This document is a Rail Operations Track Allocation Procedure issued by LA Metro that establishes the requirements and processes for obtaining approval and work permits to conduct maintenance, repair, and contractor work on Metro Rail property and infrastructure. The procedure applies to all work performed on Metro Rail property, track zones, stations, buildings, and equipment critical to rail system operation. The Track Allocation registration and submission process occurs online at https://metrotrackallocation.azurewebsites.net/, with submission deadlines of one week in advance for standard work requests (by 4 p.m. Friday prior to the weekly Tuesday 9 a.m. Track Allocation meeting) and three weeks in advance for work requiring changes to revenue train schedules such as single tracking or bus bridges. Weekly Track Allocation meetings are held every Tuesday at 100 South Santa Fe Avenue, Room 10, Los Angeles, CA 90013, though meetings are currently conducted via conference call due to the COVID-19 pandemic. All work crew members must complete Metro Rail Safety and Metro Wayside Worker Protection training (conducted in English), obtain safety ID badges, and attend required job briefings. Work priorities are established for emergency repairs, regulatory preventive maintenance, infrastructure and equipment maintenance, high-priority work activities, and contractor work activities.
Work permits are issued for approved requests and must be activated upon arrival at the work location and deactivated at the end of each workday by the Engineer in Charge (EIC). Operational restrictions apply depending on proximity to overhead catenary systems and contact rails, including power down and grounding requirements, flag protection protocols, and wayside worker protection measures. The request form requires complete information including work start and end times, dates, locations, crew size, operational restrictions and impacts, power requirements, and detailed work descriptions. Requests may be submitted up to one month in advance and must be resubmitted for each week of work until project completion. Late requests submitted after the Friday deadline are reviewed at the end of the meeting and approval is not guaranteed based on manpower availability and train service impact. The Track Allocation Coordinator may deny requests due to scheduling conflicts, incorrect information, lack of required training or support, or insufficient notice.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rail Operations Track Allocation
Procedures martinezcarl Text Box
ATTACHMENT B
Rail Operations Track Allocation Procedure
Page 2 of 17 V3 Updated: 03/25/2020
Table of Contents:
Guidelines, Registration, and Submission.…………………………………………………………….…………………... Page 3 Meeting.…………………………………………………………………………………………………………………….…………...… Page 4 Work Permit, Rules and Procedures, Safety Training………………………………………………………….……... Page 5 Rail Safety Training Information………………………………………………………………………….…………....…...…. Page 6 Track Allocation Process Flow.….………………………………………………………………………………….…….……... Page 7 Contacts………………………………………………………………………………………………………………………...….………. Page 8 New User Guide…………………………………………………………………………………………………………............…… Page 9 Track Allocation Weekly Meeting…………………………………………………………………………………….…..……. Page 16 Track Allocation Document…………………………………………………………………………………….……………….... Page 19 Track Allocation Progress…………………………………………………………………………………………………….……. Page 21 Future Track Allocation Process Flow…………………………………………………………………………………..……. Page 23
Page 3 of 17 V3 Updated: 03/25/2020
All work on Metro Rail Property or any work that could potentially foul the envelope of a train must receive prior approval from the Rail Operations Control Department of Metro. This Track Allocation/Work Permit process must be complied with to ensure the safety of external agencies, Metro employees, and Metro customers. Metro Rail Operations Control Work Permits will be issued for approved work. Failure to meet all the requirements listed below will delay the approval of requested work.
GUIDELINES1
Track Allocation has defined the priorities listed below as guidelines to be considered when allocating access to any and all rail infrastructure, track zone area (Right-of-Way), station, buildings/rooms, property and any equipment critical to the operation of the rail system. The following guidelines are to be used to prioritize track access and/or Track Allocation scheduling, but are subject to change:
• Emergency repairs
• Regulatory preventive maintenance programs
• Maintenance of infrastructure and equipment
• High priority work activities
• Contractor work activities/access
REGISTRATION
Registrations is done online at https://metrotrackallocation.azurewebsites.net/. We recommend that you do not use Internet Explorer, many have had issues with submitting and registering. Once your registration is approved, you will be able to submit Track Allocation. Please refer to the New User Guide on pages 9-16.
SUBMISSION
Submissions are done on the same link as registration. When submitting track allocation, the previously entered contact information from registration will automatically populate. When a track allocation form is submitted, you will have the ability to re-use the same form.
