CN-550000-CAM50-W0070000.pdf

PDF 1003 KB Posted

Attached to
Master Agreement FL|CAL76|be626232bd5ce2006152c2ac64b517ea
Contract number
CAL76
Issued by
Florida

About this file

This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT), specifically District 4, for a professional consulting contract with TRACE Consultants Inc., located in Miami, Florida. The contract is part of the CAM50 Districtwide Design Minor Projects indefinite delivery vehicle and involves a specific project for the State of Florida.

The task work order authorizes TRACE Consultants to install controlled midblock crossings at three locations on Broward Boulevard, with a total contract value of $187,318.53. The contract is broken down into two primary elements: Basic Services at $149,509.54 and SUE & Survey Services at $37,808.99, to be compensated through lump sum and loaded billing rates. The project scope includes providing two signalized midblock crossings between Berkeley Boulevard and Florida Avenue, and between SW 30th Avenue and NW 28th Way. The work will involve curb ramps, refuge islands, temporary traffic control plans, signalization, lighting, and landscaping improvements. The contract period runs from the execution date until February 6, 2028, with an independent assessment confirming the hours and quantities as fair, reasonable, and competitive.

View the file

Other files

File Type Posted
CN-550000-CAL76-00020000.pdf PDF
CN-550000-CAL76-W0040000.pdf PDF
CN-550000-CAL76-W0060000.pdf PDF
CN-550000-CAL76-W0070000.pdf PDF
CN-550000-CAM50-W0080000.pdf PDF
CN-550000-CAL76-W0020000.pdf PDF
CN-550000-CAL76-W0050000.pdf PDF
CN-550000-CAL76-W0010000.pdf PDF
CN-550000-CAL76-W0030000.pdf PDF
CN-550000-CAL76-W0030100.pdf PDF
CN-550000-CAL76.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

2/6/2028

*Limiting or Estimating/Budgeted Amount.

Distribution:

Consultant Acceptance:

Signature

Consultant, Procurement, Financial Services, FDOT Project Manager, File

President

$187,318.53

$0.00

(name) (title)

Frank Panellas, P.E.

$187,318.53

Total authorizations to date (including this one):

Departmental Approval:

$149,509.54 Limit

SUE & Survey Services $37,808.99 Limit

Install controlled midblock crossing, three locations on Broward Blvd

TRACE CONSULTANTS INC

8900 SW 117th Avenue, Suite 105B, Miami, FL 33186

(To be entered upon execution of T.W.O.)

Brief Task Description:

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$187,318.53

(LS2) Lump sum paid based on % of completion

(LA4) Units worked at loaded billing rates in Table 6

Page 1 Total

Page 2 thru 6 Subtotal

Total

Basic Services

$2,382,877.00

(name) (title) Signature

Luciana Amato Contracts Coordinator

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

Task Work Order No.:

Contract No.: Payment FM No.:

CAM50 451493-1-32-01

DocuSign Envelope ID: 163D0835-4FF9-4220-B9F1-27DAE5A8E73A

05/14/2024 | 1:34 PM EDT

EXHIBIT A

TASK WORK ORDER SCOPE OF SERVICES

DISTRICTWIDE DESIGN MINOR PROJECTS

CAM50

Signalized Midblock Crossings

Contract Number:

Task Work Order No.:

Project Description:

Construction Project FPID: 451493-1-32-01

Project Location: SR 842/Broward Blvd. from W of Berkeley Blvd. to SW 22nd Ave Roadway ID: 86006000 Project Limits: From W of Berkeley Blvd. to SW 22nd Ave County: Broward County Project Manager: Hong Benitez, P.E.

TRACE Project Manager: Favio Laverde, P.E.

Background:

This Traffic Operations improvement project is in Broward County along SR 842 (Broward Blvd.) from W of Berkeley Blvd. to SW 22nd Avenue. The scope includes providing two signalized midblock crossings at the following locations:

- Between Berkeley Blvd. and Florida Avenue

- Between SW 30th Avenue and NW 28th Way

The project will address the required improvements to signing and pavement markings, signalization and lighting as needed.

Scope:

The scope for the project includes the following:

Project General Tasks

- Contract Maintenance and Attendance of Meetings

- Digital Delivery

- Specifications Package

- PIO Efforts under separate TWO

Roadway

- Provide new curb ramps and midblock refuge islands to serve the proposed signalized midblock crossings

- Development of temporary traffic control plans including TTCP General Notes, phasing notes, typical sections, and pedestrian detours, as required

Miscellaneous Structures (Under separate TWO)

Signing & Pavement Markings

- Provide new high emphasis crosswalks at the signalized midblock crossings and associated signing improvements

Signalization

- Provide new signalized midblock crossings at the two locations denoted above.

- Coordinate signalization improvements with Broward County Traffic Engineering Division.

Lighting

- Evaluate and provide the necessary lighting for the proposed midblock crosswalks as required per FDM 222.

Landscaping/Irrigation

- Selective Clearing 7 Grubbing analysis of existing vegetation within impacted median areas o Includes all pruning and selective removals for clear sight o No Tree Disposition anticipated

- Existing Irrigation inventory and analysis of impacts

- Final irrigation design for two median locations

- Technical Special Provision for Irrigation components

SUE

- Provide Quality Level A Locates (Test Holes) for 4 mast arm locations and at 2 pedestal locations

Provide Utility Coordination and Prepare Estimated Quantities Report associated with the proposed improvements

Deliverables:

Include the following Deliverables:

Constructability, Biddability, and Production (Signed and Sealed Plans, Estimated Quantities Report, and Specifications), and Lighting Design Analysis Report

Schedule:

Design and Plans preparation will follow the current project schedule (subject to change) for FM #451493-1-32-01

Services may begin immediately after this task work order is executed.

