sitework Design Documents and Schedule Cost & Manpower Loading

15 days Tue 8/22/23 Mon 9/11/23 Mon 8/14/23

8 Submit Early Sitework Design Documents and Schedule Cost & Manpower Loading

0 days Mon 9/11/23 Mon 9/11/23 Fri 9/1/23

9 BOP Reviews Early Sitework Design Documents and Schedule Cost & Manpower Loading

5 days Tue 9/12/23 Mon 9/18/23 Mon 9/4/23

10 BOP Delivers Early Sitework Design and Schedule Review Report to Contractor

0 days Mon 9/18/23 Mon 9/18/23 Fri 9/8/23

11 Contractor Prepares Updated Early Sitework Design Documents and Schedule Cost & Manpower Loading

5 days Tue 9/19/23 Mon 9/25/23 Mon 9/11/23

12 Contractor Submits Updated Early Sitework Design Documents and Schedule Cost & Manpower Loading

0 days Mon 9/25/23 Mon 9/25/23 Fri 9/15/23

13 BOP Reviews Updated Early Sitework Design Documents and Schedule Cost & Manpower Loading

5 days Tue 9/26/23 Mon 10/2/23 Mon 9/18/23

14 BOP Approves Design Documents and Schedule Loading;

Issues NTP For Early Sitework Construction

0 days Mon 10/2/23 Mon 10/2/23 Fri 9/22/23

15 Contractor Distributes Early Sitework Package "Construction Issue" Documents

0 days Mon 10/9/23 Mon 10/9/23 Fri 9/29/23

16 PRELIMINARY DESIGN PHASE ‐ PACKAGE A 57 days Tue 8/22/23 Wed 11/8/23 Mon 8/14/23

17 Develop Preliminary Design Documents 30 days Tue 8/22/23 Mon 10/2/23 Mon 8/14/23

18 Submit Preliminary Design Documents 0 days Mon 10/2/23 Mon 10/2/23 Fri 9/22/23

19 BOP Reviews Preliminary Design Documents 10 days Tue 10/3/23 Mon 10/16/23 Mon 9/25/23

20 BOP Delivers Design Review Report to Contractor 0 days Mon 10/16/23 Mon 10/16/23 Fri 10/6/23

21 Contractor Prepares Response to Des. Rvw. Rpt. 5 days Tue 10/17/23 Mon 10/23/23 Mon 10/9/23

22 Contractor Provides Agenda for Prelim. Des. Rvw. Mtg.

(PDRM)

0 days Wed 10/18/23 Wed 10/18/23 Tue 10/10/23

23 PRELIMINARY DESIGN REVIEW MTG.‐ PACKAGE A 2 days Tue 10/24/23 Wed 10/25/23 Mon 10/16/23

24 Contractor Prepares & Delivers Minutes from PDRM 5 days Thu 10/26/23 Wed 11/1/23 Wed 10/18/23

25 BOP Issues NTP For Final Design Phase ‐ Pkg. A @ PDRM 0 days Wed 10/25/23 Wed 10/25/23 Tue 10/17/23

26 Contractor Prepares Corrected Preliminary Design Documents

10 days Thu 10/26/23 Wed 11/8/23 Wed 10/18/23

6/12

9/11

9/18

9/25

10/2

10/9

10/2

10/16

10/18

10/25

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 H

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Project: Leavenworth FCI Proposed Performance Schedule Date: Wed 4/12/23