Request forms must be filled out completely and provide necessary information: start/end time of work, dates of work, location(s) of work, crew size, operational restrictions, operational impacts, power requirements, and a detailed description of work, required support, equipment, and of required building/room access. Operational Restrictions include:
• Power Down and Grounding: may be required when working within 10-feet of Overhead Catenary System (Blue/Expo/Green/Gold Lines). Power down and grounding of the Contact Rail (Red/Purple Line) is required when working at track level. Remote power down may be required for work being performed in close proximity to the Overhead Catenary System or Contact Rail. Your work will begin once all Power Down requirements are met.
• The work crew leader (EIC) must assure that proper flagging protection for Flag Protected Slow Zones or Flag Protected Work Zones are in place (if applicable) prior to beginning work. This must be assured through proper communications with Metro personnel (Track Inspector, Field Supervisor, Traction Power or Signal Personnel) supporting your work. Proper placement of flags and the appropriate protection is required for the intended work to be performed.
• Wayside System personnel (track, signal, traction power etc.) will be provided appropriate Wayside Worker
1 The priorities listed above are guidelines and are subject to change based on Metro’s goals and objectives.
https://metrotrackallocation.azurewebsites.net/
Page 4 of 17 V3 Updated: 03/25/2020
Protection2 with clear limits/block and it will be your responsibility to contact Control once you arrive at the end of your limits in order to establish a new work limit/block. You are not allowed to begin your work until you receive authorization from the Rail Operations Control Center (ROC). You will be responsible for ensuring the appropriate level of wayside worker protection is established when working on or about Metro rail lines.
Contractors and Metro Departments must allow time for the implementation of Operational Restrictions to make the area safe for work (i.e. 3 placement of flags, watch person, block protection, power down and grounding).
Submission Info:
• Request forms must be submitted 1 week in advance of the proposed work week (Sunday-Saturday).
Submissions must be received by 4pm on Friday, prior to the weekly Track Allocation meeting.
• Request requiring a change in the revenue train schedule (i.e. single tracking, bus bridge, etc.) must be submitted 3 weeks in advance of the proposed work week (Sunday-Saturday). Submissions must be received by Close of Business on Friday, 3 weeks prior to the weekly Track Allocation meeting in order to allow ample time to create a proper train schedule and to notify Metro customers of any the changes.
• Track Allocation forms are date and time stamped. If the request is submitted late, it will be reviewed at the end of the meeting. Late requests may not be approved depending on the availability of manpower to support the work and how it may impact train service.
• Requests may be submitted up to one month in advance of requested/projected start date.
• Once a request form is submitted through the Track Allocation site, you should receive an email. If you do not receive an email, please resubmit and then contact the track allocation team to ensure delivery.
• Requests must be submitted for each week of work until completion of work or project.
• Submitting a Track Allocation request does not guarantee that the approval for work will be authorized.
Meet the Line Letters:
Please see below a list of the updated line names that were implemented on November 3, 2019.
Blue Line – A Line Red Line – B Line Green Line – C Line Expo Line – E Line Gold Line – J Line
MEETING
Meetings are held at 100 South Santa Fe Avenue Room 10, Los Angeles, CA 90013 every Tuesday at 9am.
***Due to the ongoing COVID-19 pandemic and upon the advisement of the CDC, State & Local Govt’s, the Weekly Track Allocation Meetings will no longer be an in-person meeting and will instead be replaced with a Conference Call until further notice.
Conf Call Phone Number: 888.557.8511 Pin #: 9319391
A representative for the person/agency/department requesting Track Allocation shall attend the Track Allocation meeting on the Tuesday 1 week prior to the work start date to confirm details and coordinate support functions. Track
2 Wayside Worker Protection: protection provided to employees or contractors to enhance their safety while working on or about the Metro Rail Lines in accordance with the Metro Rail Operating Rules. This protection includes both "On Track Protection" — a method of protecting personnel on the right of way (ROW) that affects train movement, and "Safety Watch" — a method of protecting personnel on the ROW that does not affect train movement. On Track Protection and Safety Watch requirements are determined by the applicable Rail Rule Book and SOPs2.
3 Included but not limited to
Page 5 of 17 V3 Updated: 03/25/2020
Allocation is only granted on a weekly basis.
All Track Allocation requests will be discussed at the Track Allocation Meeting. The Track Allocation Coordinator may deny a request due to:
• No representation at TA meeting
• Scheduling conflicts
• Incorrect information
• No MOW4 Support
• No Metro Rail Safety and/or Wayside Worker Protection Training
• Planned and unplanned special events
• Does not meet TA requirement
• Not enough notice provided
• Duplicate Submissions
After the track allocation meeting, the track allocation coordinator will send out the weekly Track Allocation document. ROC will generate a permit based on the approved weekly Track Allocation document.