Name of Consultant Project Information Sheet

Financial Project Identification Number: 451493-1-32-01

Name of Prime / Subconsultant: TRACE Consultants, Inc. County: Broward

Project Description: SR 842 / Broward Blvd. from W of Berkley Blvd. to SW 22 Avenue - CAM50

Begin Milepost: Miles

Number of Lanes: (Urban / Rural / Int.) Lane Configuration: (Divided / Undivided)

Project Type: Roadway Classification: (NHS/FIHS/Off Sys.)

CAP Level:

Design Variations:

Proposed Design Contract Time: months/days Date of Negotiation: Context Classification:

3. Project Common & Project General Tasks

4. Roadway Analysis

5. Roadway Plans 6a. Drainage Analysis 6b. Drainage Plans 6c. Selective C&G

7. Utilities

8. Environmental Permits and Env. Clearances

9. Structures Summary

10. Structures - Bridge Development Report

11. Structures - Temporary Bridge

12. Structures - Short Span Concrete

13. Structures - Medium Span Concrete

14. Structures - Structural Steel

15. Structures - Segmental Concrete

16. Structures - Movable Span

17. Structures - Retaining Walls

18. Structures - Miscellaneous

19. Signing and Pavement Marking Analysis

20. Signing and Pavement Marking Plans

21. Signalization Analysis

22. Signalization Plans

23. Lighting Analysis

24. Lighting Plans

25. Landscape Analysis

26. Landscape Plans

27. Survey

28. Photogrammetry

29. Mapping

30. Terrestrial Mobile LiDAR

31. Architecture Development

32. Noise Barriers Impact Design Assessment

33. Intelligent Transportation Systems Analysis

34. Intelligent Transportation Systems Plans

35. Geotechnical

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Access Management Classification:

TTCP Level: Survey Level:

1. Design Exceptions: 1.

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Federal Aid Project Identification Number:

End Milepost: Project Length:

Typical Section:

Project Activity:

Estimated By: Negotiated By: (name - firm)

Consultant FDOT Consultant FDOT

2. 2.

3. 3.

4. 4.

5. 5.

(Minor / Major)

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office Enter name & firm Enter name & office

FPID 451493-1_SHE_TRACE.xlsx Project Information Page 1 of 32 4/15/2024

Project Staff Hour Summary

Name of Consultant: TRACE Consultants, Inc.

Activity No. Activity TRACE C&H MGV Sub 3 Sub 4 Sub 5 Sub 6 Sub 7 Sub 8 Sub 9 Sub 10 Sub 11 Sub 12 Total Hours

3 Project Common and General Tasks 209 209

4 Roadway Analysis 211 211

5 Roadway Plans 54 54

6a Drainage Analysis 0

6b Drainage Plans 0

6c Selective C&G 49 49

7 Utilities 111 111

8 Env. Permits and Env. Clearances 4 4

9 Structures - Summary, Misc. Tasks, Dwgs. 0

10 BDR 0

11 Temporary Bridge 0

12 Short Span Concrete Bridge 0

13 Medium Span Concrete Bridge 0

14 Structural Steel Bridge 0

15 Segmental Concrete Bridge 0

16 Movable Span 0

17 Retaining Walls 0

18 Miscellaneous Structures 0

19 Signing & Pavement Marking Analysis 52 52

20 Signing & Pavement Marking Plans 12 12

21 Signalization Analysis 88 88

22 Signalization Plans 32 32

23 Lighting Analysis 78 78

24 Lighting Plans 28 28

25 Landscape Analysis 56 56

26 Landscape Plans 30 30

27 Survey - Field and Office Support 55 55

28 Photogrammetry 0

29 Mapping 0

30 Terrestrial Mobile LiDAR 0

31 Architecture Development 0

32 Noise Barriers Impact Design Assessment 0

33 ITS Analysis 0

34 ITS Plans 0

35 Geotechnical 0

879 135 55 0 0 0 0 0 0 0 0 0 0 1,069

27 Survey Field Crew Days 14 14

Notes: 1. Staff hours for prime consultant come directly from each discipline's worksheet.

2. Staff hours for subconsultants are to be entered manually into columns D through O.

3. For workbooks prepared by subconsultants, their project hours will be totaled in column C.

2 / Broward Blvd. from W of Berkley Blvd. to SW 22 Avenue - CAM50

Project Total

451493-1-32-01 Project Staff Hours

FPID 451493-1_SHE_TRACE.xlsx Summary Page 2 of 32 4/15/2024

Financial Project Number: 451493-1-32-01 Project Name: SR 842 / Broward Blvd. from W of Berkley

FAP Number: 0 Date: 4/15/2024 Name of Consultant: TRACE Consultants, Inc.

WORK EMPLOYEE CLASSIFICATION

ACTIVITY ON CADD

Firm Total

Project Manager 3

Home

Senior Engineer 1

Home

Engineer 2 Home

Engineering Intern Home

Chief Designer

Home

Staff Classi-fication 6

Staff Classi-fication 7

Staff Classi-fication 8

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12

Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours PERCENT

3. Project Common and Project General Tasks 209 21 31 52 52 52 0 0 0 0 0 0 0 208 229

4. Roadway Analysis 211 21 32 53 53 53 0 0 0 0 0 0 0 212 233

5. Roadway Plans 54 5 8 14 14 14 0 0 0 0 0 0 0 55 61

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

7. Utilities 111 11 17 28 28 28 0 0 0 0 0 0 0 112 123

8. Environmental Permits,and Env. Clearances 4 0 1 1 1 1 0 0 0 0 0 0 0 4 4

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

19. Signing & Pavement Marking Analysis 52 5 8 13 13 13 0 0 0 0 0 0 0 52 57

20. Signing & Pavement Marking Plans 12 1 2 3 3 3 0 0 0 0 0 0 0 12 13

21. Signalization Analysis 88 9 13 22 22 22 0 0 0 0 0 0 0 88 97

22. Signalization Plans 32 3 5 8 8 8 0 0 0 0 0 0 0 32 35

23. Lighting Analysis 78 8 12 20 20 20 0 0 0 0 0 0 0 80 88

24. Lighting Plans 28 3 4 7 7 7 0 0 0 0 0 0 0 28 31

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

TOTALS 879 87 133 221 221 221 0 0 0 0 0 0 0 883 971

Field Survey Estimate:

