CN-370000-HW551-DC10OCO1.pdf
PDF 882 KB Posted
- Contract number
- HW551
- Issued by
- Florida
About this file
This document comprises a Task Assignment Notification and Change Order for Florida Department of Environmental Protection (FDEP) Contract No. HW551, Task Assignment DC010o, executed between the State of Florida Department of Environmental Protection and AECOM Technical Services, Inc. (AECOM). The contract pertains to well abandonment activities at the Aristocrat Cleaners facility located at 3201 Hollywood Boulevard, Hollywood, Broward County, Florida (Site ID ERIC_4204). Billy Hessman serves as the DEP Contract Manager, with Mark Rasberry representing AECOM.
The original task assignment, dated April 21, 2020, established a fixed-price contract valued at $7,272.62 for conducting well abandonment activities and generating a Well Abandonment Report. Change Order No. 1, executed on August 12, 2020, reduced the task amount by $887.48, resulting in a final cost of $6,385.14. The cost reduction was attributed to a decrease in subcontractor fees and oversight labor associated with abandoning four fewer wells than originally planned, as those wells had been previously abandoned during system decommissioning activities. The deliverable—the Well Abandonment Report—was originally due August 14, 2020, but the completion date was extended to October 23, 2020. Invoice requirements stipulate that payment of $6,385.14 is due upon completion of well abandonment activities and FDEP approval of the Well Abandonment Report.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Change Order No.:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
Site Name:
Site ID / Facility ID::
Description of Change [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverable:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Cost Reimbursement Fixed Fee
Original Task Amount
Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders $0.00 $0.00 $0.00 $0.00
Original Task Completion Date:
Completion Date Prior to this Change:
Net Increase/Decrease in Task Period:
Completion Date with all Change Orders:
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
FIXED PRICE
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
ITEM
$0.00
$0.00
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
Final Deliverable Due Date:
$0.00
$0.00
CHANGE IN TASK TIME
FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
WCP TAFORM 01_18
Received
HW551
1DC010o
AECOM Technical Services, Inc. (AECOM)
Mark Rasberry
850-245-8972Billy Hessman
Aristocrat Cleaners
ERIC_4204
This Task Assignment Change Order adjusts subcontractor fees and labor associated with well abandonment activities.
Well Abandonment Report
$ 7,272.62 $ 0.00 $ 0.00 $ 0.00
$ 7,272.62 $ 0.00 $ 0.00 $ 0.00 $ 7,272.62
($ 887.48) $ 0.00 $ 0.00 $ 0.00 ($ 887.48)
$ 6,385.14
10/23/2020
10/23/2020
N/A
10/23/2020
Billy Hessman Digitally signed by Billy Hessman Date: 2020.08.12 13:32:03 -04'00'
Billy Hessman Digitally signed by Billy Hessman Date: 2020.08.12 13:32:09 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2020.08.12 16:06:44 -04'00'
Digitally signed by Rasberry, Mark DN: cn=Rasberry, Mark, ou=USORL3 Date: 2020.08.17 14:50:58 -04'00'
Rasberry, Mark
$ 6,385.14 $ 0.00 $ 0.00 $ 0.00
$ 7,272.62
Rasberry, Mark Joyal
Rasberry, Mark Typewriter 8/17/2020
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01_18
Contract Number:
Task Assignment #:
Change Order #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Received
HW551
DC010o
$ 6,385.14
Well Abandonment Report
Upon completion of well abandonment activities and FDEP approval of the Well Abandonment Report $ 6,385.14
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
TO: HW551 Contract File Aristocrat Cleaners Hollywood, Broward County
ERIC_4204
FROM: Billy Hessman, Contract Manager
DATE:
August 12, 2020
SUBJECT:
Task Assignment Summary HW551 DC010o Change Order #1 Well Abandonment
Task Assignment Change Order DC010o-1 adjusts subcontractor fees and labor associated with well abandonment activities. Specific changes are detailed below:
Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.
Subtask 2: Well Abandonment Costs under subtask 2 decreased $862.21 for a reduction in subcontractor fees and oversight labor. Cost reduction is associated with abandoning four less wells than originally planned. These wells were previously abandoned during system decommissioning activities.
Task Assignment Change Order DC010o-1 results in a total cost decrease of $887.48.
The final cost total for Task Assignment DC010o-1 is $6,385.14.
FDEP COST ESTIMATEContractor: AECOM, Inc.
