CN-370000-CN208-T5-CO1.pdf
PDF 761 KB Posted
- Contract number
- CN208
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) involving the consultant firm Calvin, Giordano & Associates. The change order modifies Task Assignment #5 under FDEP Contract No. CN208 for the Biscayne Bay Environmental Center 40 Year Re-Certification project located in Miami. The primary contacts include James Messick, P.E. as the consultant representative, and Mae Roth as the FDEP Contract Manager. The change order was approved on December 12, 2017, by Patricia Rose (Budget Representative), Kevin Levern (Project Manager), Mae Roth (Contract Manager), and James Messick, with final authorization by Joanna Walczak (Contract Authority) on December 26, 2017.
This is a time-only change order with no adjustment to task amounts. The original task amount of $15,182.00 (consisting of $382.00 in reimbursement and $14,800.00 in fixed fees) remains unchanged. The modification extends the task execution period by 90 days, from the original end date of December 31, 2017, to a new end date of March 31, 2018. The extension was requested due to delays in procuring a qualified electrical vendor and delays in permitting for electrical improvements associated with the Pelican Harbor Site Electric project. No change order amount is reflected in the FLAIR code section, with a total of $0.00 recorded.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN208-T2.pdf | ||
| CN-370000-CN208-T4.pdf | ||
| CN-370000-CN208-T5.pdf | ||
| CN-370000-CN208-CMC1.pdf | ||
| CN-370000-CN208-CMC3.pdf | ||
| CN-370000-CN208-T12.pdf | ||
| CN-370000-CN208-T14.pdf | ||
| CN-370000-CN208-T6CO1.pdf | ||
| CN-370000-CN208-T7CO1.pdf | ||
| CN-370000-CN208-T9.pdf | ||
| CN-370000-CN208-A1.pdf | ||
| CN-370000-CN208-CMC2.pdf | ||
| CN-370000-CN208-T1.pdf | ||
| CN-370000-CN208-T11.pdf | ||
| CN-370000-CN208-T12CO1.pdf | ||
| CN-370000-CN208-T13CO1.pdf | ||
| CN-370000-CN208-T3.pdf | ||
| CN-370000-CN208-T6.pdf | ||
| CN-370000-CN208-T7.pdf | ||
| CN-370000-CN208-T9CO2.pdf | ||
| CN-370000-CN208-T9CO2.pdf.crdownload | CRDOWNLOAD file | |
| CN-370000-CN208.pdf | ||
| CN-370000-CN208-CMC4.pdf | ||
| CN-370000-CN208-T10.pdf | ||
| CN-370000-CN208-T13.pdf | ||
| CN-370000-CN208-T7CO2.pdf | ||
| CN-370000-CN208-T9CO1.pdf | ||
| CN-370000-CN208-TA8.pdf | ||
| CN-370000-CN208.pdf.crdownload | CRDOWNLOAD file |
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
OOO – 012 (Effective 5-19-2016) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN208 TA5 1 CN1704
Biscayne Bay Environmental Center, Miami 40 Year Re-Certification
Calvin, Giordano & Associates
James Messick 954-766-2789 jmessick@cgasolutions.com
Mae Roth 850-245-2781 mae.roth@dep.state.fl.us
Time Only Change Order - project will not be completed within the original contract period. See attached request for additional time.
$ 382.00 $ 14,800.00 $ 15,182.00 $ 382.00 $ 14,800.00 $ 15,182.00 $ 0.00 $ 0.00 $ 0.00
$ 382.00 $ 14,800.00 $ 15,182.00
07/17/2017
12/31/2017
12/31/2017
3/31/2018
Patricia Rose 12/12/2017
Kevin Levern 12/12/2017
Mae Roth 12/12/2017
James Messick, P.E. 12/12/2017
Joanna Walczak 12/26/2017
$ 0.00
From: James Messick [mailto:JMessick@cgasolutions.com] Sent: Friday, December 08, 2017 8:24 AM To: Rose, Patricia <Patricia.Rose@dep.state.fl.us> Cc: Thom Palumbo <TPalumbo@cgasolutions.com>; Levern, Kevin <Kevin.Levern@dep.state.fl.us>;
Manuel Docurro <MDocurro@cgasolutions.com>; Jose Jimenez <JJimenez@cgasolutions.com> Subject: FDEP Task Assignment #5 - Pelican Harbor Site Electric
Patricia, Please consider this email as request to extend the above referenced (and attached) Task Assignment #5 for the Pelican Harbor Site Electric project from 12/31/17 to 3/31/17 to the task 2 – Services During Construction portion of the contract. This extension is due to delays in procuring a qualified vendor as well as delays in permitting for the electrical improvements. Please forward an updated change order so that we can execute and continue to work under an agreed upon Task Assignment for this project.
Thank you, Jimmy Messick, P.E.
Project Manager | Engineering Department (Broward)
Calvin, Giordano & Associates, Inc. | 1800 Eller Drive | Suite 600 | Fort Lauderdale, FL 33316 Office: 954.921.7781 | Direct: 954.766.2789 | Fax: 954.921.8807 Fort Lauderdale | Miami-Dade | West Palm Beach | Clearwater/Tampa | Estero | Port St. Lucie
This transmission may contain information that is privileged, confidential and/or exempt from disclosure under applicable law. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution, or use of the information contained herein (including any reliance thereon) is STRICTLY PROHIBITED. If you received this transmission in error, please immediately contact the sender and destroy the material in its entirety, whether in electronic or hard copy format. Thank you.
http://www.calvin-giordano.com/ https://goo.gl/maps/Y74p8AffPPC2 https://goo.gl/maps/Y74p8AffPPC2 https://www.facebook.com/Calvin-Giordano-Associates-Inc-315572025453925/ https://twitter.com/cga_solutions https://www.linkedin.com/company-beta/136435/
| CN208 TA5 Change Order 1-corrected end date |
| CN208 TA5 Change Order 1 Messick email |
File details come from the government source that posted it. Updated .