Distance Measuring Equipment (DME), Very High Frequency Omnidirectional Range (VOR), Tactical Navigation System (TACAN)
(DVT)
DVT Sustainment Program
Status Update
July 2020
Federal Aviation Administration Federal Aviation Administration Federal Aviation Administration
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> Contents Program Description Systems and Users Quantities and Sites FY20 Program Accomplishments Program Phased Approach Challenges and Strategies TACAN Antenna Acquisition Next Steps
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> Program Description The DVT Sustainment Program will sustain DMEs, VORs, and TACANs in support of a resilient Ground-Based Navigation Infrastructure DVT systems represent a significant portion of this resilient infrastructure DMEs provide slant range (Distance) information to all aircraft and enables RNAV service for air carrier aircraft. Area navigation (RNAV) is a method of instrument flight rules (IFR) navigation that allows an aircraft to choose any course within a network of navigation beacons, rather than navigate point to point.
VORs provide azimuth (position) information for en-route navigation and approach services. VOR navigation allows an aircraft to fly point to point along established airways between VORs.
TACANs provide azimuth information to military aircraft and slant range information to military and civilian aircraft.
Most DVT systems are over 30 years old and must be sustained to provide resiliency during Global Positioning System (GPS) Service Interruptions.
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> Systems and Users
Azimuth
Slant Range
| Antenna | Function | User | Band |
| VOR | Azimuth | Civilian | VHF |
| DME | Slant Range | Civilian | UHF |
| TACAN | Azimuth | Military | UHF |
| Slant Range | Civilian and Military | UHF |
Conventional VOR/DME Conventional VOR/TACAN
Doppler VOR/TACAN
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> Quantities and Sites
Doppler VOR/TACAN
Conventional
VOR/TACAN
Conventional VOR/DME
Low Power DME Current Inventory End State Service Delivery Points
| Future Quantity of Sites | |||||
| VOR | VOR/DME | DME | VORTAC | TACAN | LPDME |
| 17 | 270 | 197 | 381 | 55 | 655 |
| Future Quantity of Systems | |||
| DME | VOR | TACAN | LPDME |
| 467 | 668 | 436 | 655 |
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> < =10 years VOR TACAN HP DME LP DME 61 118 10+ years VOR TACAN HP DME LP DME 8 182 15+ years VOR TACAN HP DME LP DME 21 20+ years VOR TACAN HP DME LP DME 134 40 25+ years VOR TACAN HP DME LP DME 46 87 30+ years VOR TACAN HP DME LP DME 865 296 295 355 Total VOR TACAN HP DME LP DME 911 430 512 655
FY20 Program Accomplishments Conducted follow-on Vendor discussions Completed the Program Requirements Document Produced the ROM Program Cost Estimate Conducted a second DVT National Planning meeting Continued progress towards FAA AMS Investment Analysis Readiness Decision requirements Initiated TACAN Antenna acquisition process Released a Market Survey Released a draft TACAN Antenna specification
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> Program Phased Approach
PHASE 1 ~ 2021- 2027
PHASES 2 – 4 ~ 2028- 2045
TACAN Antenna
Market Survey
Specification
SIR
Contract Award
Testing Qualification
IARD for the Program – 4QFY20 FID for Phase 1– 4QFY21
Strategic
NavAid Procurements New Technology Qualification Rapid Supply Chain Key Sites
Tactical
Equipment obsolescence Facility conditions Long lead time repair items Site Assessments
Testing and Qualification Pre-planned Product Improvement TACAN Antennas Continue Implementation
Tactical Additional identified needs based on Sustainment Analysis
Critical sites DVT Planning
Congressional Communications
Specifications
SIR
Contract Award
Vendor Engagement
Prioritization Implementation at Key Sites Implementation at n# SDPs based on priorities DVT Contract Award (multi-Phase) FID for Phase 2
FIDs for Phases 3-4
Tactical Additional identified needs based on Sustainment Analysis
TACAN Antennas Coupled with DVT Implementations
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> Engaging Vendors throughout the process per AMS guidelines Follow FAA AMS Process for acquisitions Develop Procurement packages and artifacts Award a competitive TACAN Antenna acquisition contract Award a competitive DVT Sustainment acquisition contract Program Strategy for Acquisition
Strategy Decision
FY20
FY21
RFI Released October 2018 RFI Responses Received December 2018
Industry Day November 2018
FID
DVT Contract Award
IARD
FY23
TACAN Antenna Contract Award DVT System Specifications Ready
FY22
June 2019
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> Challenges and Mitigation Strategies
| Challenges | Mitigation Strategies |
| Program Scope |
Large number of systems and locations Prioritization between tactical and strategic goals Agency priorities Phased Approach based on Prioritized Needs Engage the Vendors Flight Inspection Required for all installations DVT will increase expected workload Provide additional resources, e.g., aircraft and crews Reduce time required for inspections through increased efficiency Increase number of inspections that can be performed Implementation DVT will increase Engineering Services workload Possible COVID-19 impacts Agency priorities Inherent Agency responsibilities Access to Service Delivery Points Reduce implementation times and/or increase numbers of implementations that can be performed Vendor Installation Services FAA Tiger Teams Facilities/Infrastructure – Facilities that house equipment must be upgraded to support new installations Proactive Site Assessments Third party contractors to rapidly improve facilities New Equipment Readiness Qualification/Testing – required time to complete
| Certification – ensure Technicians have knowledge and tools to perform the function | Vendor support for training and depot support | |
| Operational Downtime – minimizing down time | Plan waterfall to address opportunities where access to facilities is less challenging |
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> TACAN Antenna Acquisition
FY20
FY21
FY22
FAA Stakeholder approval Market Survey Release Develop Draft Specification Develop SIR
JRC Approval Award TACAN Antenna Contract
Continue TACAN Antenna implementation activities Goals Reduce backlog at the FAA Logistics Center Reduce TACAN Antenna Operational Impacts Support NextGen DME and VOR MON programs Frequency Changes Provide improvements for safety and issues related to the Antennas Status Market Survey/Vendor engagement to inform scope Draft TACAN Antenna specification released for industry review Procurement Plan in development
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> Next Steps Award the TACAN Antenna contract Define Program and implement innovative approaches Complete the FAA AMS process for the DVT Sustainment Program Award the DVT Sustainment Contract
<Presentation Title – Change on Master Slide> <Date of Presentation – Change on Master Slide> image1.wmf image2.png image3.png image4.png image5.jpg image6.jpg image7.jpg
Microsoft_Excel_Worksheet.xlsx Graph
VOR TACAN HP DME LP DME
30+ years 865 296 295 355
25+ years 46 87
20+ years 134 40
15+ years 21
10+ years 8 182
<=10 years 61 118
Total 911 430 512 655
< =10 years VOR TACAN HP DME LP DME 61 118 10+ years VOR TACAN HP DME LP DME 8 182 15+ years VOR TACAN HP DME LP DME 21 20+ years VOR TACAN HP DME LP DME 134 40 25+ years VOR TACAN HP DME LP DME 46 87 30+ years VOR TACAN HP DME LP DME 865 296 295 355 Total VOR TACAN HP DME LP DME 911 430 512 655 image8.emf image9.jpeg image10.jpeg image11.png image12.jpeg image13.jpeg image14.png