Date: 11-Aug-20
Task #: HW551 DC010o TACO-1 New Total SubTask 1 Project Management SubTask 6
Site: Aristocrat Cleaners SubTask 2 Well Abandonment SubTask 7
Activity/Phase: Closure SubTask 3 SubTask 8
Project Manager: Mark Rasberry SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$56.30 Project Manager 2.8 2.8 $0.00 Officer 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 Principal 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
$65.51 Sr. Engineer (Joyal) 1.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $56.30 Sr. Geologist (Rasberry) 11.0 11.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $34.65 Engineer (Tran) 16.0 16.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $23.96 Administration / Clerical (Pichardo) 1.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Hours 31.8 2.8 29.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Direct Labor $1,421.07 $157.90 $1,263.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 38.57% $548.10 $60.90 $487.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Overhead 122.13% $1,735.55 $192.84 $1,542.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,704.72 $411.64 $3,293.08 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $71.06 $7.90 $63.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 04/10 CEF AECOM Page 1
Task #: HW551 DC010o TACO-1 New Total SubTask 1 Project Management SubTask 6
Site: Aristocrat Cleaners SubTask 2 Well Abandonment SubTask 7
Activity/Phase: Closure SubTask 3 SubTask 8
Project Manager: Mark Rasberry SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $1,900.00 $1,900.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $1,900.00 $1,900.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $190.00 $190.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $2,090.00 $2,090.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $19.40 $19.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $51.90 $51.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,014.68 $419.54 $5,595.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $370.47 $41.16 $329.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $6,385.14 $460.70 $5,924.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 04/10 CEF AECOM Page 2
SITE : Aristocrat Cleaners SUBTASK: 2 Well Abandonment DATE: 11-Aug-20
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Engineer Review Well Abandonment Report 1 (Joyal) subtotal 1
Sr. Geologist Fieldwork Coordination 3 (Rasberry) Preparation of MW Abandonment Report 8
Seal Report subtotal 11
Engineer MW Abandonment Oversight 10 (Tran) Mobilization 6 subtotal 16
Admin. / Clerical Corres., Mail, Fax, etc. 1 (Pichardo) Subtotal 1
TOTAL LABOR 29
TRAVEL
TYPE RATE UNIT USAGE TOTALS
Vehicle Rental Truck $97.00 day 1 $97.00 Lodging $0.00 night 0 $0.00 Per Diem $0.00 day 0 $0.00 subtotal $97.00
TOTAL TRAVEL $97.00
SUBCONTRACTOR (EQUIP & MATERIAL PROCUREMENT)
NAME PURPOSE RATE UNIT USAGE TOTALS
subtotal $0.00
TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00
SUBCONTRACTOR (SERVICES PROCUREMENT)
NAME PURPOSE RATE UNIT USAGE TOTALS
JAEE Environmental Mobilization $400.00 ls 1 $400.00
1"-2" Well Abandonment $12.50 per ft. 102 $1,275.00 3"-4" Well Abandonment $150.00 ea 0 $0.00 2' x 2' Well Pad Removal inc ea 7 Permits 1-2 inch wells $225.00 ea 1 $225.00 subtotal $1,900.00
TOTAL SUBCONTRACTOR (SERVICES) $1,900.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QA/QC TOTALS
Analytical Costs (Fixed Lab) $0.00
TOTAL LABORATORY $0.00
FIELD EXPENSES
ITEM RATE UNIT USAGE TOTALS
Expendables $32.50 day 1 $32.50 Water level Indicator $19.40 day 1 $19.40 subtotal $51.90
TOTAL FIELD EXPENSES $51.90
Task #: HW551 DC010o TACO-1 Delta SubTask 1 Project Management SubTask 6
Site: Aristocrat Cleaners SubTask 2 Well Abandonment SubTask 7
Activity/Phase: Closure SubTask 3 SubTask 8
Project Manager: Mark Rasberry SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$56.30 Project Manager -0.2 -0.2 $0.00 Officer 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 Principal 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
$65.51 Sr. Engineer (Joyal) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $56.30 Sr. Geologist (Rasberry) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $34.65 Engineer (Tran) -2.0 -2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $23.96 Administration / Clerical (Pichardo) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Hours -2.2 -0.2 -2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Direct Labor ($77.96) ($8.66) ($69.30) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 38.57% ($30.07) ($3.34) ($26.73) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Overhead 122.13% ($95.22) ($10.58) ($84.64) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor ($203.25) ($22.58) ($180.67) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs ($3.90) ($0.43) ($3.47) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 04/10 CEF AECOM Page 1
Task #: HW551 DC010o TACO-1 Delta SubTask 1 Project Management SubTask 6
Site: Aristocrat Cleaners SubTask 2 Well Abandonment SubTask 7
Activity/Phase: Closure SubTask 3 SubTask 8
