This Exhibit A is a Statement of Work (SOW) for the Los Angeles County Metropolitan Transportation Authority (LACMTA) regarding systemwide corrosion control equipment replacement across the Metro rail system. The project involves upgrading existing cathodic protection systems at multiple locations across Metro Lines A, B, C, D, E, and K, including passenger stations, yards, and related facilities throughout Los Angeles County. The scope of work includes furnishing and installing new anodes, test stations, and replacement cathodic protection equipment; removing existing depleted equipment; installing new electrical isolation systems; and performing comprehensive system testing to ensure proper installation and adequate corrosion protection. Work locations span from Division 21 Yard in Los Angeles to Division 11 Yard in Long Beach, with passenger station upgrades at numerous locations including North Hollywood Station, Hollywood/Highland Station, Union Square Station, Norwalk Station, Lakewood Station, and others. The contractor must coordinate all work with Metro's Rail and Facilities Maintenance staff without interrupting existing revenue train operations and comply with all submittals, shop drawings, testing procedures, and as-built documentation requirements within 30 days of equipment placement in service.
The project is classified as safety-sensitive work requiring FTA-compliant drug and alcohol policies, MRO-verified pre-employment drug testing, and DOT background checks for all covered employees. The contractor must engage a NACE/AMPP Certified Cathodic Protection Specialist for all field commissioning and system testing and must comply with NFPA 70E electrical safety standards, recognizing that work in the operating railroad environment may involve hazardous DC voltage exposures exceeding 50 volts. The contractor bears responsibility for all labor, materials, equipment, permits, and coordination with third parties including LADWP, local jurisdictions, and other contractors. Metro will perform pre-construction work including coordination with elevator replacement contractors and provide access based on a mutually agreed schedule. The contract requires the contractor to furnish spare parts, operation and maintenance manuals, special test equipment, and training for ongoing maintenance and monitoring of the upgraded corrosion control systems.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LACMTA SYSTEMWIDE 01 10 00 – 1 SUMMARY OF WORK
CORROSION CONTROL REV. 0
EQUIPMENT REPLACEMENT JULY 2026
SECTION 01 11 00
SUMMARY OF WORK
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Statement of work.
1. Description and background.
2. Project locations.
3. Scope of work.
B. Related work.
C. Standard specifications.
D. Submittals.
E. Reference drawings
F. Contractor’s duties.
G. Contractor's use of site.
1.02 RELATED SECTIONS
A. Section 01 33 00: Submittal Procedures
B. Section 01 71 43: Permits, Licensing, and Approvals
C. Section 26 42 00: Cathodic Protection Systems
D. Section 33 00 00: Piped Utilities
1.03 DESCRIPTION AND BACKGROUND:
A. The LACMTA system Passenger A, B, C, D and E Lines have corrosion control measures in place to mitigate external side corrosion of buried metallic structures such as pipelines and elevator steel cylinder casings. Corrosion control in the form of cathodic protection was installed during the original construction of each subgrade passenger station and TPSS with buried firewater/water piping. Many upgrades to these corrosion control systems are necessary to extend the service life of the structures intended for external side corrosion protection.
B. The principal elements include the Contract Specifications & Drawings and reference drawings that include details on the required upgrades.
C. The Los Angeles County Metropolitan Transportation Authority (referred hereafter as Metro) is seeking a General Contractor Company, referred hereinafter as the Contractor, to provide all services and materials delineated in the specification and drawings.
D. The Contractor shall provide services for the materials supply, installation, and subsequent testing associated with the following items:
7.23.26
LACMTA SYSTEMWIDE 01 10 00 – 2 SUMMARY OF WORK
EQUIPMENT REPLACEMENT JULY 2026
1. Upgrading existing cathodic protection systems by installing new anodes, new test stations and replacing any existing cathodic protection equipment as shown in the drawings.
2. Removal of existing equipment to be replaced shall be performed for test stations and terminal boards as shown in the drawings. Removal or abandonment of existing depleted anodes shall be at the discretion of the Contractor except in the case of the elevator casing anodes which are to be removed prior to replacement.
3. Install new electrical isolation at the noted locations and testing to confirm adequate electrical isolation on piping in vaults. Testing of the remaining electrical isolation within the vaults shall be completed to confirm adequate working conditions or any changes in condition in electrical isolation status.
4. Perform system testing for all components to ensure proper installation and adequate corrosion control for the protected structures. All field commissioning shall be conducted or under the supervision of a Cathodic Protection Specialist once replacements are completed. Cathodic Protection Specialist shall be NACE/AMPP Certified.