Notes: 0 4-person crew days 883 971

1. This worksheet provides the distribution of a firm's total staff hours for a project.

2. Percentages for staff hour distribution by classification are entered below in rows 64 to 98 of this sheet.

3. Total Staff Hours (column O) may not match staff hours from Summary worksheet (column B) due to rounding. Staff hours calculated for employee classifications are to be adjusted so totals in columns B and O match.

4. Formulas under "Total Staff Hours Range" (columns O & P) may be adjusted to provide desired range.

Hours from "Summary" sheet

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

STAFF HOURS

TOTAL

FIRM TOTAL

RANGE

FPID 451493-1_SHE_TRACE.xlsx Staff Hour Summary - Firm Page 3 of 32 4/15/2024 8:48 AM

Financial Project Number: 451493-1-32-01 Project NameSR 842 / Broward Blvd. from W of Berkley

FAP Number: Date: 4/15/2024 Name of Consultant: TRACE Consultants, Inc.

Hours from "Summary" sheet

Firm Total

Project Manager 3

Home

Senior Engineer 1

Home Engineer 2

Home Engineering Intern Home

Chief Designer

Home Staff Classi-fication 6 Staff Classi-fication 7 Staff Classi-fication 8 Staff Classi-fication 9 Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12 Total

3. Project Common and Project General Tasks 209 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

4. Roadway Analysis 211 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

5. Roadway Plans 54 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00% 6a. Drainage Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00% 6b. Drainage Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00% 6c. Selective C&G 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

7. Utilities 111 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

8. Environmental Permits,and Env. Clearances 4 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

10. Structures - Bridge Development Report 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

11. Structures - Temporary Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

12. Structures - Short Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

13. Structures - Medium Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

14. Structures - Structural Steel Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

15. Structures - Segmental Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

16. Structures - Movable Span 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

17. Structures - Retaining Walls 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

18. Structures - Miscellaneous 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

19. Signing & Pavement Marking Analysis 52 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

20. Signing & Pavement Marking Plans 12 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

21. Signalization Analysis 88 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

22. Signalization Plans 32 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

23. Lighting Analysis 78 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

24. Lighting Plans 28 10.0% 15.0% 25.0% 25.0% 25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

25. Landscape Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

26. Landscape Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

27. Survey (Field & Office Support) 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

28. Photogrammetry 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

29. Mapping 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

30. Terrestrial Mobile LiDAR 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

31. Architecture Development 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

32. Noise Barriers Impact Design Assessment 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

33. Intelligent Transportation Systems Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

34. Intelligent Transportation Systems Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

35. Geotechnical 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Staff Hour Distribution Percentages - Firm Total

FPID 451493-1_SHE_TRACE.xlsx Staff Hour Summary - Firm Page 4 of 32 4/15/2024 8:48 AM

Financial Project Number: 451493-1-32-01 Project Name: SR 842 / Broward Blvd. from W of Berkley

FAP Number: Date: 4/15/2024 Name of Consultant: Cotleur & Hearing

ACTIVITY ON CADD

Firm Total

Senior Landscape Architect

Home

Project Landscape Architect

Home

Landscape Designer/

Landscape Planner Home

Chief Designer

Home

Staff Classi-fication 5

Staff Classi-fication 6

Staff Classi-fication 7

Staff Classi-fication 8

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12

Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours PERCENT

3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6c. Selective C&G 49 10 15 24 0 0 0 0 0 0 0 0 0 49 54

7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

23. Lighting Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

25. Landscape Analysis 56 11 17 20 8 0 0 0 0 0 0 0 0 56 62

26. Landscape Plans 30 6 9 11 4 0 0 0 0 0 0 0 0 30 33

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

TOTALS 135 27 41 55 12 0 0 0 0 0 0 0 0 135 149

Field Survey Estimate:

Notes: 0 4-person crew days 135 149

1. This worksheet provides the distribution of a firm's total staff hours for a project.

2. Percentages for staff hour distribution by classification are entered below in rows 64 to 98 of this sheet.

3. Total Staff Hours (column O) may not match staff hours from Summary worksheet (column B) due to rounding. Staff hours calculated for employee classifications are to be adjusted so totals in columns B and O match.

4. Formulas under "Total Staff Hours Range" (columns O & P) may be adjusted to provide desired range.

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Hours from "Summary" sheet

TOTAL

STAFF HOURS

RANGE

FIRM TOTAL

FPID 451493-1_SHE_TRACE.xlsx Staff Hour Summary - Firm (C&H) Page 5 of 32 4/15/2024 8:48 AM

Financial Project Number: 451493-1-32-01 Project NameSR 842 / Broward Blvd. from W of Berkley

FAP Number: Date: 4/15/2024 Name of Consultant: Cotleur & Hearing

Hours from "Summary" sheet

Firm Total

Senior Landscape Architect

Home

Project Landscape Architect

Home

Landscape Designer/

Landscape Planner

Chief Designer

Home Staff Classi-fication 5 Staff Classi-fication 6 Staff Classi-fication 7 Staff Classi-fication 8 Staff Classi-fication 9 Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12 Total