27 Contractor Distributes Corrected Preliminary Design Documents

0 days Wed 11/8/23 Wed 11/8/23 Tue 10/31/23

28 FINAL DESIGN PHASE ‐ PACKAGE A 100 days Thu 10/26/23 Wed 3/13/24Wed 10/18/23

29 Develop Final Design Documents 43 days Thu 10/26/23 Mon 12/25/23 Wed 10/18/23

30 Submit Final Design Documents 0 days Mon 12/25/23 Mon 12/25/23 Fri 12/15/23

31 BOP Reviews Final Design Documents 15 days Tue 12/26/23 Mon 1/15/24 Mon 12/18/23

32 BOP Delivers Design Review Report to Contractor 0 days Mon 1/15/24 Mon 1/15/24 Fri 1/5/24

33 Contractor Prepares Response to Des. Rvw. Rpt. 5 days Tue 1/16/24 Mon 1/22/24 Mon 1/8/24

34 Contractor Provides Agenda for Final Des. Rvw. Mtg. (FDRM0 days Wed 1/17/24 Wed 1/17/24 Tue 1/9/24

35 FINAL DESIGN REVIEW MTG.‐ PACKAGE A 2 days Tue 1/23/24 Wed 1/24/24 Mon 1/15/24

36 Contractor Prepares & Delivers Minutes Of FDRM 5 days Thu 1/25/24 Wed 1/31/24 Wed 1/17/24

37 Contractor Prepares Updated Project Documents 10 days Thu 1/25/24 Wed 2/7/24 Wed 1/17/24

38 Contractor Delivers Updated Project Documents 0 days Wed 2/7/24 Wed 2/7/24 Tue 1/30/24

39 BOP Reviews Updated Project Documents 5 days Thu 2/8/24 Wed 2/14/24 Wed 1/31/24

40 BOP Delivers Comments on Updated Documents 0 days Wed 2/14/24 Wed 2/14/24 Tue 2/6/24

41 Contractor Prepares Corrected Project Documents 5 days Thu 2/15/24 Wed 2/21/24 Wed 2/7/24

42 Contractor Delivers Corrected Project Documents 0 days Wed 2/21/24 Wed 2/21/24 Tue 2/13/24

43 BOP Reviews Corrected Project Documents 5 days Thu 2/22/24 Wed 2/28/24 Wed 2/14/24

44 BOP Approves Corrected Project Documents; Issues NTP For Package A Construction

0 days Wed 2/28/24 Wed 2/28/24 Tue 2/20/24

45 Contractor Distributes Package A "Construction Issue" Documents

0 days Wed 3/13/24 Wed 3/13/24 Tue 3/5/24

46 PRELIMINARY DESIGN PHASE ‐ PACKAGE B 82 days Tue 8/22/23Wed 12/13/23 Mon 8/14/23

47 Develop Preliminary Design Documents 50 days Tue 8/22/23 Mon 10/30/23 Mon 8/14/23

48 Submit Preliminary Design Documents 0 days Mon 10/30/23 Mon 10/30/23 Fri 10/20/23

49 BOP Reviews Preliminary Design Documents 15 days Tue 10/31/23 Mon 11/20/23 Mon 10/23/23

50 BOP Delivers Design Review Report to Contractor 0 days Mon 11/20/23 Mon 11/20/23 Fri 11/10/23

51 Contractor Prepares Response to Des. Rvw. Rpt. 5 days Tue 11/21/23 Mon 11/27/23 Mon 11/13/23

52 Contractor Provides Agenda for Prelim. Des. Rvw. Mtg.

(PDRM)

