CN-370000-CN221-T7.pdf
PDF 328 KB Posted
- Contract number
- CN221
- Issued by
- Florida
About this file
This is a Task Assignment Notification Form for the Florida Department of Environmental Protection (FDEP) contract CN221, Task Assignment Number 07, issued to Registe, Sliger Engineering, Inc. (RSE). The contract involves preliminary engineering services for Hurricane Irma sinkhole access repairs at Devil's Millhopper Geological State Park. The FDEP contract manager is Philip Stone, with Teri Carron serving as the FDEP project manager. RSE's project representative is John Sliger, P.E. The contract also engages multiple subconsultants including Cornerstone Land Surveying for topographic surveys, Southern Earth Sciences, Inc. for asbestos and lead-based paint testing, and Environmental and Geotechnical Specialists, Inc. for geotechnical investigations.
The contract consists of two primary subtasks with fixed-price costs totaling $24,901.10, with no reimbursable expenses. Subtask 1 ($10,222.20) encompasses project coordination, topographic survey, asbestos and lead-based paint assessment, and geotechnical investigations. Subtask 2 ($14,678.90) includes structural inspection and preliminary engineering of the existing wooden retaining wall and stairway, with cost estimates for repair versus demolition alternatives. The contract term commenced upon execution on February 6, 2018, with a completion date of December 30, 2018. Payment is due upon FDEP approval of deliverables for each subtask. The project schedule indicated completion of all work by April 1, 2018, with individual subtasks scheduled between February and April 2018.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN221-CMC2.pdf | ||
| CN-370000-CN221-CMC4.pdf | ||
| CN-370000-CN221-T12CO1.pdf | ||
| CN-370000-CN221-T2.pdf.crdownload | CRDOWNLOAD file | |
| CN-370000-CN221-T7CO1.pdf | ||
| CN-370000-CN221-T8.pdf | ||
| CN-370000-CN221-T9.pdf | ||
| CN-370000-CN221-A1.pdf | ||
| CN-370000-CN221-CMC1.pdf | ||
| CN-370000-CN221-CMC5.pdf | ||
| CN-370000-CN221-T11.pdf | ||
| CN-370000-CN221-T2.pdf | ||
| CN-370000-CN221-T3.pdf | ||
| CN-370000-CN221-CMC3.pdf | ||
| CN-370000-CN221-T5.pdf | ||
| CN-370000-WQ154-T6.pdf | ||
| CN-370000-CN221-T1.pdf | ||
| CN-370000-CN221-T12.pdf | ||
| CN-370000-CN221-T1CO1.pdf | ||
| CN-370000-CN221-T4.pdf | ||
| CN-370000-CN221-TA12 CO2.pdf | ||
| CN-370000-CN221.pdf |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: I Task Assignment No.: Owner's Name: I Project No.:
CN221 07 FDEP-BDC 61202
Project Location: Project Name:
Devil's Millhopper Geological SP Hurricane Irma Sinkhole Access Repair
Consultant Name:
Registe, Sliger, Engineering, Inc.
Consultant Representative: Phone: Email:
John Sliger, P.E. 850-894-4521 sligerj@reng.biz
FDEP Contract Manager: Phone: Email:
Philip Stone 850-245-2570 philip.stone@dep.state.fl.us
Description of Task:
Consultant to provide topographic survey, asbestos and lead-based paint survey, structural inspection, geotechnical investigations, and preliminary engineering for the sinkhole access (wooden stairway, boardwalk, and retaining wall) per the attached proposal dated 2/6/18.
Project Manager: Teri Carron, or successor
Start Date: I Upon execution Completion Date: I 12/30/18
Greg Turral
Budget Representative, FDEP
Teri Carron
Project Manager, FDEP
Philip Stone
Contract Manager, FDEP
John Sliger, P.E.
Consultant
Michael W. Foster Jr. , P.E.
Contract Authority, FDEP
Pro.iect # Grant#
61202 FD073
29 die:it FLAIR Code:
Or2 Code 37502000109
Schedule Fixed Price Cost: $24,901.10
Cost Reimbursement not to exceed: $ 0.00 Total Task Amount: $24,901.10
Approval Signatures:
Greg Tu rra I DigitaUy signed by Greg Turral Date: 2018.02.0615:01 ;36 -05'00'
Signature
Theresa Carron Digitally signed by Theresa Carron Date: 2018.02.06 15:13:40 -05'00'
Signature
Ph'1l1'p T Stone DigitallysignedbyPhlllpT.Stone
• Date: 2018.02.09 13:28:06 -05'00'
Signature John F Sliger II
2018.02.12 10:15:49 -05'00'
Signature
2-8-2017
Date
Date
2/9/2018
Date
2/12/2018
Date
~J-:;/4 Dair '
Cat/Year Fund Module Ob.iect Code EO Amount
080039/18 675002 U3200 131500 XR $24,901.10
Total: $24,901.10
:a.----. 8Jt119rB:natneert:na, Xno.