3. Project Common and Project General Tasks 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

4. Roadway Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

5. Roadway Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00% 6a. Drainage Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00% 6b. Drainage Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00% 6c. Selective C&G 49 20.0% 30.0% 50.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

7. Utilities 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

8. Environmental Permits,and Env. Clearances 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

10. Structures - Bridge Development Report 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

11. Structures - Temporary Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

12. Structures - Short Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

13. Structures - Medium Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

14. Structures - Structural Steel Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

15. Structures - Segmental Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

16. Structures - Movable Span 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

17. Structures - Retaining Walls 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

18. Structures - Miscellaneous 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

19. Signing & Pavement Marking Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

20. Signing & Pavement Marking Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

21. Signalization Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

22. Signalization Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

23. Lighting Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

24. Lighting Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

25. Landscape Analysis 56 20.0% 30.0% 35.0% 15.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

26. Landscape Plans 30 20.0% 30.0% 35.0% 15.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

27. Survey (Field & Office Support) 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

28. Photogrammetry 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

29. Mapping 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

30. Terrestrial Mobile LiDAR 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

31. Architecture Development 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

32. Noise Barriers Impact Design Assessment 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

33. Intelligent Transportation Systems Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

34. Intelligent Transportation Systems Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

35. Geotechnical 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Staff Hour Distribution Percentages - Firm Total

FPID 451493-1_SHE_TRACE.xlsx Staff Hour Summary - Firm (C&H) Page 6 of 32 4/15/2024 8:48 AM

ESTIMATE OF WORK EFFORT AND COST - PRIME CONSULTANT

Name of Project: SR 842 / Broward Blvd. from W of Berkley Blvd. to SW 22 Avenue - CAM50 Consultant Name: TRACE Consultants, Inc.

County: Broward Consultant No.:

FPN: 451493-1-32-01 Date: 4/15/2024 FAP No.: Estimator: Favio Laverde

SH Salary Average

By Cost By Rate Per $233.72 $213.94 $188.44 $109.56 $101.29 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Activity Activity Task

3. Project Common and Project General Tasks 209 21 31 52 52 53 0 0 0 0 0 0 0 209 $32,405 $155.05

4. Roadway Analysis 211 21 32 53 53 52 0 0 0 0 0 0 0 211 $32,815 $155.52

5. Roadway Plans 54 5 8 14 14 13 0 0 0 0 0 0 0 54 $8,369 $154.98 6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

7. Utilities 111 11 17 28 28 27 0 0 0 0 0 0 0 111 $17,287 $155.74

8. Environmental Permits,and Env. Clearances 4 0 1 1 1 1 0 0 0 0 0 0 0 4 $613 $153.31

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

19. Signing & Pavement Marking Analysis 52 5 8 13 13 13 0 0 0 0 0 0 0 52 $8,071 $155.21

20. Signing & Pavement Marking Plans 12 1 2 3 3 3 0 0 0 0 0 0 0 12 $1,859 $154.96

21. Signalization Analysis 88 9 13 22 22 22 0 0 0 0 0 0 0 88 $13,669 $155.33

22. Signalization Plans 32 3 5 8 8 8 0 0 0 0 0 0 0 32 $4,965 $155.16

23. Lighting Analysis 78 8 12 20 20 18 0 0 0 0 0 0 0 78 $12,220 $156.67

24. Lighting Plans 28 3 4 7 7 7 0 0 0 0 0 0 0 28 $4,352 $155.43

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

Total Staff Hours 879 87 133 221 221 217 0 0 0 0 0 0 0 879 Total Staff Cost $20,333.64 $28,454.02 $41,645.24 $24,212.76 $21,979.93 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $136,625.59 $155.43

Check = $136,625.59 Survey Field Days by Subconsultant SALARY RELATED COSTS: $136,625.59 4 - Person Crew: OVERHEAD: 0% $0.00

OPERATING MARGIN: 0% $0.00

Notes: FCCM (Facilities Capital Cost Money): 0.00% $0.00

1. This sheet to be used by Prime Consultant to calculate the Grand Total fee. EXPENSES: 0.00% $0.00

2. Manually enter fee from each subconsultant. Unused subconsultant rows may be hidden. Survey (Field - if by Prime) 0 4-person crew days @ -$ / day $0.00

SUBTOTAL ESTIMATED FEE: $136,625.59

Subconsultant: C&H $12,883.95 Subconsultant: MGV $37,808.99 Subconsultant: Sub 3 $0.00 Subconsultant: Sub 4 $0.00 Subconsultant: Sub 5 $0.00 Subconsultant: Sub 6 $0.00 Subconsultant: Sub 7 $0.00 Subconsultant: Sub 8 $0.00 Subconsultant: Sub 9 $0.00 Subconsultant: Sub 10 $0.00 Subconsultant: Sub 11 $0.00 Subconsultant: Sub 12 $0.00

SUBTOTAL ESTIMATED FEE: $187,318.53

Geotechnical Field and Lab Testing $0.00

SUBTOTAL ESTIMATED FEE: $187,318.53

Optional Services $0.00

GRAND TOTAL ESTIMATED FEE: $187,318.53

Senior Engineer 1

Home

Engineer 2 Home

Engineering Intern Home

Chief Designer

Home Staff Classification

Total Staff Hours From

"SH

Summary -

Firm"

Project Manager 3

Home

Staff Classi-fication 12

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 6

Staff Classi-fication 7

Staff Classi-fication 8

FPID 451493-1_SHE_TRACE.xlsx Fee Sheet - Prime Page 32 of 7 4/15/2024 8:48 AM

ESTIMATE OF WORK EFFORT AND COST - SUBCONSULTANT

Name of Project: SR 842 / Broward Blvd. from W of Berkley Blvd. to SW 22 Avenue - CAM50 Consultant Name: Cotleur & Hearing County: Broward Consultant No.:

FPN: 451493-1-32-01 Date: 4/15/2024 FAP No.: Estimator: Aaron Wilbur

SH Salary Average

By Cost By Rate Per $122.58 $102.29 $81.32 $75.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Activity Activity Task

3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6c. Selective C&G 49 10 15 24 0 0 0 0 0 0 0 0 0 49 $4,712 $96.16

7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

23. Lighting Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

25. Landscape Analysis 56 11 17 20 8 0 0 0 0 0 0 0 0 56 $5,319 $94.98

26. Landscape Plans 30 6 9 11 4 0 0 0 0 0 0 0 0 30 $2,853 $95.11

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

Total Staff Hours 135 27 41 55 12 0 0 0 0 0 0 0 0 135 Total Staff Cost $3,309.66 $4,193.89 $4,472.60 $907.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $12,883.95 $95.44

Check = $12,883.95

SALARY RELATED COSTS: $12,883.95

OVERHEAD: 0.00% $0.00

OPERATING MARGIN: 0% $0.00

Notes: FCCM (Facilities Capital Cost Money): 0.000% $0.00

1. This sheet to be used by Subconsultant to calculate its fee. EXPENSES: 0.00% $0.00

SUBTOTAL ESTIMATED FEE: $12,883.95

Survey (Field) 0 4-person crew -$ / day $0.00 Geotechnical Field and Lab Testing $0.00

SUBTOTAL ESTIMATED FEE: $12,883.95

Optional Services $0.00

GRAND TOTAL ESTIMATED FEE: $12,883.95

Staff Classi-fication 12

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11Staff Classification Staff Classi-fication 6 Staff Classi-fication 7 Staff Classi-fication 8

Senior Landscape Architect

Home

Project Landscape Architect

Home

Landscape Designer/

Landscape Planner

Chief Designer

Home

Staff Classi-fication 5Total Staff

Hours From "SH Summary -

Firm"

FPID 451493-1_SHE_TRACE.xlsx Fee Sheet - C&H Page 32 of 8 4/15/2024 8:48 AM

Project Activity 3: General Tasks

SR 842 / Broward Blvd. from W of Berkley Blvd. to SW 22 Avenue - CAM50

451493-1-32-01

Signature / Date

NOTE: Signature Block is optional, per District preference

Task No. Task Units No of Units Hours/ Unit Total

Hours Comments

3.1

3.1.1 Community Awareness Plan LS 1 0 0 By ISCG

3.1.2 Notifications LS 1 0 0 By ISCG

3.1.3 Preparing Mailing Lists LS 1 0 0 By ISCG

3.1.4 Median Modification Letters LS 1 0 0 N/A

3.1.5 Driveway Modification Letters LS 1 0 0 N/A

3.1.6 Newsletters LS 1 0 0 N/A

3.1.7 Renderings and Fly Throughs LS 1 0 0 N/A

3.1.8 PowerPoint Presentation LS 1 0 0 N/A - No Public Meeting is anticipated (Mailing of Flyers only)

3.1.9 Public Meeting Preparations LS 1 0 0 N/A - No Public Meeting is anticipated (Mailing of Flyers only)

3.1.10 Public Meeting Attendance/Followup LS 1 0 0 N/A

3.1.11 Other Agency Meetings LS 1 12 12 Meetings with the City of Ft. Lauderdale (2 Meetings), and Broward County (2 Meetings): 4 meetings x 3 hours per meeting (includes prep time, meeting, and minutes) = 12 hours

3.1.12 Web Site LS 1 0 0 By ISCG

3.2 Joint Project Agreements EA 0 0 0 N/A

3.3

3.3.1 Specifications Package Preparation LS 1 16 16

Report 1 Calculated Hours

Components 6 28

3.4 Contract Maintenance and Project Documentation LS 1 78 78 16 hours for setup and 3 hours per month x 18 months + 8 hours for Project Documentation = 78 hours

3.5 Value Engineering (Multi-Discipline Team) Review LS 1 0 0 N/A

3.6 Prime Consultant Project Manager Meetings LS 1 56 56 See listing below

Based on 16 hours, plus 2 hours for each component. (Roadway, SPM, Signalization, Landscape, Lighting, and Misc. Structures)

Estimator: FAL

3.1 Public Involvement Subtotal

TRACE Consultants, Inc.

Representing Print Name

FDOT District 4

Public Involvement

Specifications & Estimates

3.3.2 Estimated Quantities Report Preparation 28

FPID 451493-1_SHE_TRACE.xlsx

3. Project General Tasks Page 9 of 32 4/15/2024

Project Activity 3: General Tasks

Task No. Task Units No of Units Hours/ Unit Total

Hours Comments

3.7 Plans Update LS 1 0 0 N/A

3.8 Post Design Services LS 1 0 0 N/A

3.9 Digital Delivery LS 1 15 15 4 Signatures (Roadway EOR, Lighting EOR, Structures EOR, Landscape Architect): 6 hours for 1st EOR + 3 hours for each additional EOR = 15 hours

3.10 Risk Assessment Workshop LS 1 0 0 N/A

3.11 Railroad, Transit, and/or Airport Coordination LS 1 4 4 To coordinate with Broward County Transit

3.11.1 Aeronautical Evaluation LS 1 0 0 N/A

3.12 Landscape and Existing Vegetation Coordination LS 1 0 0 N/A

3.13 Other Project General Tasks LS 1 0 0 N/A

Units No of Units Hours/ Unit Total Hours Comments

EA 0 0 0

EA 0 0 0

EA 0 0 0

EA 3 2 6

EA 1 2 2

EA 2 2 4

EA 0 0 0

EA 1 2 2

EA 1 2 2

EA 2 2 4

EA 0 0 0

EA 0 0 0

EA 2 2 4

EA 0 0 0

EA 0 0 0

EA 0 0 0

EA 0 0 0

EA 0 0 0

EA 12 1 12

EA 2 4 8

EA 2 6 12

28 56 Total PM Meeting Hours carries to Task 3.6 above

Notes:

1. If the hours per meeting vary in length (hours) enter the average in the hour/unit column.

2. Do not double count agency meetings between permitting agencies.

3. Project manager meetings are calculated in each discipline sheet and brought forward to Column D.

Roadway Analysis

3.6 - List of Project Manager Meetings

3. Project Common and Project General Tasks Total

Total Project Manager Meetings

Field Reviews

Phase Reviews

Progress Meetings

Geotechnical

ITS Analysis

Structures

Environmental

Utilities

Drainage

Noise Barriers

Signalization

Architecture

Terrestrial Mobile LiDAR

ROW & Mapping

Selective C&G

Photogrammetry

Survey

Landscape Architecture

Lighting

Signing & Pavement Marking

FPID 451493-1_SHE_TRACE.xlsx

3. Project General Tasks Page 10 of 32 4/15/2024

451493-1-32-01

Signature / Date

NOTE: Signature Block is optional, per District preference

Documentation

Description Units Complexity

Low

Cover 0 0 0 0 0 N/A

Typical 0 2-Lane FS & Ramps 0 0 0 0

Typical 0 2-Lane C & Muti-Lane FS 0 0 0 0

Typical 0 LA w/ Barrier & Multi-Lane C 0 0 0 0

4.2 Pavement Type Selection Report Report 0 0 0 0 0

Report & Assembly 0 Low 0 0 0 0 N/A - Use pavement design from FPID 446094-1

Pavt Designs 0 Travel/Aux.

Lanes 0 0 0 0

Pavt Designs 0 Other Roads & Shoulders 0 0 0 0

X-Slope Assessment 0.00 Undivided

Roadway 0 0 0 0

X-Slope Assessment 0.00 Divided

Roadway 0 0 0 0 N/A

Concepts for Corrections 0 0 0 0 0

HSM

Assessment 0 0 0 0 0

Crash Analysis 1 Simple 8 0 8 8 To support TEM Variation for not meeting crosswalk distance to side-streets/driveways

Monitor Exist.

Structures 1 Low 4 0 4 4

Access Management 0.00 Low 0 0 0 0 N/A

Roundabout 0 1x1 Roundabout 0 0 0 0

Roundabout 0 1x2 Roundabout 0 0 0 0

Roundabout 0 2x2 Roundabout 0 0 0 0

RRR 0 0 0 0 0

Other Reports 0 0 0 0

Variation Memo 0 0 0 0 0

Formal Variation 1 24 0 24 24 TEM Variation for not meeting crosswalk distance to side-streets/driveways

Design Exception 0 0 0 0 0

4.10 Master Design File Setup & Maintenance, Model

Management Plan LS 1 Low 30 0 15 15 Utilize previous preliminary design from feasibility and update and maintain throughout design phase

Mainline 0.08 Low 14 0 14 14 To update preliminary design of midblock crossings at the two proposed locations, including but not limited to curb ramps, median midblock refuge islands, and milling limits (7 hours per location x 2 = 14 hours)

Side Road & Ramps 0.00 Low 0 0 0 0

Frontage Road 0.00 Low 0 0 0 0

Mainline 0.00 Low 0 0 0 0 N/A

Side Road & Ramps 0.00 Low 0 0 0 0

Frontage Road 0.00 Low 0 0 0 0

AMG Files 0 Low 0 0 0 0

TTCP Analysis LS 1 Low 20 0 20 20 Level 1 TTCP; Includes development of vehicular and pedestrian TTCP concept and lane closure analysis

Length (Phase-Miles) 0.00 Low 0 0 0 0 N/A (TTCP Typical Sections and phasing notes only)

Pedestrian 0 0 0 0 0 Utilize Standard Plans Index 102-660

Design Reports

TTCP Master Design Files

4.6 Design Analysis

Safety Analysis

Staff Hours

Provide documentation when negotiated hours differ from the calculated hours.

What is the overall project complexity? (See Roadway Guidelines)

Calculated Department Consultant Negotiated

4.9 Design Variations and Exceptions

4.12

4.7 Operational Analysis

4.8

4.11

Horizontal /Vertical Master Design Files

4.1 Typical Section Package

4.3 Pavement Design Package

4.4

Task No. Task

Project Parameter

Cross Slope Analysis (lanes and shoulders)

4.5

Representing Print Name

FDOT District 4

4. Roadway Analysis Staff HoursEstimator: FAL

3D Modeling Development

TRACE Consultants, Inc.

TTCP 3D Modeling (Isolated Locations) Locations 0 0 0 0 0 N/A

4.13 Utility Data Collection & Analysis LS 1 Low 6 0 6 6

Length (Miles) 0.08 Low 1 0 1 1

Interchanges Rest Areas 0 0 0 0 0

Validation 1 Low 36 0 36 36

TTCP Quantities for EQ Report Major Phases 1 Simple 6 0 6 6

Engineer Estimate 2 Low 20 0 20 20

LRE Updates 2 Low 10 0 10 10

4.16 Technical or Modified Special Provisions TSPs & MSPs 0 0 0 0 0 Check with ASA

4.17 Other Roadway Tasks Other Analysis 0 0 0 0

179 0 164 164

4.18 Quality Assurance/Quality Control LS 1 5% 9 0 9 9

4.19 Supervision LS 1 5% 9 0 9 9

Meetings 6 12 0 10 10

Travel Time 0 0 0 0

4.21 Field Reviews (listed below) LS 12 0 12 12

42 0 40 40

4.22 Coordination LS 1 3% 7 0 7 7

228 0 211 211

Carries to Summary Tab

Technical Meetings # Meetings Designer

Travel Time (Hours)