E. The replacement components of the corrosion control systems shall comply with these principal elements and shall improve upon the existing equipment installed.
F. Corrosion control system upgrades shall be in strict coordination with Metro's Rail and Facilities Maintenance staff and shall not interrupt the existing revenue train(s) operations. All work shall be performed in a workman like manner and to the highest professional standards using the highest qualified and professional work force.
G. The existing corrosion control equipment are located in Metro Passenger Line underground stations, Related Yards and at aboveground locations in public areas.
H. Existing Metro Stations listed in Section 1.04.A may require additional corrosion protection at their critical infrastructure equipment; such as elevators, escalators, or metal roof canopies. The Contractor will install new test wells to monitor these components. This work is being defined as Additional Corrosion Protection Equipment Installations. These additional test wells will be installed similar to existing Metro Corrosion Protection equipment. Metro will work closely with the contactor to identify each location.
1.04 PROJECT LOCATIONS
A. Metro desires to upgrade the existing corrosion control systems and related equipment at the following locations:
1. Metro A Line Yards
Division 21 Yard 1800 Baker St, Los Angeles, CA 90012
Division 11 Yard 4350 E 208th St, Long Beach, CA 9081
2. Metro B and D Line Passenger Stations Los Angeles, CA
North Hollywood Station
Universal City Station
Hollywood/Highland Station
LACMTA SYSTEMWIDE 01 10 00 – 3 SUMMARY OF WORK
EQUIPMENT REPLACEMENT JULY 2026
Hollywood/Vine Station
Hollywood/Western Station
Vermont/Sunset Station
Vermont/Santa Monica Station
Vermont/Beverly Station
Wilshire/Vermont Station
Wilshire/Normandy Station
Wilshire/Western Station
Westlake/MacArthur Park Station
7th Street/Metro Station
Pershing Square Station
Civic Center Station
Union Square Station
Additional Corrosion Protection Equipment Installations
3. Metro B and D Line Yard
Division 20 Yard 320 S Santa Fe Ave, Los Angeles, CA 90013
4. Metro C Line Passenger Stations and TCCB Los Angeles County, CA
Norwalk Station
Lakewood Station
Long Beach TCCB
Long Beach Station
Willowbrook Station
Avalon Station
Harbor Station
Harbor TCCB
Vermont Station
Crenshaw Station
Aviation/Century
Additional Corrosion Protection Equipment Installations
5. Metro E Line Passenger Stations and Facilities Los Angeles County, CA
Mariachi Station
Soto Station
East Portal
LACMTA SYSTEMWIDE 01 10 00 – 4 SUMMARY OF WORK
EQUIPMENT REPLACEMENT JULY 2026
Additional Corrosion Protection Equipment Installations
6. Metro K Line Passenger Stations and TCCB Los Angeles County, CA
Mariposa Station
El Segundo Station
Douglas Station
Redondo Beach Station
Additional Corrosion Protection Equipment Installations
B. The Contractor shall cooperate with other Contractors to the extent reasonably necessary for the performance by other Contractors of their work, and shall cause its employees, agents, officers and Subcontractors and other persons for whom Contractor may be contractually or legally responsible to so cooperate.
C. The Contractor shall cooperate with various Divisions of the Metropolitan Transportation Authority (MTA) including Rail Operations Center, Rail Operations and Maintenance of Way.
D. The work shall be performed in accordance with the following documents:
1. Los Angeles County Metropolitan Transportation Authority (LACMTA) Metro Rail Design Criteria.
2. Los Angeles County Metropolitan Transportation Authority (LACMTA) Electrical Safety Program.
3. Applicable State and Local laws, codes and regulations.
4. The Contract Technical Specifications, herein.
5. Design Drawings and shop drawings.
6. General Information: The Contractor shall furnish, install, startup/commissioning of the upgraded corrosion control systems. The Contractor shall also remove the existing corrosion control equipment as needed without interrupting the existing train operation and replace the existing corrosion control equipment according to LACMTA approved design and technical specifications.
1.05 SCOPE OF WORK:
A. The scope of work consists of furnishing materials for removing and replacing existing corrosion control equipment.
B. The Contactor shall provide a comprehensive corrosion control equipment replacement and installation plan that shall be submitted to Metro for review and approval. The Contractor shall coordinate with Metro and any other jurisdictions for work in the public right of way.
C. The Contractor shall:
1. Submit shop drawings, incorporating key elements of the Contract milestone schedule, demonstrating the ability to complete corrosion control
LACMTA SYSTEMWIDE 01 10 00 – 5 SUMMARY OF WORK
EQUIPMENT REPLACEMENT JULY 2026
system upgrades to function as intended, and the ability to perform the scope of work within the construction schedule.