Project Manager: Mark Rasberry SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) ($600.00) ($600.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal ($600.00) ($600.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee ($60.00) ($60.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost ($660.00) ($660.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal ($867.15) ($23.01) ($844.14) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee ($20.33) ($2.26) ($18.07) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost ($887.48) ($25.27) ($862.21) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 04/10 CEF AECOM Page 2
SITE : Aristocrat Cleaners SUBTASK: 2 Well Abandonment DATE: 11-Aug-20
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Engineer Review Well Abandonment Report 0 (Joyal) subtotal 0
Sr. Geologist Fieldwork Coordination 0 (Rasberry) Preparation of MW Abandonment Report 0
Seal Report subtotal 0
Engineer MW Abandonment Oversight (2) (Tran) Mobilization 0 subtotal (2)
Admin. / Clerical Corres., Mail, Fax, etc. 0 (Pichardo) Subtotal 0
TOTAL LABOR (2)
TRAVEL
TYPE RATE UNIT USAGE TOTALS
Vehicle Rental Truck $97.00 day 0 $0.00 Lodging $0.00 night 0 $0.00 Per Diem $0.00 day 0 $0.00 subtotal $0.00
TOTAL TRAVEL $0.00
SUBCONTRACTOR (EQUIP & MATERIAL PROCUREMENT)
NAME PURPOSE RATE UNIT USAGE TOTALS
subtotal $0.00
TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00
SUBCONTRACTOR (SERVICES PROCUREMENT)
NAME PURPOSE RATE UNIT USAGE TOTALS
JAEE Environmental Mobilization $400.00 ls 0 $0.00
1"-2" Well Abandonment $12.50 per ft. 0 $0.00 3"-4" Well Abandonment $150.00 ea -4 ($600.00) 2' x 2' Well Pad Removal inc ea 0 Permits 1-2 inch wells $225.00 ea 0 $0.00 subtotal ($600.00)
TOTAL SUBCONTRACTOR (SERVICES) (600.00)
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QA/QC TOTALS
Analytical Costs (Fixed Lab) $0.00
TOTAL LABORATORY $0.00
FIELD EXPENSES
ITEM RATE UNIT USAGE TOTALS
Expendables $32.50 day 0 $0.00 Water level Indicator $19.40 day 0 $0.00 subtotal $0.00
TOTAL FIELD EXPENSES $0.00
Contractor: AECOM, Inc.
Task #: HW551 DC010o TACO-1 Original SubTask 1 Project Management SubTask 6
Site: Aristocrat Cleaners SubTask 2 Well Abandonment SubTask 7
Activity/Phase: Closure SubTask 3 SubTask 8
Project Manager: Mark Rasberry SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$56.30 Project Manager 3.0 3.0 $0.00 Officer 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 Principal 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
$65.51 Sr. Engineer (Joyal) 1.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $56.30 Sr. Geologist (Rasberry) 11.0 11.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $34.65 Engineer (Tran) 18.0 18.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $23.96 Administration / Clerical (Pichardo) 1.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Hours 34.0 3.0 31.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Direct Labor $1,499.03 $166.56 $1,332.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 38.57% $578.17 $64.24 $513.93 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Overhead 122.13% $1,830.77 $203.42 $1,627.35 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,907.97 $434.22 $3,473.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $74.95 $8.33 $66.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Contractor: AECOM, Inc.
Task #: HW551 DC010o TACO-1 Original SubTask 1 Project Management SubTask 6
Site: Aristocrat Cleaners SubTask 2 Well Abandonment SubTask 7
Activity/Phase: Closure SubTask 3 SubTask 8
Project Manager: Mark Rasberry SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $2,500.00 $2,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $2,500.00 $2,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $250.00 $250.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $2,750.00 $2,750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $19.40 $19.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $51.90 $51.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,881.82 $442.55 $6,439.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $390.80 $43.42 $347.38 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $7,272.62 $485.97 $6,786.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
4/23/2020
HW551
D000 NADC010o
AECOM Technical Services, Inc. (AECOM)
Mark Rasberry
Billy Hessman
ERIC_4204
Aristocrat Cleaners
3201 Hollywood Blvd, Hollywood, Broward County
Well Abandonment
AECOM will conduct well abandonment activities due to the site reaching closure. A Well Abandonment Report will be generated.
Well Abandonment Report
08/14/2020
10/23/2020
$ 7,272.62 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Billy Hessman Digitally signed by Billy Hessman Date: 2020.04.21 13:46:23 -04'00'
Billy Hessman Digitally signed by Billy Hessman Date: 2020.04.21 13:46:29 -04'00'
Digitally signed by Jennifer Farrell Date: 2020.04.21 16:47:32 -04'00'
Digitally signed by Rasberry, Mark DN: cn=Rasberry, Mark, ou=USORL3 Date: 2020.04.23 09:25:40 -04'00'
Rasberry, Mark
$ 7,272.62
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Well Abandonment Report 08/14/2020
Upon completion of well abandonment activities and FDEP approval of the Well Abandonment Report $ 7,272.62
$ 7,272.62
HW551
DC010o
| Task Assignment CHANGE ORDER |
| BWC Task Assignment Change Order Form (Rev 02-17).pdf |
| Task Assignment CHANGE ORDER |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
File details come from the government source that posted it. Updated .