0 days Wed 11/22/23 Wed 11/22/23 Tue 11/14/23

53 PRELIMINARY DESIGN REVIEW MTG.‐ PACKAGE B 2 days Tue 11/28/23 Wed 11/29/23 Mon 11/20/23

54 Contractor Prepares & Delivers Minutes Of PDRM 5 days Thu 11/30/23 Wed 12/6/23 Wed 11/22/23

55 BOP Issues NTP For Final Design Phase ‐ Package B 0 days Wed 11/29/23 Wed 11/29/23 Tue 11/21/23

56 Contractor Prepares Corrected Preliminary Design Documents

10 days Thu 11/30/23 Wed 12/13/23 Wed 11/22/23

11/8

12/25

1/15

1/17

2/7

2/14

2/21

2/28

3/13

10/30

11/20

11/22

11/29

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 H

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Project: Leavenworth FCI

57 Contractor Distributes Corrected Preliminary Design Documents

0 days Wed 12/13/23 Wed 12/13/23 Tue 12/5/23

58 FINAL DESIGN PHASE ‐ PACKAGE B 162 days Thu 11/30/23 Fri 7/12/24Wed 11/22/23

59 Develop Final Design Documents 100 days Thu 11/30/23 Wed 4/17/24 Wed 11/22/23

60 Submit Final Design Documents 0 days Wed 4/17/24 Wed 4/17/24 Tue 4/9/24

61 BOP Reviews Final Design Documents 15 days Thu 4/18/24 Wed 5/8/24 Wed 4/10/24

62 BOP Delivers Design Review Report to Contractor 0 days Wed 5/8/24 Wed 5/8/24 Tue 4/30/24

63 Contractor Prepares Response to Des. Rvw. Rpt. 5 days Thu 5/9/24 Wed 5/15/24 Wed 5/1/24

64 Contractor Provides Agenda for Final Des. Rvw. Mtg. (FDRM0 days Fri 5/10/24 Fri 5/10/24 Thu 5/2/24

65 FINAL DESIGN REVIEW MTG.‐ PACKAGE B 2 days Thu 5/16/24 Fri 5/17/24 Wed 5/8/24

66 Contractor Prepares & Delivers Minutes Of FDRM 5 days Mon 5/20/24 Fri 5/24/24 Fri 5/10/24

67 Contractor Prepares Updated Project Documents 10 days Mon 5/20/24 Fri 5/31/24 Fri 5/10/24

68 Contractor Delivers Updated Project Documents 0 days Fri 5/31/24 Fri 5/31/24 Thu 5/23/24

69 BOP Reviews Updated Project Documents 10 days Mon 6/3/24 Fri 6/14/24 Fri 5/24/24

70 BOP Delivers Comments on Updated Documents 0 days Fri 6/14/24 Fri 6/14/24 Thu 6/6/24

71 Contractor Prepares Corrected Project Documents 5 days Mon 6/17/24 Fri 6/21/24 Fri 6/7/24

72 Contractor Delivers Corrected Project Documents 0 days Fri 6/21/24 Fri 6/21/24 Thu 6/13/24

73 BOP Reviews Corrected Project Documents 5 days Mon 6/24/24 Fri 6/28/24 Fri 6/14/24

74 BOP Approves Corrected Project Documents; Issues NTP For Package B Construction

0 days Fri 6/28/24 Fri 6/28/24 Thu 6/20/24

75 Contractor Distributes Package B "Construction Issue" Documents

0 days Fri 7/12/24 Fri 7/12/24 Thu 7/4/24

76 Contractor Submits Certified Fire Safety Report 0 days Fri 7/12/24 Fri 7/12/24 Thu 7/4/24

77 CPM SCHEDULE DEVELOPMENT 199 days Tue 9/5/23 Fri 6/7/24 Mon 8/28/23

78 PROJECT SCHEDULE REQUIREMENTS/ PROPOSED DESIGN‐

BUILD SCHEDULE REVIEW MEETING

2 days Tue 9/5/23 Wed 9/6/23 Mon 8/28/23

79 Submit Project Schedule (Logic) (w/ Preliminary Design Documents)

0 days Mon 10/2/23 Mon 10/2/23 Fri 9/22/23

80 BOP Review of Project Schedule (Logic) 10 days Tue 10/3/23 Mon 10/16/23 Mon 9/25/23

81 BOP Delivers Project Schedule (Logic) Review Report 0 days Mon 10/16/23 Mon 10/16/23 Fri 10/6/23

82 Contractor Prepares Response to Project Schedule (Logic) Review Report

5 days Tue 10/17/23 Mon 10/23/23 Mon 10/9/23

83 PROJECT SCHEDULE LOGIC REVIEW MEETING 2 days Tue 10/24/23 Wed 10/25/23 Mon 10/16/23

84 Submit Project Schedule (Revised Logic; Loading) for Package A (w/ Package A Final Design Documents)