CIVIL, STRUCTURAL AND WATER RESOURCES
3370 CAPITAL CIRCLE NE SUITE J, TALLAHASSEE, FL 32308
PHONE: (850) 894-4521 ~ FAX: (850) 224-0505
February 6, 2018
Theresa R. Carron
Preconstruction Project Manager
Bureau of Design and Construction, (BDC)
Florida Department of Environmental Protection
3800 Commonwealth Boulevard 260L, MS 520
Tallahassee, FL 32399
RE: Consultant Contract Number CN221 TA 07
Devil's Mill hopper Geological State Park-Sinkhole Access Preliminary Engineering
Dear Teri, For your review, Registe, Sliger Engineering, Inc. (RSE), has provided a proposal summary and man hour documentation for the services identified below:
• Survey, asbestos and lead based paint survey, structural inspection, and preliminary engineering for wooden staircase, retaining wall, and boardwalk accessing the sinkhole.
Please review the attached Proposal Summary and deliverables.
John Sliger, P.E.
Vice President/Project Manager
Subtask 1: Preliminary
Sinkhole Access Preliminary Engineering Devil's Millhopper Geological State Park
CN221, Task Assignment Number 07
Description: Design team will provide coordination with subconsultants and BOC, provide design survey and geotechnical services for the sinkhole access, as well as Lead/ Asbestos survey of the existing boardwalk and retaining wall.
• lA: RSE will provide overall project management and coordinate with subconsultants and BDC.
• 1B: Design Survey- Cornerstone will provide a topographic survey to include the retaining wall and will extend 20 feet on both sides of the entire staircase and 30 feet around the lower platform and include the retaining wall at the top of the stairs. Cornerstone will provide elevations at all corners of each landing and all corners at the top and bottom of each row of stairs. Cornerstone will also locate the support columns as requested. A minimum of 2 benchmarks will be located on site or near the area for easy location by others. All work will be based on a recorded vertical datum (NAVD88), but will not be in State Plane Coordinate System for Horizontal locations. All work will meet or exceed Florida Minimum Standards for Topographic Surveys. FDEP will allow access to the site.
• lC: Asbestos & Lead Based Paint Testing - Southern Earth Sciences, Inc. (SESI) proposes to perform an Asbestos NESHAPS (40CFR Part 61) demolition survey of the visitor walkway/hiking trail (about½ mile long) and retaining wall at the Devil's Millhopper Geological State Park. SESI will also use an EPA Toxic Substances Control Act (TSCA) Lead Based Paint (LBP) Inspector to test exposed surfaces for LBP using a RMD LPA-1 XRF. SESI will issue a report with identified locations, quantities and actions for demolition. SESI will collect a sample for Toxicity Characteristic Leaching Procedure (TCLP) Lead if LBP is identified on the surfaces. FDEP will allow access to the site.
• lD: Geotechnical Letter Report - Environmental and Geotechnical Specialists, Inc. (EGS) will determine the Depth to Rock (within 10 feet of the existing surface) along the alignment of the existing boardwalk and overlook area, on 500 feet centers. Provide depth to rock measurements on an aerial plan sheet, as well as provide cone penetrometer results of the soils encountered, on 2 ½ feet centers. EGS will provide results in a geotechnical letter report.
Deliverable: Design team will provide BOC with topographic survey, digitally signed and sealed Geotechnical Report, and Asbestos & Lead Based Paint Report. Topographic survey will be in electronic 24x36 pdf and native Autocad drawing file format.
• lA: RSE will provide digital copies of emails or memos to BDC documenting coordination with subconsultants and BCD.
• lB: Design Survey-Cornerstone Land Surveying will provide the finished survey on disk in Autocad format using FDEP's standards and provide a scan of the signed survey.
• lC: Asbestos & Lead Based Paint Testing - SESI will issue a report with identified locations, quantities and actions for renovation via email to BDC in digital format.
• lD: Geotechnical Letter Report - EGS will provide a digitally signed and sealed Geotechnical Report including recommendations and allowable bearing capacity for the proposed shallow foundation.