2. Furnish and install the replacement corrosion control equipment in the manner and locations as shown in LACMTA approved design drawings.
3. The contractor shall coordinate the installation of all new equipment.
4. Remove, replace, and test the corrosion control equipment.
5. The Contractor shall interface and coordinate work with local agencies (Cities, Fire Authority, & other governing bodies) to obtain required permits and approvals. See specification 01 71 43 for information regarding Permits, Licenses, and Agreements.
6. Prepare test procedures, submit test reports, and commission the upgraded corrosion control systems.
7. Provide as-built drawings that accurately depict the final status of all upgraded corrosion control equipment as installed and placed in service following completion of all testing and within 30 days after the equipment is placed in service.
8. Provide recommended spare parts list and spare parts that sufficient for maintenance, testing and performing minor modifications to all equipment
9. Spare parts shall include equipment subject to normal deterioration, and recommendations of the Manufacturer, or as obvious by definition, (such as sacrificial pieces).
10. Provide operation and maintenance manuals, special test equipment and training sufficient to maintain, test and monitor the upgraded corrosion control equipment as described in the Specifications.
11. Perform integrated tests, and all other testing necessary for commissioning of the corrosion control systems.
12. The Contractor shall be aware that work within an operating railroad environment may involve exposure to hazardous electrical conditions. The traction power negative return system includes multiple interconnections, which can cause circulating DC current through bonded elements. In accordance with NFPA 70E, voltage exposures exceeding 50 volts DC are considered hazardous. Contractor personnel must be trained and qualified to recognize and mitigate risks associated with return current paths.
13. This Contract is considered safety-sensitive. The Contractor shall comply with the following:
Submit an FTA-compliant drug and alcohol policy PRIOR to the start of their safety-sensitive maintenance work
Awardee must submit MRO-verified negative pre-employment drug test results for each FTA- covered employee, prior to the first performance of safety-sensitive functions, in accordance with 49 CFR Part 655.41.
Within 30 days of commencement of award, the awardee must submit documentation of the performance of DOT drug and alcohol
LACMTA SYSTEMWIDE 01 10 00 – 6 SUMMARY OF WORK
EQUIPMENT REPLACEMENT JULY 2026
background checks for each safety-sensitive applicant who has held a DOT-covered position within the prior 24 months, in accordance with 49 CFR Part 40.25.
1.06 RELATED WORK
A. The Contractor shall coordinate with LADWP for any work related to their piping.
1.07 METRO-PERFORMED WORK
A. Several items of work will be performed by Metro. Below is a general list of areas that will have Work performed by Metro.
B. Pre-Construction Work – Coordinate with elevator replacement Contractor for scheduling of the related corrosion control system upgrades.
C. Provide access to Contractor based on mutually agreed upon schedule.
D. Contractor shall perform all other Work.
1.08 STANDARD SPECIFICATIONS
A. Work is referenced in various Sections to conform to the latest edition and supplements of the Standard Specification for Public Works Construction (SSPWC, Green Book) as adopted by the local agencies. For this Project the following apply:
1. SSPWC or other governing agency.
2. City of Los Angeles and County of Los Angeles Standards.
3. City of Los Angeles and County of Los Angeles Standards for Traffic Control
4. NFPA 70 – National Electrical Code (NEC)
5. NFPA 70E – Electrical Safety Requirements for Employees
Specific Standards:
Organization: Ref: Number: Title:
AMPP/NACE SP0169 Control of External Corrosion on Underground or Submerged Metallic Piping Systems
AMPP/NACE SP086 The Electrical Isolation of Cathodically Protected Pipelines
APTA RT-FS-S-005-03 Rev. 2 Traction Electrification Stray Current/Corrosion Control Equipment Inspection and Maintenance
6. All other applicable Federal, State, and Local regulations, and all Nationally recognized standards.
1.09 QUALITY PROGRAM REQUIREMENTS
A. The Contractor shall perform the Work included in this Section in strict accordance with the requirements of the Approved Contractor's Quality Control Program.
LACMTA SYSTEMWIDE 01 10 00 – 7 SUMMARY OF WORK
EQUIPMENT REPLACEMENT JULY 2026
1.10 SUBMITTALS
A. Refer to Section 01 33 00 – Submittal Procedures, for submittal requirements and procedures.
B. The Contractor shall submit all information required by these Specifications.
Information shall include all material cut sheets, Shop Drawings, testing procedures, and test results submitted in the approved order and in accordance with the appropriate Section of the Specifications.