0 days Mon 12/25/23 Mon 12/25/23 Fri 12/15/23

85 BOP Review of Project Schedule (Loading) Package A 15 days Tue 12/26/23 Mon 1/15/24 Mon 12/18/23

12/13

4/17

5/8

5/10

5/31

6/14

6/21

6/28

7/12

7/12

10/2

10/16

12/25

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 H

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Project: Leavenworth FCI

86 BOP Delivers Project Schedule (Loading) Review Report‐ Package A

0 days Mon 1/15/24 Mon 1/15/24 Fri 1/5/24

87 Contractor Prepares Response to Project Schedule (Loading) Review Report‐ Package A

5 days Tue 1/16/24 Mon 1/22/24 Mon 1/8/24

88 PROJECT SCHEDULE LOADING REVIEW MEETING‐ PACKAGE 2 days Tue 1/23/24 Wed 1/24/24 Mon 1/15/24

89 Submit Revised Loading for Package. A 0 days Wed 1/31/24 Wed 1/31/24 Tue 1/23/24

90 BOP Review Of Revised Loading for Package A 5 days Thu 2/1/24 Wed 2/7/24 Wed 1/24/24

91 BOP Acceptance of Loading Package A 0 days Wed 2/7/24 Wed 2/7/24 Tue 1/30/24

92 Submit Project Schedule (Revised Logic; Loading) for Package B (w/ Package B Final Design Documents)

0 days Wed 4/17/24 Wed 4/17/24 Tue 4/9/24

93 BOP Review of Project Schedule (Loading) Package B 15 days Thu 4/18/24 Wed 5/8/24 Wed 4/10/24

94 BOP Delivers Project Schedule (Loading) Review Report‐ Package B

0 days Wed 5/8/24 Wed 5/8/24 Tue 4/30/24

95 Contractor Prepares Response to Project Schedule (Loading) Review Report‐ Package B

5 days Thu 5/9/24 Wed 5/15/24 Wed 5/1/24

96 PROJECT SCHEDULE LOADING REVIEW MEETING‐ PACKAGE 2 days Thu 5/16/24 Fri 5/17/24 Wed 5/8/24

97 Submit Revised Loading for Package. B 0 days Fri 5/24/24 Fri 5/24/24 Thu 5/16/24

98 BOP Review Of Revised Loading for Package B 10 days Mon 5/27/24 Fri 6/7/24 Fri 5/17/24

99 BOP Acceptance of Loading Package B 0 days Fri 6/7/24 Fri 6/7/24 Thu 5/30/24

100 CONSTRUCTION ‐ EARLY SITEWORK 150 days Mon 10/2/23 Mon 4/29/24 Fri 9/22/23

101 BOP Issues NTP For Early Sitework Construction 0 days Mon 10/2/23 Mon 10/2/23 Fri 9/22/23

102 Early Sitework Construction 150 days Tue 10/3/23 Mon 4/29/24 Mon 9/25/23

103 CONSTRUCTION ‐ PACKAGE A 210 days Wed 2/28/24Wed 12/18/24 Tue 2/20/24

104 BOP Issues NTP For Package A Construction 0 days Wed 2/28/24 Wed 2/28/24 Tue 2/20/24

105 Procurement of Long Lead Equipment and Materials 200 days Thu 2/29/24 Wed 12/4/24 Wed 2/21/24

106 Package A Construction 210 days Thu 2/29/24 Wed 12/18/24 Wed 2/21/24

107 CONSTRUCTION ‐ PACKAGE B 467 days Fri 6/28/24 Tue 4/14/26 Thu 6/20/24

108 BOP Issues NTP For Package B Construction 0 days Fri 6/28/24 Fri 6/28/24 Thu 6/20/24

109 Package B Construction 467 days Mon 7/1/24 Tue 4/14/26 Fri 6/21/24

110 Date of Substantial Completion (90 Calendar Days Prior To Final Acceptance)

0 days Wed 1/14/26 Wed 1/14/26 Tue 1/6/26

111 Inspection/Correction/Closeout/Final Inspection 64 days Thu 1/15/26 Tue 4/14/26 Wed 1/7/26

112 Final Acceptance By BOP 0 days Tue 4/14/26 Tue 4/14/26 Mon 4/6/26

113 CONTRACT COMPLETION DATE 0 days Tue 4/14/26 Tue 4/14/26 Mon 4/6/26

1/15

1/31

2/7

4/17

5/8

5/24

6/7

10/2

2/28

6/28

1/14

4/14

4/14

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 H

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Project: Leavenworth FCI

File details come from the government source that posted it. Updated .