One hardcopy and one digital copy of the signed final report will be delivered to BDC.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask lA: Coordination - RSE
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Registe, Sliger Engineering Senior Project Manager $187.14 8 $1,497.12
Reimbursable expense $0
Subtask 1A Total $1,497.12
Subtask lB: Design Survey- Cornerstone
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Cornerstone Principal Surveyor $95.19 8 $761.52
Cornerstone Survey Crew $96.00 28 $2,688.00
Cornerstone Cadd Tech/Drafting $60.00 16 $960.00
Subtask 1B Total $4,409.52
Subtask 1C: Asbestos & Lead Based Paint Testing- Southern Earth Sciences
Firm Name Position Classification Hourly Hours Total Fixed
Rate Price Cost
Southern Earth Sciences Asbestos Consultant $127.00 16 $2,032.00
Task Description Rate Each Qty
Lab Fees Bulk Polarized Light $25.00 8 $200.00
Microscopy (PLM) Subtask lC Total $2,232.00
Subtask lD: Geotechnical Investigation - EGS
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
EGS, Inc. Senior Engineer $194.76 1 $194.76
EGS, Inc. Engineering Intern $77.25 4 $309.00
EGS, Inc. Sr. Engineering Technician $78.99 20 $1,579.80
Subtask 1D Total $2,083.56
Total for Subtask 1: $10,222.20
Subtask 2: Existing Wooden Retaining Wall and Stairway Structural Inspection and Report
Description: RSE will conduct an inspection of one wooden retaining wall and stairway/decking.
• 2A: Structural Inspection and Letter Report of Findings - RSE will conduct one site visit with two engineers and one engineering intern to structurally evaluate all the visual elements of one of the existing wooden retaining wall and stalr:way/decks. RSE will expose one pile to a depth of no more than three feet below existing ground surface to determine the pile condition underground. RSE will provide a letter report of findings to FDEP. No material or destructive testing will be performed.
FDEP will allow RSE access to the site.
• 2B: Preliminary Engineering Letter Report - RSE will prepare a Preliminary Engineering Letter Report with an opinion of probable cost for repairing the existing stairway/retaining wall verses an opinion of probable cost for demolishing and replacing the stairway/retaining wall in kind or one other material option. No plans or details will be provided.
Deliverable:
• 2A: RSE will provide letter report of findings based upon the structural inspection, in PDF format.
• 2B: RSE will provide a Preliminary Engineering Letter Report, in PDF format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2A: Structural Inspection and Letter Report of Findings - RSE Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Registe, Sliger Engineering Chief Engineer $215.42 14 $3,015.88 Registe, Sliger Engineering Senior Project Engineer $164.67 18 $2,964.06 Registe, Sliger Engineering Engineer Intern $80.62 34 $2,741.08
Reimbursable expense $0 Subtask 2A Total $8,721.02
Subtask 2B: Preliminary Engineering Letter Report - RSE Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Registe, Sliger Engineering Chief Engineer $215.42 4 $861.68 Registe, Sliger Engineering Senior Project Manager $187.14 10 $1,871.40 :
Registe, Sliger Engineering Engineer Intern $80.62 40 $3,224.80 I
Reimbursable expense $0 Subtask 2B Total $5,957.88
Total for Subtask 2: $14,678.90
Proiect Schedule: Based upon receiving NTP by February 12, 2018
Activity Duration (Calendar Days) Dates
Subtask lA: Coordination - RSE 7 2/12/18 - 2/19/18 Subtask lB: Design Survey- 21 2/19/18 - 3/05/18 Cornerstone
Subtask lC: Asbestos and LBP 21 2/19/18 - 3/05/18
Survey
Subtask 1D: Geotechnical 30 2/19/18 - 3/12/18 Investigation and Report Subtask 2A: Structural 21 2/19/18 - 3/05/18 Inspection & Letter Report of Findings Subtask 2B: Preliminary 21 3/12/18 - 4/01/18 Engineering Letter Report
Summarv of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask lA: Coordination - RSE $1,497.12 $0.00
Subtask lB: Design Survey- $4,409.52 $0.00
Cornerstone
Subtask lC: Asbestos & Lead Based $2,232.00 $0.00
Paint Testing - Southern Earth Sciences
Subtask 1D - Geotechnical $2,083.56 $0.00 Investigation - EGS
Subtask 2A: Structural Inspection - RSE $8,721.02 $0.00
Subtask 2B: Preliminary Engineering - $5,957.88 $0.00
RSE
Total Fixed Price Cost: $24,901.10
Total Reimbursable Cost: $0.00
Overall Total Cost: $24,901.10
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.