This is a Best Value Scoring Summary document for a Texas state and local contract opportunity (PM-1413) for roof replacement services at Jack B. Kelly, Classroom Center, and Cornette Library. Seven contractors submitted proposals for the project, with evaluation based on total bid cost (51% weight), construction time (10% weight), technical proposal (24% weight), and qualitative factors including litigation/claims history, safety/risk assessment, and quality control (10% combined weight). The evaluation process identified dGen Energy as the highest-ranked contractor based on best value scoring with a total score of 8.05, followed by AG & Sons (7.06) and CS Advantage (6.86).

The base bids ranged from $2,296,933.28 (dGen Energy, lowest cost) to $7,342,906.00 (Mikocorp), with proposed construction schedules ranging from 45 days to 430 days. dGen Energy was not awarded the contract due to non-compliance with project specifications requiring ISO insulation adhered using low-foam adhesive, as the contractor proposed a mechanically fastened system instead. AG & Sons was disqualified for non-compliance with solicitation requirements. CS Advantage was ultimately awarded the project following negotiations, with a base bid of $3,580,000.00 and a proposed construction schedule of 150 days.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NAME/DESCRIPTION: Pkg A - JBK, CC, & Cornette Lib. Roof Replacement

PROJECT NUMBER: PM-1413

PROJECT LOCATION: Jack B. Kelly, Classroom Center, & Cornette Library

OVERALL RANKING

Contractor Score Rank LBK Roofing 5.02 6 CS Advantage 6.86 3

Tecta 6.35 4

AG & Sons 7.06 2 dGen Energy 8.05 1 Lydick-Hooks 5.52 5 Mikocorp 4.82 7

COST

Contractor Base Bid Total Alt. Total Bid LBK Roofing $3,783,980.42 $0.00 $3,783,980.42 CS Advantage $3,580,000.00 $0.00 $3,580,000.00 Tecta $3,244,610.00 $0.00 $3,244,610.00

Lydick-Hooks $4,168,094.00 $0.00 $4,168,094.00 Mikocorp $7,342,906.00 $0.00 $7,342,906.00 AG & Sons $3,000,280.00 $0.00 $3,000,280.00 dGen Energy $2,296,933.28 $0.00 $2,296,933.28

Min Bid $2,296,933.28 Max Bid $7,342,906.00

SCHEDULE

Contractors Base Time Total Alt. Time Total Time

Tecta 430 0 430 CS Advantage 150 0 150 LBK Roofing 119 0 119

Lydick-Hooks 404 0 404 Mikocorp 220 0 220 dGen Energy 45 0 45 AG & Sons 60 0 60

Min Time 45 Max Time 430

BEST VALUE SCORING

Category Value Rating Score Rating Score Rating Score Rating Score Rating Score Rating Score Rating Score Rating Score Rating Score Rating Score Total Bid 51% 5.51 2.81 6.07 3.10 3.13 1.60 6.42 3.27 7.66 3.90 7.08 3.61 10.00 5.10 Construction Time 10% 1.11 0.11 3.78 0.38 2.05 0.20 3.00 0.30 7.50 0.75 1.05 0.10 10.00 1.00 Technical Proposal 24% 6.67 1.60 4.35 1.04 6.32 1.52 7.47 1.79 5.87 1.41 6.80 1.63 3.97 0.95 Litigation/Claims 5% PASS 0.50 PASS 0.50 PASS 0.50 PASS 0.50 PASS 0.50 PASS 0.50 PASS 0.50 Safety/Risk Assessment 5% FAIL 0.00 FAIL 0.00 PASS 0.50 PASS 0.50 FAIL 0.00 PASS 0.50 Quality Control 5% PASS 0.50 FAIL 0.00 PASS 0.50 PASS 0.50 PASS 0.50 PASS 0.50 FAIL 0.00

TOTAL SCORES 100% 5.52 5.02 4.82 6.86 7.06 6.35 8.05

LBK Roofing

ACCEPTABLE Examples: 1) Contract agreement cannot be reach with top ranked contractor (terms & conditions or VE).

2) After interviews, it is determined that a contractor does NOT have everything needed in their proposal that represents an accurate price and they are disqualified/they'd like to withdraw their proposal, etc.

UNACCAPTABLE Examples: Client wants a particular contractor that isn't the best value contractor per rankings below.

CSP: FINAL BEST VALUE RANKING (Tab 9)

Tecta dGen EnergyLydick-Hooks Mikocorp CS Advantage AG & Sons

Notes/Comments/Remarks: Information can be entered below to document how/why the best value contractor (as shown below) did not end up being the final contractor selected… dGen Energy was not awarded this project because the specifications required all ISO insulation to be adhered using low-foam adhesive, while the contractor proposed a mechanically fastened system.

AG & Sons was not awarded the project due to non-compliance with solicitation requirements.

CS Advantage was awarded this project after negotiations.