This document is a Task Work Order for Professional Services issued by the State of Florida Department of Transportation (FDOT), specifically FDOT District 3, involving Gortemoller Engineering, Inc. as the consultant. The task work order is associated with Contract No. CAO55 and relates to a safety improvement project at the intersection of SR 291 and Langley Avenue in Escambia County, Florida.
The task work order authorizes post-design (construction support) services for a traffic signal replacement project, with a total compensation amount of $20,797.00. The services include construction assistance, such as answering design questions, providing clarifications, addressing changed field conditions, attending pre-construction and progress meetings, reviewing shop drawings, and potentially updating project plans. The work is to be completed by 5/29/2026, and the compensation is limited to the specified amount. The document indicates this is part of a larger set of authorizations, with total authorizations to date reaching $2,072,847.00.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CAM50-W0090000.pdf | ||
| CN-550000-CAO55-00020000.pdf | ||
| CN-550000-CAO55-00030000.pdf | ||
| CN-550000-CAO55-W0090000.pdf | ||
| CN-550000-CAO55-W0100000.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| CN-550000-CAO55-W0070100.pdf | ||
| CN-550000-CAO55-W0080000.pdf | ||
| CN-550000-CAO55-W0110000.pdf | ||
| CN-550000-CAO55.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR PROFESSIONAL SERVICES
375-030-25
PROCUREMENT
08/21
Consultant:
Address:
Date:
5/29/2026
*Limiting or Estimating/Budgeted Amount.
Distribution:
Task Work Order No.:
Contract No.: Payment FM No.:
CAO55 44566616202
$2,072,847.00
(name) (title) Signature
Jason Peters, P.E. Director of Transportation Operations
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
(LA4) Units worked at loaded billing rates in Table 6
Page 1 Total
Page 2 thru 6 Subtotal
Total
Post Design Services (LA 4)
Gortemoller Engineering, Inc.
708 Thomas Drive, Panama City Beach, FL 32408
(To be entered upon execution of T.W.O.)
Brief Task Description:
In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).
Compensation elements are as follows:
Element Description Amount Estimate/LimitMethod of Compensation
The total amount or the limiting amount of the compensation will be:
All services required under this Task Work Order will be completed on or before:
$20,797.00
$20,797.00 Limit
CS Traffic Operations Minor Design for develop roadway plans for providing safety improvements related to traffic signal replacement at the intersection of SR 291 at
Langley Avenue in Escambia County. Scope of Services, attached. (F.A.P. No. D324 090 B)
Signature
Michael Lewis, Jimmy Smith, Consultant, FS, PSU A. Goines
President
$20,797.00
$0.00
(name) (title)
Dexter M. Gortemoller, P.E.
$20,797.00
Encumber by Task
Total authorizations to date (including this one):
Departmental Approval:
Consultant Acceptance:
Docusign Envelope ID: 1FD0B65D-F9DC-49D0-8861-033E8E099542
4/11/2025
1/8/2025
SCOPE OF WORK
FDOT District 3
Continuing Services Traffic Operations Safety Consultant Services
Gortemoller Engineering, Inc.
(Contract No. CAO55, FPID 445666-1-32-01)
SR 291 at Langley Avenue Intersection Improvements
[Escambia County] Section #48070, MP 5.200 Safety Improvement Project
POST DESIGN SERVICES
FPID 445666-1-62-01
Background
The CONSULTANT was originally retained by the DEPARTMENT under Contract CAO55 to develop roadway plans for providing safety improvements related to traffic signal replacement at the intersection of SR 291 at Langley Avenue in Escambia County, Florida.
Purpose
The purpose of this task work order is to authorize the CONSULTANT to provide post-design (construction support) services for this project. All communications associated with these services will be coordinated with the DEPARTMENT and documented accordingly.
Services to be Performed
The intent of these services is to answer questions, provide design clarifications and address change conditions that may occur following acceptance of the plans. Typical examples of these services are:
Construction Assistance
The CONSULTANT shall provide the DEPARTMENT qualified representation during the construction phase to deal with construction questions concerning the intent and interpretation of the contract plans and documents prepared in the work. Should changed conditions be encountered in the field, and when requested by the DEPARTMENT, the CONSULTANT shall respond in a timely manner with suitable engineering solutions which take into account the changed conditions and meet the original intent of the work. From time to time during construction, the CONSULTANT may be requested by the DEPARTMENT or its designated representative to review contractor proposed field changes or to respond with a recommended solution to remedy particular field situations not covered by the plans and specifications.
1/8/2025
Meeting Attendance The CONSULTANT shall attend the Pre-Construction Meeting, at the request of the DEPARTMENT and/or LOCAL AGENCY.
GE has included up to five (5) one-hour monthly progress meetings and up to two (2) field meetings are included to facilitate communication between the contract and CONSULTANT during construction and each shall occur at the request of the DEPARTMENT and/or LOCAL AGENCY.
Anevay has included a single field meeting. Virtual meetings or teleconferences are assumed for the progress meetings.
Review of Shop Drawings The CONSULTANT may be required to provide construction shop drawing reviews.
The CONSULTANT shall review the shop drawings and erection plans for all components supplied by the contractor requiring review. This review shall verify the conformance of the shop drawings submitted with the final design drawings.
Project-specific elements anticipated for review on this include the roadway components, sign and lighting equipment, and signal submittal data by the associated Engineers of Record.
Shop drawings shall be reviewed in accordance with the Shop Drawings Review Procedure for compliance with the construction documents. The Consultant shall review and process shop drawing submittals within thirty calendar days of their receipt. Upon completion of the shop drawing review, the CONSULTANT shall forward the shop drawing package to the Department’s Review Office.
Plan Updates / Revisions The CONSULTANT may be requested by the DEPARTMENT to review proposed field changes or to respond with a recommended solution to remedy particular field situations not covered by the plans and specifications. Preparation of revised plan sheets by the CONSULTANT may also be necessary to address changes to the design.
Consultant Responsibilities All services and requirements as outlined in the Original Agreement shall remain in full force and effect.
Department Responsibilities The DEPARTMENT’s responsibilities shall remain the same as in the Original Agreement.
| Insert from: "445666-1SR291LangleyAveIntersection_PostDesign.pdf" |
| SR 291 at Langley Avenue |
| Intersection Improvements |
| [Escambia County] |
| POST DESIGN SERVICES |
| FPID 445666-1-62-01 |
| Background |
| Purpose |
| Services to be Performed |
| Plan Updates / Revisions |
| The CONSULTANT may be requested by the DEPARTMENT to review proposed field changes or to respond with a recommended solution to remedy particular field situations not covered by the plans and specifications. Preparation of revised plan sheets by the C... |
| Consultant Responsibilities |
| All services and requirements as outlined in the Original Agreement shall remain in full force and effect. |
| Department Responsibilities |
| The DEPARTMENT’s responsibilities shall remain the same as in the Original Agreement. |