EXHIBIT C - LIQUIDATED DAMAGES.pdf

PDF 183 KB Posted

Attached to
Corrosion Control System Upgrades
Solicitation number
OP138382(2)
Issued by
California

About this file

This is an Exhibit C document outlining liquidated damages provisions for a contract with Metro PM. The contract establishes a project schedule with defined milestones outlined in Section 1.05 of the Scope of Services (Exhibit A). The contractor is obligated to complete all milestones within specified timeframes, with any delays beyond the designated periods resulting in financial penalties. Metro PM retains discretionary authority to waive liquidated damages if circumstances warrant such action.

Liquidated damages are assessed at a daily rate of $1,962.00 per calendar day for each missed milestone. The financial liability for any individual missed milestone is capped at 14 days of damages, regardless of the actual duration of the delay. This maximum cap applies uniformly across all milestones, meaning that even if a milestone is delayed beyond 14 days, the total liquidated damages charge for that specific milestone cannot exceed the equivalent of 14 days' worth of penalties. The structure ensures predictable financial exposure while incentivizing timely milestone completion.

View the file

Other files

File Type Posted
EXHIBIT E-1 - PAYMENT CERTIFICATION (CONTINUOUS).pdf PDF
EXHIBIT A - SOW 7.23.26.pdf PDF
A LINE DRAWING.pdf PDF
EXHIBIT 12 - MINIMUM QUALIFICATIONS.pdf PDF
FORM 3 - BUSINESS DATA SHEET.pdf PDF
FORM 1 - SBE-DVBE SUBS & SUPPLIERS.pdf PDF
FORM 6 - SBE-DVBE DEALER-DISTR AFFIRMATION.pdf PDF
FORM 4 - SBE-DVBE AFFIRMATION.pdf PDF
IFB No. OP138382(2).pdf PDF
EXHIBIT B - PRICING AGREEMENT.pdf PDF
EXHIBIT F - RELEASE OF CLAIMS.pdf PDF
EXHIBIT H - DELIVERABLES AND PAYMENT SCHEDULE.pdf PDF
E LINE DRAWING.pdf PDF
EXHIBIT 15 - BID BOND.pdf PDF
EXHIBIT 7 - LIST OF COMPLETED CONTRACTS - LAST FIVE (5) YEARS.pdf PDF
EXHIBIT 5 - BID LETTER.pdf PDF
SUBCONTRACTOR LISTING FORM.pdf PDF
EXHIBIT E-2 - PAYMENT CERTIFICATION (FINAL).pdf PDF
C LINE DRAWING.pdf PDF
EXHIBIT 8 - ETHICS DECLARATION.pdf PDF
EXHIBIT 11 - NONCOLLUSION AFFIDAVIT TO BE EXECUTED BY BIDDER.pdf PDF
EXHIBIT 9 - GENERAL CERTIFICATIONS.pdf PDF
FORM 5 - BIDDERS LIST FORM.pdf PDF
EXHIBIT 13 - CERTIFICATION OF PROSPECTIVE CONTRACTOR.pdf PDF
EXHIBIT 16 PERFORMANCE AND PAYMENT BOND.pdf PDF
EXHIBIT G - APPROVED SUBCONTRACTORS AND SUPPLIERS.pdf PDF
EXHIBIT D - DEOD CONTRACT COMPLIANCE MANUAL (Non-Fed).pdf PDF
B D LINE DRAWING.pdf PDF
EXHIBIT 10 - CERTIFICATE OF COMPLIANCE WITH 49 CFR PART 655.pdf PDF
FORM 2 - AFFIDAVIT.pdf PDF
EXHIBIT 3 - RESERVED.pdf PDF
EXHIBIT 4 - LIST OF CERTIFIED FIRMS.pdf PDF
EXHIBIT 2 - SCHEDULE OF QUANTITIES AND PRICES.pdf PDF
EXHIBIT 6 - LIST OF CURRENT CONTRACTS - BACKLOG.pdf PDF
EXHIBIT 14 -PUBLIC WORKS VERIFICATION FORM.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT C - LIQUIDATED DAMAGES

A. For purposes of this Contract, the Parties agree to Liquidated Damages, as described below, because it will be impracticable or extremely difficult to ascertain or fix the actual damages which Metro will sustain. Metro PM may choose to waive liquidated damages at Metro PM’s discretion.

B. Project Schedule (Section 1.05 Project Schedule of the Scope of Services, Exhibit A): Contractor shall complete all milestones in Section 1.05 Project Schedule of the Scope of Services in accordance with the time period specified for each Milestone. Any delays beyond the time period specified for each Milestone will result in liquidated damages in the amount of $1,962.00 (One thousand nine hundred sixty-two dollars) per calendar day.

C. Maximum Cap: For each individual missed milestone a liquid damages charge will be imposed. This charge is calculated based on a daily rate with a maximum cap of 14 days for each missed milestone .

D. Multiple Missed Milestones: the total amount of liquidated damages for each individual missed milestone shall not exceed the sum of 14 days for any given missed milestone. The financial impact will be limited to the equivalent of 14 days worth of damages regardless of how many additional days the milestone is delayed.

File details come from the government source that posted it. Updated .