WORK PERMIT
Metro Work Permits will be issued for approved work. In the event you have not received your Work Permit via email by the Friday prior to the scheduled work week, contact the Floor Manager or the appropriate Rail Controllers (contacts on pg.9) a minimum of three hours prior to scheduled start time of work.
• Work permits must be activated upon arrival at approved work location and de-activated at the end of each workday with the appropriate Controller by the EIC. The Rail Controller will authorize EIC/work crew to begin work after all safety requirements are satisfied. EIC must notify the appropriate Controller each time crews move to a different work location if multiple work locations are noted on work permit. The EIC shall assure that all personnel and equipment (including flagging equipment) are clear of the mainline prior to contacting Control to cancel your work permit.
• During the required job briefing the EIC must discuss the permit, description of work being conducted, the support required, the tools/equipment being used, and the operational restriction prior to entering the Right of Way and conducting work. Appropriate notations shall be made on the Mainline Access Form.
• The EIC and the Safety Watchperson must always maintain a copy of the Operating Clearance in their possession during the time the authorized work is being conducted.
RULES AND PROCEDURES
• All work shall be performed in accordance with Metro Light and Heavy Rail Operations Rules and Procedures.
• Restrictions and protective equipment will be required per applicable rules.
• Violation of Rail Operations Rules or Procedures may result in the cancellation of a Work Permit.
• Personnel must be in proper position (facing oncoming train) and location when providing hand signals to approaching trains. When flagging the use of proper equipment (yellow flag, green flag, red flag, and flashlight) is essential in providing information to train operators. A Watchperson must not be assigned to any other duty and cannot engage in or assist with any work.
SAFETY AND WAYSIDE WORKER PROTECTION TRAINING / ID BADGE
4 Maintenance of Way
Page 6 of 17 V3 Updated: 03/25/2020
• All members of the work crew will be required to attend Metro Rail Safety and Metro Wayside Worker Protection (WWP) training.
• Safety and wayside worker protection training is only conducted in English. Ability to understand and speak English is required for Safety certification. No translation or interpreters may be used.
• Rail Safety classes are held every Wednesday from 7:00 am to 10:00 am and 11:00 am to 2:00 pm and Wayside worker classes are held every 1st and 3rd Thursday of the month from 10:00 am to 2:00 pm at 100 South Santa Fe Avenue Rm 10, Los Angeles, CA 90013 (same room as the TA meeting).
o A picture ID is required.
o Prior reservation is required. Contact Rail Instruction at 213 922-3228 or railsafety@metro.net
Due to the Coronavirus class sizes are reduced and limited, please contact
• Safety ID badges will be issued upon successful completion of the safety and wayside worker protection training by Metro Rail Safety Training staff.
• Crew members are always required to wear Metro Safety Badges while performing work on or near Metro property.
mailto:railsafety@metro.net
Page 7 of 17 V3 Updated: 03/25/2020
Track Allocation Current Process Flow
Page 8 of 17 V3 Updated: 03/25/2020
Rail Operations Track Allocation/ Work Permit Process
Page 9 of 17 V3 Updated: 03/25/2020
RAIL OPERATIONS CONTACTS
Rail Operations F. Andres Di Zitti, Manager (213) 418-3004 Track Allocation Coordinator Email: DiZittiF@metro.net
Sarah Sidani, Associate (213) 922-2051 Temporary Letter Request/Single Tracking Email: SidaniS@metro.net
Roderick Hodge, Director (213) 418-3293 Email: HodgeR@metro.net
David Peña, Sr. Planner (213) 418-3008 Email: PenaDa@metro.net
Hector A. Guerrero, Super. (213) 418-3003 Email: GuerreroH@metro.net
Rail Operations Control Center Robert Castanon, Super. (213) 418-3025 Email: CastanonR@metro.net
Armando Jimenez, Director (323) 563-5010 Email: JimenezA@metro.net
Michael Alexander, Director (323) 563-5022 Email: alexanderm@metro.net
