This document is a Request for Proposal (RFP) from the Arizona Department of Environmental Quality (ADEQ), Solicitation No. BPM006010, for ASRAC Assessment and Remediation of Hazardous Substances. The RFP includes Attachment 11 - References, which provides four client references for Tetra Tech, spanning work with San Bernardino County (California), Le Petomane Inc. (Nevada), Lockheed Martin Corporation (California), and Ivanhoe Electric Inc. (Arizona).
The references demonstrate Tetra Tech's extensive experience in environmental services, including environmental site assessments, soil and groundwater investigations, remediation system design, regulatory permitting, groundwater modeling, treatment plant management, and environmental compliance. The projects range from long-term engagements (since 1994 with Lockheed Martin) to current ongoing work, with project scopes varying from site characterization and hazard mitigation to detailed environmental inspections and compliance monitoring. Project values range from approximately $4 million for the Salero Ranch Mine site to over $50 million for the Lockheed Martin groundwater treatment project, highlighting the company's capability to handle complex environmental remediation efforts across diverse industries and geographical locations.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposal
Solicitation No. BPM006010
ASRAC Assessment and Remediation of Hazardous Substances
Arizona Department of Environmental Quality (ADEQ)
1110 W. Washington Street Phoenix, AZ 85007
Solicitation Attachment – References | Revision No. 1 | Revised 11-22
Attachment 11 – References
ADEQ intends to conduct reference checks for accounts provided by Offerors. ADEQ may, at its sole discretion, contact additional clients not presented as references, including internal state clients. Offerors shall provide at least three (3) client references for assignments that replicate or mirror the requirements of this Solicitation. At least one (1) of the projects referenced must be related to public sector work. All references shall be for work received and completed within the last five (5) years. Include information which documents successful and reliable past performance to clients providing services similar to those detailed in solicitation Scope of Work, DO NOT include ADEQ references.
1 Client company/Address Contact Begin date End date
San Bernadino County 777 East Rialto Avenue, San Bernardino, CA 92415-0831 James Jenkins 2002 Current
Phone number Email address
909-387-8812 / 909-844-3334 jjenkins@airports.sbcounty.gov
Summarize the scope and deliverables provided, including timeline and outcome.
On behalf of San Bernadino County Tetra Tech provides environmental site assessments; soil and groundwater investigations;
removal actions; groundwater monitoring/reporting; soil import/export profiling; RAP preparation; public outreach and participation; remediation system design and implementation; construction environmental response; and oversight of remedial actions.
List key Materials or Services provided.
Environmental Site Assessments; soil, soil vapor, and groundwater subsurface investigations; groundwater monitoring and reporting; plan preparation (work plans, health and safety plans, quality assurance project plans, and sampling and analysis plans); remediation system design and implementation; time-critical removal actions; feasibility studies; pilot studies;
numerical groundwater flow and contaminant transport modeling; human health and ecological risk assessments; regulatory permitting; aquifer testing; waste characterization and disposal; public outreach and participation; and Geotracker data processing and uploads.
2 Client company/Address Contact Begin date End date
Le Petomane, Inc., 510 S. Fourth Street, Henderson, NV 89015 Brian Loffman 2017 Current
Phone number Email address
702-960-4301 brian.loffman@lepetomaneinc.com
Summarize the scope and deliverables provided, including timeline and outcome.
The subject project involves overall site management, site characterization, and development of site remediation actions at the former Salero Ranch Mine site near Patagonia, Arizona. The project objectives include implementing measures to reduce potential Site risks to humans and the environment, and stabilize mining-related structures, tailings storage facilities, waste rock dumps, acid mine drainage, and safety hazards (open mine features). The project included a detailed characterization of Site conditions and hazards. The approximate cost of the project is anticipated to be approximately $4 Million at its completion. All remediation activities are now complete, and the site is being monitored and prepared for transfer to a new owning entity.
List key Materials or Services provided.
Mekaela Bennett (Key Personnel for this solicitation) is the Project Manager for the remediation implementation phase. Her responsibilities include management of characterization activities, remediation activities, reporting, and detailed budget monitoring. She also manages all field coordination and overall task management. Daryl Longwell is the Project Engineer for remediation design and implementation. Dylan Begley, Jon Logan, Miles Hearn, April Hussey, Kyle Avery, and Ryan Toomey have all provide support of investigation, design development, or construction oversight on the project.
mailto:jjenkins@airports.sbcounty.gov mailto:brian.loffman@lepetomaneinc.com
Request for Proposal
Solicitation No. BPM006010
ASRAC Assessment and Remediation of Hazardous Substances
Arizona Department of Environmental Quality (ADEQ)
1110 W. Washington Street Phoenix, AZ 85007
Solicitation Attachment – References | Revision No. 1 | Revised 11-22
3 Client company/Address Contact Begin date End date
Lockheed Martin Corporation Energy, Environment, Safety and Health 2550 North Hollywood Way, Suite 406, Burbank, CA 91505
Patrick T. McCullough, PG, CHg, QSD 1994 Current
Phone number Email address
818-847-0584 Patrick.t.mccullough@lmco.com
Summarize the scope and deliverables provided, including timeline and outcome.
The subject project involved characterization of the vertical and horizontal extent of a 10-mile long 3-mile wide solvent and perchlorate plume, construction of a 3-dimensional fate and transport groundwater model that encompasses the western and central portion of the 120 mi2 groundwater basin, and design and treatment of potable production wells to remove volatile organic compounds (VOCs) and perchlorate. The treatment systems are capable of treating over 20,000 gallons per minute (gpm) for potable supply for four water purveyors in the Basin. The approximate cost of project exceeds $50,000,000 over the past 20years, with a typical annual budget of $2,000,000
List key Materials or Services provided.
Services included installation of groundwater monitoring wells and sampling for plume characterization; installation of potable water supply production wells to replace lost capacity due to perchlorate and TCE impacts; development and maintenance of the 3D fate and transport groundwater model; management of the engineering design/build team of several treatment plants to treat up to 20,000 gpm of impaired water to potable well standards, and stakeholder and regulator interface and negotiation.
4 Client company/Address Contact Begin date End date
Ivanhoe Electric Inc.
99 North Sacaton St. Casa Grande, AZ 85122 Kami Ballard 2022 Current
Phone number Email address
928-965-6059 Kami.Ballard@ivanhoeelectric.com
Summarize the scope and deliverables provided, including timeline and outcome.
Environmental compliance, permitting, health & safety, and consulting support.
List key Materials or Services provided.
Tetra Tech performs the required inspections at each active and reclaimed drill site to ensure the project complies with the SWPPP and SPCC. SWPPP inspections are conducted every 2 weeks, SPCC inspections monthly, BMP inspections are daily.
Other responsibilities include the following: Coordinating with Permitting and Social Responsibility, Operations department, and drill crews; Rectifying field-level issues with disturbance areas; Marking and confirming the location of drill sites prior to site construction; Checking that biological and cultural resource environmental clearances have been completed prior to drill site construction; Checking active drill sites for compliance with 811 (underground utilities location);Coordinating reclamation post drilling, if needed; Inspecting drill site condition post-reclamation; and Documenting and reporting site inspection results to the Ivanhoe Electric team.