C. The contractor shall provide Corporate Safety with safety data sheets for all materials listed but not limited to: epoxy, mastic, and other wax tape seals for review and approval.
1.11 REFERENCE DRAWINGS
A. As-Built drawings for the existing corrosion control systems are provided for reference only. Metro does not warrant their accuracy or completeness, and Contractor is encouraged to review each site in detail prior to substation manufacture and delivery.
PART 2 - PRODUCTS
2.01 MATERIALS
A. The Contractor shall furnish and install all material, equipment, tools, supplies, and transportation for completion of the work, unless otherwise specified in the Contract Documents.
PART 3 - EXECUTION
3.01 CONTRACTOR'S DUTIES
A. Except as otherwise specified, furnish and pay cost for the following:
1. Labor, superintendence and products.
2. Construction supplies, equipment, tools, machinery and materials.
3. Other facilities and services necessary to properly execute and complete the Work.
4. Cost of permits and coordination with third parties.
B. Pay costs of legally required sales, consumer, gross receipt and use taxes, and governmental fees and permits.
C. Perform Work in accordance with applicable codes, ordinances, rules, regulations, orders and other legal requirements of governmental bodies, public agencies, and utilities including LACMTA. Modify above-mentioned services to conform to permit requirements of City or County Agency.
D. Maintain order, safe practices, and proper conduct among the Contractor's and subcontractors' employees. LACMTA or its designee may require that disciplinary action be taken against an employee for disorderly, improper or unsafe conduct.
LACMTA SYSTEMWIDE 01 10 00 – 8 SUMMARY OF WORK
EQUIPMENT REPLACEMENT JULY 2026
Should an employee of the Contractor be dismissed from his duties as a result of that employee's misconduct, incompetence, or unsafe practices, or combinations thereof, do not rehire that employee for duration of the Contract. LACMTA shall be held harmless from such employee claim or lawsuit as a result of such dismissal.
E. Coordinate prosecution of Work with those public utilities, governmental bodies, private utilities and other Contractors, including LACMTA, performing Work on, and adjacent to, the Worksite; eliminate or minimize delays in Work and conflicts with those utilities, governmental bodies and Contractors. Confirm coordination measures for each individual case with LACMTA or its designee by memorandum.
F. Perform Work as specified, and in a timely manner. Submit Schedule of Work which will be performed at times other than during the normal eight-hour Working day, daylight hours, and five-day Working week to the LACMTA or its designee for review and approval not less than 48 hours in advance of those times. The City and County of Los Angeles require notification prior to 11:00 AM on Friday for Inspection in the following workweek. Construction operations will be confined to those hours stated in the specifications.
G. Maintain access to, and visibility of, fire hydrants, police call boxes, fire alarm boxes, standpipe connections and traffic control devices.
H. Maintain safe access to pedestrian walkways when working in the public right-of-way.
I. Salvage material on the Worksite - Reuse or salvaged material shall not be allowed.
J. Provide timely notification to all affected agencies regarding impacts of design or construction, including but not limited to the following departments and public agencies:
1. Police and Sheriff Departments
2. Fire Departments
3. Los Angeles Department of Transportation (LADOT)
4. Los Angeles County Department of Public Works (LACPW)
5. State of California Department of Transportation (Caltrans)
6. Bus and Transit Companies
7. School Districts
8. Utility Services
9. Emergency Facilities
3.02 CONTRACTOR'S USE OF WORKSITE
A. Confine Worksite operations to areas permitted by law, ordinances, permits, and Contract Documents.
B. Consider safety of Work and of people and property on, and adjacent to, Worksite when determining amount, location, movement and use of materials and equipment on Worksite.
C. Do not load site or use equipment and products that would endanger integrity of Work or third-party facilities, including utilities.
LACMTA SYSTEMWIDE 01 10 00 – 9 SUMMARY OF WORK
EQUIPMENT REPLACEMENT JULY 2026
D. Properly protect products stored on Worksite.
E. Relocate stored products that interfere with operations of LACMTA, governmental bodies, public and private utilities, and other Contractors.
F. Secure additional storage and Work areas needed for operations.
G. Coordinate scheduling of Work to be performed on private property with LACMTA or its designee, to minimize inconvenience to property owner and tenants.
H. Protect general public and residents from construction-related activities; do not unduly inconvenience those persons by construction activities. Comply with traffic control requirements of governing agency.
I. If Contractor wishes to have utilities temporarily relocated, for his own convenience, he shall arrange with utility owners, pay for work and inform the CM.
J. Restrict construction operations to areas within LACMTA Right-of-Way (ROW) Lines.
END OF SECTION 01 11 00