The file's text, extracted by GovTribe without its formatting.
2026 Pricing
| STATE OF FLORIDA |
| DEPARTMENT OF TRANSPORTATION |
| ERROR:#VALUE! |
| EXHIBIT C - PRICE PROPOSAL |
| DOT-RFP-26-6202SD-REBID |
| DISTRICT SIX INTELLIGENT TRANSPORTATION SYSTEMS |
| (ITS) / TRANSPORTATION MANAGEMENT CENTER (TMC) |
| OPERATIONS CONTRACT |
FINANCIAL PROJECT NUMBERS: 434665-2-82-01,
435506-4-82-01, 439031-3-82-01, 445023-1-82-01, 445023-2-82-01, 445023-3-82-01, 445023-4-82-01, 445023-5-82-01, AND
445023-6-82-01
| The Consultant named below agrees that If this agreement is renewed, it shall be renewed for the same terms, and conditions as set forth in the original agreement. (see Special Condition 32) | |
| Company Name | |
| Company FEID Number | |
| Authorized Signature | |
| Type or Print Name | |
| Title | |
| Address | |
| City, State, Zip | |
| Telephone | Fax |
| E-mail Address | |
By signing above, the Consultant acknowledges they have read and understood the RFP Instructions and the complete procurement package and acknowledge that the lump sum and loaded billing rates submitted in this Price Proposal includes the Consultant’s staff salaries, overhead, fringe benefits, sub-consultant costs, allowable expenses and operating margin necessary for the Consultant to perform the described services.
| SECTION 1 |
| LUMP SUM - PROGRAM AND TMC MANAGEMENT SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the Program and TMC Management Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For Program and TMC Management Services” lump sum amount.
| (1.1) PROGRAM AND TMC MANAGEMENT SERVICES (Lump Sum) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| Project Manager | 2,080 | 2,080 | $ - 0 | $ - 0 |
| TMC Office Manager/Executive Administrative Assistant | 2,080 | 2,080 | $ - 0 | $ - 0 |
| TMC Receptionist | 2,080 | 2,080 | $ - 0 | $ - 0 |
| TMC Manager | 2,080 | 2,080 | $ - 0 | $ - 0 |
| Assistant TMC Manager | 2,080 | 2,080 | $ - 0 | $ - 0 |
| QA/QC Event Manager | 2,080 | 2,080 | $ - 0 | $ - 0 |
| Construction Coordinator | 2,080 | 2,080 | $ - 0 | $ - 0 |
| Special Projects Technical Coordinator | 480 | 480 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 1.1 = | $ - 0 |
| YEAR 1 COSTS (Amount in Subtotal 1.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 1: TOTAL 5 YEAR CONTRACT TERM COSTS FOR PROGRAM AND TMC MANAGEMENT SERVICES: | $ - 0 |
| SECTION 2 |
| LUMP SUM - FREEWAY OPERATIONS SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the Freeway Operations Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For Freeway Operations Services” lump sum amount.
| (2.1) FREEWAY OPERATIONS SERVICES (Lump Sum) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| Shift Supervisor(s) | 8,760 | 8,760 | $ - 0 | $ - 0 |
| Freeway Operator(s) | 17,520 | 17,520 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 2.1 = | $ - 0 |
| YEAR 1 COSTS (Amount in Subtotal 2.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 2: TOTAL 5 YEAR CONTRACT TERM COSTS FOR FREEWAY OPERATIONS SERVICES: | $ - 0 |
| SECTION 3 |
| LUMP SUM - ARTERIAL OPERATIONS SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the Arterial Operations Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For Arterial Operations Services” lump sum amount.
| (3.1) ARTERIAL OPERATIONS SERVICES (Lump Sum) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| Arterial Operations Program Manager | 2,080 | 2,080 | $ - 0 | $ - 0 |
| Arterial Operator(s) | 4,160 | 4,160 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 3.1 = | $ - 0 |
| YEAR 1 COSTS (Amount in Subtotal 3.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 3: TOTAL 5 YEAR CONTRACT TERM COSTS FOR ARTERIAL OPERATIONS SERVICES: | $ - 0 |
| SECTION 4 |
| LUMP SUM – EXPRESS LANES AND RAMP SIGNALING OPERATIONS SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the Express Lanes and Ramp Signaling Operations Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For Express Lanes and Ramp Signaling Operations Services” lump sum amount.