Karen Watt Harrison, Director (323) 563-5022 Email: wattharrisonk@metro.net
ROC Floor Manager (323) 563-5022
B/D Line Control (323) 563-5290
A Line Control (323) 563-5015
E Line Control (323) 563-5095
Downtown Control (323) 563-5049
C Line Control (323) 563-5298
MOW CONTACTS:
Traction Power:
Lucian Popescu, Director (213) 922-3354 Email: PopescuL@metro.net
Mazhar Chaudhry, Sr. Manager (213) 922-3323 Email: ChaudhryM@metro.net
Signals Department:
Ricardo Moran, Director (213) 922-3218 Email: MoranR@metro.net
Alfred Weeks, Sr. Manager (213) 922-3343 Email: WeeksA@metro.net
Track Department Paul Squires, Director (323) 563-9430 Email: SquiresP@metro.net
Mark McKendrick, Sr. Manager (323) 563-9440 Email: McKendrickMP@metro.net
Facilities Maintenance Chris Limon, Director (213) 922-6637 Email: LimonC@metro.net
Elvis South, Sr. Manager (323) 826-1005 Email: SouthE@metro.net
Rail Communications Leticia Solis, Director (213) 613-2115 Email: SolisLe@metro.net
Claire Reyes, Sr. Manager (213) 613-2148 Email: ReyesCl@metro.net
SCADA
David Chu, Interim Supervisor (323) 563-5285 Email: Chud@metro.net
L Line Control: (323) 563-5055
Traction Power:
Lucian Popescu, Director (213) 922-3354 Email: PopescuL@metro.net
Mazhar Chaudhry, Sr. Manager (213) 922-3323 Email: ChaudhryM@metro.net
Signals Department:
Ricardo Moran, Director (213) 922-3218 Email: MoranR@metro.net
Alfred Weeks, Sr. Manager (213) 922-3343 Email: WeeksA@metro.net
Track Department Paul Squires, Director (323) 563-9430 Email: SquiresP@metro.net
Mark McKendrick, Sr. Manager (323) 563-9440 Email: McKendrickMP@metro.net
Facilities Maintenance Chris Limon, Director (213) 922-6637 Email: LimonC@metro.net
Elvis South, Sr. Manager (323) 826-1005 Email: SouthE@metro.net
Rail Communications Leticia Solis, Director (213) 613-2115 Email: SolisLe@metro.net
Claire Reyes, Sr. Manager (213) 613-2148 Email: ReyesCl@metro.net
SCADA
David Chu, Interim Supervisor (323) 563-5285 Email: Chud@metro.net mailto:DiZittiF@metro.net mailto:HodgeR@metro.net mailto:PenaDa@metro.net mailto:GuerreroH@metro.net mailto:CastanonR@metro.net mailto:JimenezA@metro.net mailto:PopescuL@metro.net mailto:ChaudhryM@metro.net mailto:MoranR@metro.net mailto:WeeksA@metro.net mailto:SquiresP@metro.net mailto:McKendrickMP@metro.net mailto:LimonC@metro.net mailto:SouthE@metro.net mailto:SolisLe@metro.net mailto:ReyesCl@metro.net mailto:Chud@metro.net mailto:PopescuL@metro.net mailto:ChaudhryM@metro.net mailto:MoranR@metro.net mailto:WeeksA@metro.net mailto:SquiresP@metro.net mailto:McKendrickMP@metro.net mailto:LimonC@metro.net mailto:SouthE@metro.net mailto:SolisLe@metro.net mailto:ReyesCl@metro.net mailto:Chud@metro.net
Page 10 of 17 V3 Updated: 03/25/2020
NEW USER GUIDE
This manual will detail the steps for submitting a request on the Track Allocation form https://Metrotrackallocation.azurewebsites.net.
TRACK USER REGISTRATION
Microsoft Account A Microsoft account is what you use to access many Microsoft devices and services. It’s the account that you use to sign in to Skype, Outlook.com, OneDrive, Windows Phone, and Xbox LIVE – and it means your files, photos, contacts and settings can follow you to any device. Microsoft account used to be called "Windows Live ID".
If you already use an email address and password to sign in to Microsoft devices and services, then you already have a Microsoft account.
When you first login to the site, you may be one of 3 types of users. Follow the registration steps for your user type.
• Non-Metro user without a Microsoft Account (Step 1a)
• Non-Metro user with a Microsoft Account (Step 1b)
• Metro user (Step 1c)
Step 1a: Registration Steps for Non-Metro User without a Microsoft Account
1. On the sign-in page, click “Get a new account”
2. This will bring you to a page where you can create your account.
https://metrotrackallocation.azurewebsites.net/
Page 11 of 17 V3 Updated: 03/25/2020
a. Enter your email address and any password (it doesn’t have to be the same as the password used to login to your email) and click “Next”.
b. LA Metro Track Allocation will need to access the following information from your email. Click “Yes” to accept and proceed.
