Attachment 5 Past Performance Questionnaire.docx

DOCX document 16 KB Posted

Attached to
75H70122R00050 Kyle-Wanblee Sprinkler Projects
Solicitation number
75H70122R00050
Issued by

About this file

This document contains a past performance questionnaire and details of a federal contract opportunity for construction projects. The past performance questionnaire is for a contractor proposing for an Indian Health Service construction contract to provide design and installation of a fire sprinkler system at the Kyle Health Center and replacement of a dry sprinkler system at the Wanblee Health Center. The federal contract opportunity is a solicitation for these sprinkler system projects with a period of performance of 360 calendar days, anticipated construction magnitude between $250,000 and $500,000, and firm fixed price contract type. The solicitation will be procured as a 100% small business set-aside and requests for proposal are due on the date specified in block 13 of the SF1442 form. Evaluation will be based on lowest price technically acceptable proposals.

View the file

Other files

File Type Posted
B05 Amendment 2.pdf PDF
B05 Amendment 2 Wanblee Health Center Addition.pdf PDF
B05 Amendment 2 Kyle Health Center Addition.pdf PDF
B05 Amendment 2 Kyle Wet System.pdf PDF
B05 Amendment 2 Kyle Hydrant Flow Test.pdf PDF
B05 Amendment 2 Schedule of Submissions.pdf PDF
B05 Amendment 1 Drawings Kyle Health Center.pdf PDF
B05 Amendment 1.pdf PDF
B05 Amendment 1 Drawings Wanblee Health Center.pdf PDF
Attachment 1 Wage Determination - Kyle.pdf PDF
Attachment 16 Release of Claims.pdf PDF
Attachment 3 Self Performed Calculation Sheet (Construction).docx DOCX document
Attachment 7 Appendix B Kyle Sprinkler Riser.pdf PDF
Attachment 2 Wage Determination - Wanblee.pdf PDF
Attachment 11 Appendix F Wanblee Demolition Plan.pdf PDF
Attachment 14 Appendix I Wanblee Existing Fire Suppression Plan.pdf PDF
Attachment 15 WH347 PAYROLL.pdf PDF
Attachment 4 Technical Experience Offeror Worksheet.docx DOCX document
Attachment 13 Appendix H Wanblee Existing Riser Nameplate.pdf PDF
Attachment 12 Appendix G Wanble Sprinkler Riser.pdf PDF
Attachment 8 Appendix C Kyle Existing Riser Nameplate.pdf PDF
Attachment 6 Appendix A Kyle Campus.pdf PDF
B01 75H70122R00050.pdf PDF
Attachment 10 Appendix E Wanblee Campus.pdf PDF
Attachment 9 Appendix D Kyle Fire Suppression Plan.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 6 PAST PERFORMANCE QUESTIONNAIRE

Instructions to client:

The contractor is proposing for a construction contract with Indian Health Service https://www.ihs.gov/ You are requested to complete this form, sign, and return it to the contractor so it may be submitted with their proposal.

PART I CONTRACT INFORMATION (Contractor to complete)

Contractor Name:

Project Title

Award Value

Period of Performance

Prime Contractor or Subcontractor
☐ Prime ☐ Subcontractor

Agency or Entity Name and Address

PART II PERFORMANCE INFORMATION (Client to complete)

Name / Title

Phone #

Email Address

Contract Type

Signature

Instructions: Please select the adjective rating that best reflects your evaluation of the contractor’s performance. See Part III for rating guidance.

Category
Exceptional
Good
Satisfactory
Marginal
Unsatisfactory
N/A

Quality

Schedule

Cost Control

Management

Small Business

☐☐☐☐☐☐
Regulatory Compliance
☐☐☐☐☐☐
Comments (expand as needed)

PART III RATING GUIDANCE

RATING
DEFINITION
NOTE
(E) Exceptional
Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(G) Good
Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory
Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.

File details come from the government source that posted it. Updated .