| (4.1) 95 EXPRESS LANES AND RAMP SIGNALING OPERATIONS SERVICES (Lump Sum) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| Express Lanes and Ramp Signaling Operations Program Manager | 1,040 | 1,040 | $ - 0 | $ - 0 |
| 95 Express Lanes Shift Supervisor(s) | 4,160 | 4,160 | $ - 0 | $ - 0 |
| Express Lanes Operator(s) | 14,600 | 14,600 | $ - 0 | $ - 0 |
| Ramp Signaling Operator(s) | 4,160 | 4,160 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 4.1 = | $ - 0 |
| (4.2) 75/826 EXPRESS LANES AND RAMP SIGNALING OPERATIONS SERVICES (Lump Sum) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| Express Lanes and Ramp Signaling Operations Program Manager | 1,040 | 1,040 | $ - 0 | $ - 0 |
| 75/826 Express Lanes Shift Supervisor(s) | 4,160 | 4,160 | $ - 0 | $ - 0 |
| Express Lanes Operator(s) | 8,760 | 8,760 | $ - 0 | $ - 0 |
| Ramp Signaling Operator(s)* | 4,160 | 4,160 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 4.2 = | $ - 0 |
| *Ramp Signaling Services on the 75/826 Express Lanes are not anticipated to be active at the start of the Contract. FDOT will reduce the year one cost by the "Ramp Signal Operator(s)" pricing related to the hours programmed for Ramp Signaling Operations on the 75/826 Express Lanes until operations begin. The TSM&O Program Engineer shall provide written notice to the Consultant upon determination of the start date for these services, at which time compensation shall be rendered on a pro‑rated basis. | | | | |
| YEAR 1 COSTS (Sum of Subtotals 4.1 and 4.2) = | | | | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | | | | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | | | | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | | | | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | | | | $ - 0 |
| SECTION 4: TOTAL 5 YEAR CONTRACT TERM COSTS FOR EXPRESS LANES AND RAMP SIGNALING OPERATIONS SERVICES: | | | | $ - 0 |
| SECTION 5 |
| LUMP SUM – INCIDENT MANAGEMENT PROGRAM SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the Incident Management Program Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For Incident Management Program Services” lump sum amount.
| (5.1) INCIDENT MANAGEMENT PROGRAM SERVICES (Lump Sum) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| Incident Management Program Manager | 2,080 | 2,080 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 5.1 = | $ - 0 |
| YEAR 1 COSTS (Amount in Subtotal 5.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 5: TOTAL 5 YEAR CONTRACT TERM COSTS FOR INCIDENT MANAGEMENT PROGRAM SERVICES: | $ - 0 |
| SECTION 6 |
| LOADED BILLING RATE – INCIDENT RESPONSE VEHICLE OPERATIONS SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, operating margin, and costs related to IRV Units, equipment, and storage. Payment for expenses shall be made on the basis of actual allowable cost incurred, less any applicable deductions, as authorized and approved by the Department. The Lump Sum for the Incident Response Vehicle Operations Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For Incident Response Vehicle Operations Services”.
| (6.1) INCIDENT RESPONSE VEHICLE OPERATIONS SERVICES * (Loaded Billing Rate) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| I-75 IRV Operator | 4,160 | 4,160 | $ - 0 | $ - 0 |
| I-95 IRV Operator | 6,240 | 6,240 | $ - 0 | $ - 0 |
| SR 826 IRV Operator | 4,160 | 4,160 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 6.1 = | $ - 0 |
| * This is a “Loaded Billing Rate” service and the amount indicated under Subtotal 6.1 shall be considered the annual “Maximum Limiting Amount” for this service for the term of this Contract. Although the Consultant’s loaded billing rate includes the cost of fuel for the Incident Response Vehicle services, the Department has established a “Fuel Cost Adjustment” clause for the benefit of both parties. Exhibit A-2 - Supplemental Incident Response Vehicle Operations Requirements describes how fuel price adjustments shall be made. | | | | |
The quantities listed under this section are estimated and they are not guaranteed. The Consultant shall only be compensated for the actual hours worked and for the actual services provided and verified by the Department. The Department reserves the right to use funding not used for this service for other Agreement services.
| YEAR 1 COSTS (Amount in Subtotal 6.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 6: TOTAL 5 YEAR CONTRACT TERM COSTS FOR INCIDENT RESPONSE VEHICLE OPERATIONS SERVICES: | $ - 0 |
| SECTION 7 |
| LUMP SUM – COMMUNITY OUTREACH AND CUSTOMER SUPPORT SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the Community Outreach and Customer Support Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For Community Outreach and Customer Support Services” lump sum amount.
| (7.1) COMMUNITY OUTREACH AND CUSTOMER SUPPORT SERVICES (Lump Sum) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| Community Outreach Specialist | 2,080 | 2,080 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 7.1 = | $ - 0 |
| YEAR 1 COSTS (Amount in Subtotal 7.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 7: TOTAL 5 YEAR CONTRACT TERM COSTS FOR COMMUNITY OUTREACH AND CUSTOMER SUPPORT SERVICES: | $ - 0 |
| SECTION 8 |
| LUMP SUM – TMC INFORMATION TECHNOLOGY SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the TMC Information Technology Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For TMC Information Technology Services” lump sum amount.
