10021_-_Emergency_Dry_Docking_Basic_Spec_.doc
DOC document 35 KB Posted
- Attached to
- Emergency Dry Dock for Z-Drive Repairs
- Solicitation number
- EA-133M-18-RQ-01428
About this file
10021 - Emergency Dry Docking Basic Spec
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_04.pdf | ||
| 10021_-_Dry_Docking_REV_1.doc | DOC document | |
| Amendment_03.pdf | ||
| Amendment_02.pdf | ||
| 12351_-_Z-drive_Flush,_Seal_replacement_REV1.doc | DOC document | |
| Amendment_01.pdf | ||
| AMC-997-1A.pdf | ||
| NF-241-05__Z_Drive_Tech_Man.pdf | ||
| NF-505-6501097_Standard_Piping_Details.pdf | ||
| MOC-300-3.pdf | ||
| 12351_-_Z-drive_Flush,_Seal_replacement.doc | DOC document | |
| RFQ_EA-133M-18-RQ-01428.pdf | ||
| 10011_-_General_Requirements.doc | DOC document | |
| NF085002_F,_Docking_Plan.pdf | ||
| NF085001.pdf | ||
| AMC-000-1F_.pdf | ||
| AMC-000-2C.doc | DOC document | |
| MOC-631-2D.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA SHIP NANCY FOSTER
(R-352)
30APR2018
ITEM NO. 10021
BASIC ITEM
MED/KRZ
Dry Docking l.0 ABSTRACT
1.1 This item describes the requirements for drydocking the ship.
2.0 REFERENCES:
2.1 Drawing NF-085-002, Docking Plan
2.2 NOAA Standard Specification AMC-997-1A, “Drydocking and Routine Drydock Work (As modified)”
2.3 NOAA Standard Specification AMC-000-2C, “Temporary Services at Contractor Facilities (As modified)”
3.0 ITEM LOCATION/DESCRIPTION:
3.1 Overall length
186'- 0"
Beam, Molded
40'- 0"
Draft, Design
11'- 0"
Draft, Navigational
12'- 0"
Displacement (FL)
1271 LT
Propulsion Z-Drives
Propulsion shafts -
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES
4.1 Government Furnished Eqipment: None.
4.2 Government Furnished Services:
4.2.1 The Government will provide the services of an ABS Surveyor.
5.0 NOTES
5.1 The contractor and all subcontractors regardless of tier are advised to review other work items under this contract, including but not limited to 10011 to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in references included in work item 10011.
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.
7.0 STATEMENT OF WORK REQUIRED
7.1 SEQ CHAPTER \h \r 1Accomplish the requirements of Reference 2.2 to drydock the ship in accordance with Reference 2.1.
7.2 The crew will be living aboard during the dry docking period. As a clarification to Ref. 2.3, services required while in drydock include:
7.2.1 Cooling water for the A/C plant.
7.2.2 1 and ½” NPT Water connection for hotel flushing, connection is in Auxiliary machinery space on port side.
7.2.3 3” Camlock connection for sewage connection to ship’s deck riser.
7.2.4 Three each phone lines to ship’s phone junction box on main weather deck.
7.2.5 1-1/2“ Potable water connection located on main deck port or stbd side.
7.2.6 High Speed Internet Service.
7.2.7 Trash bins.
7.2.8 Crane service as required to remove trash or load stores.
7.2.9 Electrical power, one each cable, 3 phase, 300 Amp service, 460V.
7.2.10 Fire Main connection.
7.2.10 Provide 10 each parking spaces.
7.3 SEQ CHAPTER \h \r 1Provide for removal of up to 500 gallons oily waste from ship & disposal of oily rags.
8.0 GENERAL REQUIREMENTS: None Additional.
002-2