About this file

This document is a Task Assignment Change Order (TACO #2) issued by the State of Florida Department of Environmental Protection (DEP) for Contract GC130, Task Assignment #6, with contractor NorthStar Contracting Group, Inc. The change order was prepared by the Division of Waste Management's Petroleum Restoration Program (PRP) and approved on February 8-9, 2022. The Department's Project Manager is Robert Perlowski, and the Contractor's Project Manager is Kristy Trueblood.

The change order reallocates existing funding within Task Assignment #6 for administrative services support with no net change to the original funding amount of $1,288,488.25. The itemized changes show reductions totaling $52,687.00 in Task 15 positions (Administrative Assistant, Senior Level and Accountant Staff Level) and additions totaling $52,687.00 across multiple tasks including PCPP LCAR Solicitation and Tracking (Task 5), Follow-up Correspondence (Task 8B), Self Addressed Stamped Envelopes (Task 8C), Processing and Tracking of Certified Mail Return Receipts (Task 8D), and new embedded positions for Accountant Staff Level and Database Analyst Staff Level (Task 15). The fiscal year is 2021-2022, with appropriation category 087889 and budget entity 212001. No changes were made to compensation, expiration date, or contract attachments.

View the file

Other files

File Type Posted
CN-370000-GC130-T10.pdf PDF
CN-370000-GC130-T2.pdf PDF
CN-370000-GC130-T3CO3.pdf PDF
CN-370000-GC130-T4CO3.pdf PDF
CN-370000-GC130-T5CO1.pdf PDF
CN-370000-GC130-T9CO1.pdf PDF
CN-370000-GC130.pdf PDF
PC-370000-GC130.pdf PDF
CN-370000-GC130-CMC2.pdf PDF
CN-370000-GC130-PCAPEBD9.pdf PDF
CN-370000-GC130-T11.pdf PDF
CN-370000-GC130-T13.pdf PDF
CN-370000-GC130-T2CO1.pdf PDF
CN-370000-GC130-T6CO3.pdf PDF
CN-370000-GC130-T6CO4.pdf PDF
CN-370000-GC130-T7.pdf PDF
CN-370000-GC130-T7CO2.pdf PDF
CN-370000-GC130-T8.pdf PDF
CN-370000-GC130-A2R2.pdf PDF
CN-370000-GC130-CMC1.pdf PDF
CN-370000-GC130-T12.pdf PDF
CN-370000-GC130-T13CO1.pdf PDF
CN-370000-GC130-T14.pdf PDF
CN-370000-GC130-T3.pdf PDF
CN-370000-GC130-T3CO1.pdf PDF
CN-370000-GC130-T4CO1.pdf PDF
CN-370000-GC130-T4CO2.pdf PDF
CN-370000-GC130-T5.pdf PDF
CN-370000-GC130-T6.pdf PDF
CN-370000-GC130-T6CO1.pdf PDF
CN-370000-GC130-T9.pdf PDF
CN-370000-GC130-WCP10.pdf PDF
CN-370000-GC130-WCP9.pdf PDF
CN-370000-GC130-A1R1.pdf PDF
CN-370000-GC130-PCAP10.pdf PDF
CN-370000-GC130-PCAP11.pdf PDF
CN-370000-GC130-T1.pdf PDF
CN-370000-GC130-T10CO1.pdf PDF
CN-370000-GC130-T3CO2.pdf PDF
CN-370000-GC130-T4.pdf PDF
CN-370000-GC130-T7CO1.pdf PDF
CN-370000-GC130-T9CO2.pdf PDF
CN-370000-GC130-WCP10CO1.pdf PDF
CN-370000-GC130-WCP11.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FFLLORIDA DDEEPARTMENTT OOFF

EEnvironmentall Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ronn DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawnn Hamilton Secretary

Memorandum

TO: Justin Wolfe, Acting Chief of Staff

THROUGH: John J. Truitt, Deputy Secretary, Regulatory Programs

THROUGH: Tim J. Bahr, Director, Division of Waste Management

THROUGH: Natasha Lampkin, Administrator, Petroleum Restoration Program

THROUGH: Tameshia Reid, Budget Coordinator, Division of Waste Management

FROM: Susan Fields, Environmental Administrator, Petroleum Restoration Program

SUBJECT: FY 2021 - 2022 Change Order #2 to Contract GC130 Task Assignment #6 for NorthStar Contracting Group, Inc.

DATE: February 8, 2022

TOPIC: The Division of Waste Management’s Petroleum Restoration Program (PRP) has prepared for your review and approval under DEL-1E the attached Change Order to move existing funding within the Task Assignment to continue contractor provided administrative support services.

Based upon actual expenses to date and projected funding needs the Petroleum Restoration Program has determined that moving existing funding within the Task Assignment is appropriate (as shown on the attached Itemized Description of Change). These adjustments will result in no net change to the original funding amount of Task Assignment 6.

REQUEST: We respectfully request your approval of the attached Change Order.

Attachments: Change Order #2, Itemized Description of Change.

t Tameshia N.

Reid

Digitally signed by Tameshia N.

Reid Date: 2022.02.08 14:19:48 -05'00'

Natasha Lampkin

Digitally signed by Natasha Lampkin Date: 2022.02.08 15:07:49 -05'00'

Tim J. Bahr Digitally signed by Tim J. Bahr Date: 2022.02.08 16:09:16 -05'00'

John Truitt Digitally signed by John Truitt Date: 2022.02.08 16:27:20 -05'00'

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

6 2 GC130

Addition of needed task items, and reduction of task items not needed.

Robert Perlowski 8502458917 Contractor NorthStar Contracting Group Contractor

Contractor Kristy Trueblood Contractor 8502226446

Administrative Services

$ 0.00 $ 0.00 ✔ Expiration

Expiration 0

Funding is being moved between Scopes of Work for the PRP Program as shown on the attached Itemized Description of Change.

Contractor Kristy trueblood

DEP Administrative Contract Manager

2/8/2022

Kristy Trueblood Digitally signed by Kristy Trueblood Date: 2022.02.08 13:41:02 -05'00'

Justin Wolfe

Justin G. Wolfe, Acting Chief of Staff

Digitally signed by Justin G. Wolfe, Acting Chief of Staff Date: 2022.02.09 10:18:05 -05'00'

2/9/2022

37450404555 JG 131545 212001 087889 GC130 21 $ 0.00

GC130 TA6 CO2 Memo 2.8.22.pdf
2.8.22 TR GC130 TA6 CO2 PRP_KT.pdf