| (8.1) TMC INFORMATION TECHNOLOGY SERVICES (Lump Sum) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| IT Manager | 2,080 | 2,080 | $ - 0 | $ - 0 |
| Network Administrator | 2,080 | 2,080 | $ - 0 | $ - 0 |
| System Administrator | 2,080 | 2,080 | $ - 0 | $ - 0 |
| Software Developer | 2,080 | 2,080 | $ - 0 | $ - 0 |
| Senior Software Developer | 1,040 | 1,040 | $ - 0 | $ - 0 |
| IT Technician(s) | 6,656 | 6,656 | $ - 0 | $ - 0 |
| Procurement and Inventory Specialist | 2,080 | 2,080 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 8.1 = | $ - 0 |
| YEAR 1 COSTS (Amount in Subtotal 8.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 8: TOTAL 5 YEAR CONTRACT TERM COSTS FOR TMC INFORMATION TECHNOLOGY SERVICES: | $ - 0 |
| SECTION 9 |
| LUMP SUM – ITS UTILITY LOCATES SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the ITS Utility Locates Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For ITS Utility Locates Services” lump sum amount.
| (9.1) ITS UTILITY LOCATES SERVICES (LUMP SUM) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | Subtotal 9.1 = | $ - 0 |
| YEAR 1 COSTS (Amount in Subtotal 9.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 9: TOTAL 5 YEAR CONTRACT TERM COSTS FOR ITS UTILITY LOCATES SERVICES: | $ - 0 |
| SECTION 10 |
| LUMP SUM – IT DATA ARCHITECT SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the IT Data Architect Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amounts for the specified service. The sum of the Subtotal amount(s) shall be used to derive an annual cost labeled as “Year 1 Costs.” The Year 1 Costs value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For IT Data Architect Services” lump sum amount.
| (10.1) IT DATA ARCHITECT SERVICES (LUMP SUM) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| IT Data Architect III (Construction Office) | 2,080 | 2,080 | $ - 0 | $ - 0 |
| IT Data Architect II (Traffic Operations Office) | 2,080 | 2,080 | $ - 0 | $ - 0 |
| | | $ - 0 | $ - 0 |
| | | $ - 0 | $ - 0 |
| | | $ - 0 | $ - 0 |
| | | $ - 0 | $ - 0 |
| | | $ - 0 | $ - 0 |
| | | $ - 0 | $ - 0 |
| | | Subtotal 10.1 = | $ - 0 |
| YEAR 1 COSTS (Amount in Subtotal 10.1) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable): | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable): | $ - 0 |
| SECTION 10: TOTAL 5 YEAR CONTRACT TERM COSTS FOR IT DATA ARCHITECT SERVICES: | $ - 0 |
| SECTION 11 |
| LUMP SUM – TMC CONTRACT OVERSIGHT SERVICES |
| The job classification positions identified here shall match those provided by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, expenses, and operating margin. The Lump Sum for the TMC Contract Oversight Services is derived as follows: |
The sum of the amounts from the column labeled “Annual Cost For Job Classification” shall be used to derive the Subtotal lump sum amount for each of the specified services. The sum of the four (4) Subtotals (11.1, 11.2, 11.3, and 11.4) shall be used as the cost for the “Year 1 Costs". The "Year 1 Cost" value shall then be copied to each of the Year 2 through Year 5 Costs. The sum of the Year 1 through Year 5 Costs shall comprise the “Total 5 Year Contract Term Costs For TMC Contract Oversight Services" lump sum amount.
