This document is a Task Work Order for Professional Services issued by the State of Florida Department of Transportation (FDOT), involving AIM Engineering & Surveying, Inc. as the consultant. The contract is numbered CAL76 with a Payment FM No. of 450435-1-32-01, and the specific project is located at SR-500/US-441 at the intersection of Donegan Avenue. The document is dated 12/26/2027 and identifies Blaire Scheller as the FDOT Project Manager and Jessica Palmer as the FDOT Construction Manager.
The task work order authorizes design services with a total compensation limit of $509,759.29, broken down into various service elements including Design Services for AIM ($288,381.57), VGI ($4,272.96), FBT ($20,113.32), SEARCH ($3,910.71), BPA ($23,525.04), and GEC ($5,764.80), along with Direct Expenses for VGI ($398.33) and Geotech Services for GEC ($15,948.98). The compensation methods vary, including lump sum payments based on percentage of completion and actual expenses or billing rates. The services are to be completed by 12/26/2027, with the work to be detailed in an attached Exhibit A (Scope of Services). The document notes that an independent assessment has been performed to verify the fairness and competitiveness of the proposed services.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR PROFESSIONAL SERVICES
375-030-25
PROCUREMENT
08/21
Consultant:
Address:
Date:
12/26/2027
*Limiting or Estimating/Budgeted Amount.
Distribution:
Task Work Order No.:
Contract No.: Payment FM No.:
CAL76 450435-1-32-01
$23,525.04
Estimate
Limit
Limit
Limit
$398.33
$20,113.32
$3,910.71
$3,433,630.78
(name) (title) Signature
Catalina Chacon, PE DCPME
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
(LS2) Lump sum paid based on % of completion
(LS2) Lump sum paid based on % of completion
(LS2) Lump sum paid based on % of completion
(LA4) Units worked at loaded billing rates in Table 6
Page 1 Total
Page 2 thru 6 Subtotal
Total
(LA5) Actual expenses or at billing rates in Table 6
(LS2) Lump sum paid based on % of completion
(LS2) Lump sum paid based on % of completion
(LS2) Lump sum paid based on % of completion
Direct Expenses - VGI
Design Services - FBT
Design Services - SEARCH
Design Services - BPA
Geotech Services - GEC
Design Services - AIM
AIM Engineering & Surveying, Inc.
2161 Fowler Strereet
Suite 100
Fort Myer, FL 33901
(To be entered upon execution of T.W.O.)
Brief Task Description:
In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).
Compensation elements are as follows:
Element Description Amount Estimate/LimitMethod of Compensation
The total amount or the limiting amount of the compensation will be:
All services required under this Task Work Order will be completed on or before:
$509,759.29
$288,381.57 Limit
Design Services - VGI $4,272.96 Limit
Design Services - GEC
The consultant will provide design services for SR-500/US-441 AT THE INTERSECTION OF DONEGANAVENUE, as stated in the attached scope of services.
FDOT PM: Blaire Scheller
FDOT CM: Jessica Palmer
$5,764.80 Limit
Estimate
Signature
FDOT/AIM
Vice President
$15,948.98
$362,315.71
$147,443.58
(name) (title)
Shawn Swets
$509,759.29
Total authorizations to date (including this one):
Departmental Approval:
Consultant Acceptance:
12/27/202712/27/2027
File details come from the government source that posted it. Updated .