3. Now that your Windows Live account is created, login with your credentials and go to Step 2.
Step 1b: Registration Steps for Non-Metro User with a Microsoft Account
1. Login to your Windows Live account. Your screen may look like:
Page 12 of 17 V3 Updated: 03/25/2020
Step 1c: Registration Steps for Metro User
1. Use your Metro login credentials to sign-in.
a. This will bring you to Metro’s login page. Login with your Metro email and password.
Step 2: User Registration
1. After logging in with your Windows Live account, you will arrive at the Track Allocation User Registration page.
a. Fill out the required fields Required Fields: First Name, Last Name, Company Name, Partnering Metro Department, Metro Contact, Field Contact, Email, Office Telephone Number, Cell Phone Number, Field Cell Phone Number Optional Fields: Email2, Email3, Contract Number, Office Fax Number
b. Accept the Terms and Conditions
i. Click on “Terms and Conditions”
ii. A pop-up window will appear.
Read all the Terms and Conditions in its entirety. Click the box for “I Accept” at the bottom.
Page 13 of 17 V3 Updated: 03/25/2020
c. Click Submit
2. You should see this screen once the registration form has been correctly filled out and submitted (it may take a while for the form to submit).
3. Check your email to see if your registration is approved.
a. If your registration was approved, you will get an email with the link to submit a track allocation request.
SUBMITTING A REQUEST FORM
1. After logging in, you will arrive at the request form.
2. Select the Metro Rail Line for the track work.
3. The Contact Information section will be pre-populated with your user registration information.
Page 14 of 17 V3 Updated: 03/25/2020
4. Select the Rail Line in which the work will be taking place. You must select the line in order to choose the Station/Facility/Etc. section.
5. Select the week where track work is taking place. Once the week is chosen, the dates will populate.
a. Use the drop-down to select the start and end times (given in military time).
Start time can be as early as 00:30 (12:30am).
End time can be as late as 23:59 (11:59pm).
b. The “X” box refers to next day. Check it if the work will go spill over into the next day (i.e overnight work 2100- 0330X).
Note that the “X” is not checked off for work that stays in the same time (ie.
2100-2359).
Keep on the same line despite going into the next day.
c. Fill out the Track and Station/Facility/Etc.
i. Depending on the Rail Line selected, you can select the station/facility from the dropdown menu or search by typing.
ii. If the station/facility is not in the dropdown menu, you can add a new item.
“X” is checked if work goes from 2100 - 0330 the next morning.
Select the work week.
Select the work hours
Page 15 of 17 V3 Updated: 03/25/2020
d. Select from the drop down which track you will be using.
i. Tracks names are different on each line. For Gold, Green, and Blue: 1 and 2. For Expo: 3 and 4.
For Red: AR and AL. For Purple:
BR and BL.
e. Select whether the work requires a Power Down “Y” or “N”.
i. Then, you can select “RMT” for
Remote Power Down, “PD&G” for Power Down and Ground.
ii. If “N” is selected, you don’t have to select anything for “RMT” and “PD&G”.
f. Fill in the crew size by selecting it from the dropdown menu or typing it directly.
6. Fill in “Description of Work and Equipment”.
a. Please be brief and concise with your description. There is a 300-character limit.
b. Hovering over each type of work (Watchperson & ProTrans, Imposed False Occupancy, etc) provides a description.
Page 16 of 17 V3 Updated: 03/25/2020
7. Fill in “Description of Required Support or Building/Room Access”.
a. Check the boxes related to Metro departments providing required support.
8. Accept the Terms and Conditions
a. Click on the Terms and Condition
b. Read it in its entirety, and check “I
Accept” at the bottom, and click ok.
9. Click Submit.
10. A successful submission brings you to this page.
11. You will also receive an email receipt of your submittal.
Note: If you selected “Y” for Power Down & Ground in the previous section, this will automatically be checked.
Do not uncheck.
Page 17 of 17 V3 Updated: 03/25/2020
Note:
• If you are filling out a request on Wednesday, the notification below will appear. Close the notification. The request form can be filled out, but it will be counted as a late request.
• Fill out a recurring work request o At the top right corner, clicking ‘My
Forms’ at the top brings up a list of your past requests o Clicking on a past submission allows you to adjust the dates for future work but leave other parts of the form filled out.