| (11.1) FHP Contract Oversight (LUMP SUM) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | Subtotal 11.1 = | $ - 0 |
| (11.2) Road Ranger Contract Oversight (LUMP SUM) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | Subtotal 11.2 = | $ - 0 |
| (11.3) RISC Contract Oversight (LUMP SUM) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | Subtotal 11.3 = | $ - 0 |
| (11.4) ITS Maintenance Contract Oversight (LUMP SUM) | |
| Job Classification | Minimum |
Required Annual Hours Additional Annual Hours Total Annual Hours Loaded Billing Rate (Per Hour) Annual Cost For Job Classification
| ITS Maintenance Contract Coordinator | 2,080 | 2,080 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| 0 | 0 | $ - 0 | $ - 0 |
| | | Subtotal 11.4 = | $ - 0 |
| YEAR 1 COSTS (Sum of Subtotals 11.1, 11.2, 11.3, and 11.4) = | $ - 0 |
| YEAR 2 COSTS (Price Escalation Not Allowable) = | $ - 0 |
| YEAR 3 COSTS (Price Escalation Not Allowable) = | $ - 0 |
| YEAR 4 COSTS (Price Escalation Not Allowable) = | $ - 0 |
| YEAR 5 COSTS (Price Escalation Not Allowable) = | $ - 0 |
| SECTION 11: TOTAL 5 YEAR CONTRACT TERM COSTS FOR TMC CONTRACT OVERSIGHT SERVICES: | $ - 0 |
| SECTION 12 |
| LOADED BILLING RATE – MISCELLANEOUS TSM&O AND TRAFFIC OPERATIONS SERVICES |
| The Department has pre-established a $3,500,000 budgetary ceiling or $700,000/year cap over the five year contract term for Miscellaneous TSM&O and Traffic Operations Services. The Department shall not guarantee any minimum or maximum amount of work under this section. The Department, at its sole discretion shall assign work on an as-needed basis and may decrease or increase the pre-established cap or use for other services specified in the scope of services. |
The staff noted here shall be the same staff listed by the Consultant in the Technical Proposal. The loaded billing rates for the job classifications listed below shall include the Consultant’s staff salaries, overhead, fringe benefits, and operating margin. Payment for expenses shall be made on the basis of actual allowable cost incurred, less any applicable deductions, as authorized and approved by the Department. These billing rates shall be a “Loaded Billing Rate” for the duration of the five (5) year contract term. Work assignments shall be negotiated by the parties based on the billing rates established below.
| (12.1) MISCELLANEOUS TSM&O AND TRAFFIC OPERATIONS SERVICES (LOADED BILLING RATE) | |
| JOB CLASSIFICATION | LOADED |
BILLING RATE
(Per Hour)
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| $ - 0 |
| YEAR 1 COSTS (Department Pre-established Amount): | $ 700,000.00 |
| YEAR 2 COSTS (Department Pre-established Amount): | $ 700,000.00 |
| YEAR 3 COSTS (Department Pre-established Amount): | $ 700,000.00 |
| YEAR 4 COSTS (Department Pre-established Amount): | $ 700,000.00 |
| YEAR 5 COSTS (Department Pre-established Amount): | $ 700,000.00 |
| SECTION 12: TOTAL 5 YEAR CONTRACT TERM COSTS FOR MISCELLANEOUS TSM&O AND TRAFFIC OPERATIONS SERVICES: * | $ 3,500,000.00 |
| * The Department reserves the right to use funding not used for this service for other Contract services. | |
| SECTION 13 | | |
| LUMP SUM – TRANSITION SERVICES | | |
| The Department expects the successful Consultant that wins this procurement to transition services from the incumbent ITS Operations Consultant for the period noted in the Consultant’s Technical Proposal. The Department shall provide the Consultant a pre-established amount for the Consultant to transition. This amount is not intended to cover all the successful Consultant costs for this service. If the amount provided is not sufficient to cover these costs, then the Consultant shall build into all the other services being priced the difference in what is being provided and what it will actually cost the Consultant. | | |
| SECTION 13: TOTAL FOR TRANSITION SERVICES: | $ 50,000.00 |
| Pricing Summary | |
| TOTAL COSTS FOR SECTION 1: | |
| PROGRAM AND TMC MANAGEMENT SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 2: | |
| FREEWAY OPERATIONS SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 3: | |
| ARTERIAL OPERATIONS SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 4: | |
| EXPRESS LANES AND RAMP SIGNALING OPERATIONS SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 5: | |
| INCIDENT MANAGEMENT PROGRAM SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 6: | |
| INCIDENT RESPONSE VEHICLE OPERATIONS SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 7: | |
| COMMUNITY OUTREACH AND CUSTOMER SUPPORT SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 8: | |
| TMC INFORMATION TECHNOLOGY SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 9: | |
| ITS UTILITY LOCATES SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 10: | |
| IT DATA ARCHITECT SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 11: | |
| TMC CONTRACT OVERSIGHT SERVICES | | $ - 0 |
| TOTAL COSTS FOR SECTION 12: | |
MISCELLANEOUS TSM&O AND TRAFFIC OPERATIONS SERVICES
| (Department Pre-Established Amount) | | $ 3,500,000.00 |
| TOTAL COSTS FOR SECTION 13: | |
TRANSITION SERVICES
(Department Pre-Established Amount) $ 50,000.00
| TOTAL PRICE PROPOSAL FOR | |
| DOT-RFP-26-6202SD | | $ 3,550,000.00 |
| NOTE: The Price Proposal with lowest total price shall receive the maximum points allowed under the evaluation criteria. | |
&"Arial,Regular"&14DOT-RFP-26-6202SD-REBID &14Exhibit C &"Arial,Regular"&14Page &P of &N