# Meetings

PM

Typical Section 0 0 0

Pavement Design 1 0 0

Access Management / Driveways 0 0 0

15% Line and Grade 0 0 0

RRR / ECAR Resolution 0 0 0

Local Governments (cities, counties, MPO) 1 0 0

Work Zone Traffic Control 0 0 0

30/60/90/100% Comment Review Meetings 2 0 0

Utility Coordination 2 0 0

Other Meetings 0 0 0

Subtotal Technical Meetings 6 0 0 Progress Meetings (if required by FDOT) 0 0

Phase Review Meetings 0 0

Total Roadway Meetings 6 0

Field Reviews # of Staff Site Time (per staff)

Travel Time (per staff) Total Hours

Field Review #1 1 4 2 6

Field Review #2 1 4 2 6

Field Review #3 0 0 0 0

Field Review #4 0 0 0 0

Plans-in-hand Field Review 0 0 0 0

4.15 Cost Estimate

Roadway Analysis Technical Subtotal

4.20 Roadway Meetings (listed below)

Roadway Analysis Non-Technical Subtotal

4. Roadway Analysis Total

Documentation

Total Field Review Hours

Roadway Quantities for EQ Report 4.14

Signature / Date

NOTE: Signature Block is optional, per District preference

Documentation

Description Units Complexity

Low

Key Sheet 1 4 0 4 4

Signature Sheet 1 2 0 2 2 Typical

Sections w/

CADD

0 0 0 0 0 N/A

Typical Sections w/o

CADD

0 0 0 0 0 N/A

Partial Sections 0 0 0 0 0 N/A

5.3 Cross Slope Correction Details Pavement

Segments 0 0 0 0 0 N/A

5.4 General Notes/Pay Item Notes 1 Simple 6 0 6 6

5.5 Project Layout/Model Management 0 0 0 0 0 N/A

Length (Miles) 0.08 Low 2 0 2 2

Interchange 0 0 0 0 0

Roundabout 0 0 0 0 0

Length (Miles) 0.00 Flush Shoulder 0 0 0 0

Length (Miles) 0.00 Curbed 0 0 0 0 N/A

Driveway Curb Return 0 0 0 0 0 N/A

Intersection RR Xing 0 0 0 0 0 N/A

5.9 Sidewalk Profiles Length (Miles) 0.00 0 0 0 0 N/A

0 Standard 2 Levels 0 0 0 0 N/A

0 Complex 3+ Levels 0 0 0 0 N/A

Ramp Terminal 0 0 0 0 0

Intersection Layout 0 0 0 0 0

Special 1 10 0 10 10 For median refuge detail

5.12 Soil Survey Sheets 0 0 0 0 0 N/A

5.13 Cross Sections Alignments 0 0 0 0 0 N/A

TTC Notes 1 4 0 4 4

Length (Miles) 0.00 Low 0 0 0 0

Critical Cross Sections 0 0 0 0 0

TTC Details 2 16 0 16 16 TTCP Typical Sections

5.15 Utility Adjustment Sheets Length (Miles) 0.00 0 0 0 0 N/A

5.16 Project Control Sheets 1 4 0 4 4

5.11 Details

5.14 Temporary Traffic Control Plan

5.8 Special Profiles

5.10 Interchange Layout Sheet Interchange

5.6 Plan View (Plan Sheets)

5.7 Profile View (Plan/Profile Sheets)

5.1

5.2 Typical Section Sheets

Task No. Task

Project Parameter Staff Hours

Estimator: FAL 5. Roadway Plans Staff Hours

Representing Print Name

FDOT District 4

TRACE Consultants, Inc.

Provide documentation when negotiated hours differ from the calculated hours.

What is the overall project complexity? (See Roadway Guidelines)

Calculated Department Consultant Negotiated

5.17 Utility Verification Data (SUE) 0 0 0 0 0 Provided by Surveyor

48 0 48 48

5.18 Quality Assurance/Quality Control % 1 5% 3 0 3 3

5.19 Supervision % 1 5% 3 0 3 3

54 0 54 54 Carries to Summary Tab

Roadway Plans Technical Hours Subtotal

Roadway Plans Total

Signature / Date

NOTE: Signature Block is optional, per District preference

Documentation

Description Units Complexity

Simple

Roadway Length (Miles) 0.15 Simple 2 0 2 2 Data collection for reduced project limits. Only address reduced (limited landscape) project limits at NW 33rd Ave and NW 29th Ter/SW 29th Ave.

Interchanges Rest Areas 0 Simple 0 0 0 0 NA

6c.2 Assessment and Disposition Determination 1 Simple 16 0 4 4

SC&G assessment and determination. SC&G analysis of existing vegetation within impacted areas. SC&G analysis of all desirable vegetation to be preserved adjacent to mid-block crossings. Includes all pruning and selective removals for clear sight. No Tree Disposition anticipated. Assessment of the condition of existing plant material and the approach for the preservation, removal, or relocation of existing vegetation located within the project

Irrigation assessmnet is provided in Tab 25/26.

Only address reduced (limited landscape) project limits at NW 33rd Ave and NW 29th Ter/SW 29th Ave.

6c.3 Selective C&G Maintenance Report Report 0 0 0 0 0 SC&G Maintenance Plan not provided.

Roadway Length (Miles) 0.15 Simple 2 0 9 9 SC&G Plan Sheets. Assumes 2, 40-Scale Sheets (one for each median) plus 1 Layout Sheet.

3 Sheets @ 3 hrs each = 9 hrs. Only address reduced (limited landscape) project limits.

Interchanges Rest Areas 0 Simple 0 0 0 0 NA

Details 3 12 0 8 8 1 SC&G Details Sheet with 1 pruning details, 1 Vegetation Removal Table, and SC&G Notes. No Tree Disposition Charts or Relocation tables anticipated.

6c.5 Selective C&G Quantities for EQ Report 1 Simple 8 0 3 3 Summary table for EQ Report. Phase II, III, & IV submittals.

6c.6 Cost Estimate 0 Simple 0 0 0 0 No landscape cost estimate. No lump sum or relocation pay items expected.

40 0 26 26Selective C&G Technical Subtotal

6c.4 Selective C&G Plan

Task No. Task

Project Parameter

Department Consultant Negotiated

6c.1 Data Collection and Inventory

Staff Hours

FDOT District 4

Cotleur & Hearing

Provide documentation when negotiated hours differ from the calculated hours.

What is the overall project complexity? (See Selective C&G Guidelines)

Calculated

Estimator: AW 6c. Selective Clearing and Grubbing Staff Hours

Representing Print Name

6c.7 Quality Assurance/Quality Control % 1 5% 2 0 2 2

6c.8 Supervision % 1 5% 2 0 2 2

Meetings 5 10 0 10 10

Travel Time 0 0 0 0

6c.10 Field Reviews (listed below) LS 7 0 7 7

21 0 21 21

6c.11 Coordination % 1 3% 2 0 2 2

63 0 49 49 Carries to Summary Tab

Technical Meetings # Meetings Designer

Travel Time (Hours)

# Meetings

PM

Local Governments (cities, counties, MPO) 1 0 0

30/60/90/100% Comment Review Meetings 2 0 0

Utility Coordination 0 0 0

Other Meetings 0 0 0

Subtotal Technical Meetings 3 0 0 Progress Meetings (if required by FDOT) 0 0

Phase Review Meetings 2 0

Total Meetings 5 0

Field Reviews # of Staff Site Time (per staff)

Travel Time (per staff) Total Hours

Field Review #1 1 5 2 7 Field Review #2 0 0 0 0 Field Review #3 0 0 0 0 Field Review #4 0 0 0 0 Plans-in-hand Field Review 0 0 0 0

7Total Field Review Hours

Documentation

Selective C&G Total

6c.9 Selective C&G Meetings (listed below)

Selective C&G Non-Technical Subtotal

Project Activity 7: Utilities

Estimator: FAL SR 842 / Broward Blvd. from W of Berkley Blvd. to SW 22 Avenue - CAM50 451493-1-32-01

NOTE: Signature Block is optional, per District preference

Task No. Task Units No of Units Hours/ Unit Total

Hours

7.1 Utility Kickoff Meeting LS 1 2 2

7.2 Identify Existing Utility Agency Owner(s) LS 1 4 4

7.3 Make Utility Contacts LS 1 26 26

7.4 Exception Processing LS 1 0 0

7.5 Preliminary Utility Meeting LS 1 0 0

7.6 Individual/Field Meetings LS 1 6 6

7.7 Collect and Review Plans and Data from UAO(s) LS 1 6 6

7.8 Subordination of Easements Coordination LS 1 0 0

7.9 Utility Design Meeting LS 1 6 6

7.10 Review Utility Markups & Work Schedules, and

Processing of Schedules & Agreements LS 1 12 12

7.11 Utility Coordination/Followup LS 1 24 24

7.12 Utility Constructability Review LS 1 12 12

7.13 Additional Utility Services LS 1 0 0

7.14 Processing Utility Work by Highway Contractor (UWHC) LS 1 0 0

7.15 Contract Plans to UAO(s) LS 1 0 0

7.16 Certification/Close-Out LS 1 13 13

N/A

N/A

N/A

N/A

Representing Print Name

FDOT District 4

Signature / Date

TRACE Consultants, Inc.

Meeting is listed below

Meeting is listed below

3 UAO meetings x 2 hrs each, includes prep + meeting + minutes (Virtual)

Occurs once, with the initial distribution phase (13 UAOs x 0.5 hrs to review and update from FPID 446094-1)

One meeting, 1 person x (2 hr meeting) + 4 hrs (prep + minutes)

Occurs once, with the constructability plans response (assume 4 UAOs x 3 hrs each)

Follow up with each UAO as necessary, assume 4 UAOs x 6 hrs each

One compatibility review, 4 UAOs x 3 hours

N/A

Comments

To confirm utility contacts from previous Sunshine 811 Ticket for FPID 446094-1 (Anticipate 13 UAOs. Windstream, BC Water and Wastewater, Comcast, City of Ft. Lauderdale, City of Plantation, Atlantic Broadband, FPL, Crown Castle Fiber, Hotwire, CenturyLink, MCI, TECO Peoples Gas, ATT

Distribution 13 UAO contacts/distributions, initial and constructability phase (electronic delivery thru PSEE utility module) (2 hours per contact)

FPID 451493-1_SHE_TRACE.xlsx

7. Utilities Page 17 of 32 4/15/2024

Project Activity 7: Utilities

7.17 Other Utilities LS 1 0 0

Units No of Units Hours/ Unit Total Hours Comments PM Attendance at

Meeting Required? Number

EA 1 2 2 0

EA 0 0 0 0

EA 3 2 6 0

EA 0 0 0 0

EA 1 6 6 0

EA 0 0 0 0

14 Total Project Manager Meetings (carries to Tab 3) 0 Carries to Tab 3

Total Meetings

Field Meetings (see 7.6)

Design Meeting (see 7.9)

Other Meetings (this is automatically added into Utilities Total (cell F27))

Technical Meetings

Kickoff (see 7.1)

Preliminary Meeting (see 7.5)

Individual UAO Meetings (see 7.6)

N/A

7. Utilities Total

FPID 451493-1_SHE_TRACE.xlsx

7. Utilities Page 18 of 32…