B05 Amendment 2 Schedule of Submissions.pdf

PDF 33 KB Posted

Attached to
75H70122R00050 Kyle-Wanblee Sprinkler Projects
Solicitation number
75H70122R00050
Issued by

About this file

This document provides details for a solicitation seeking design and construction services for fire sprinkler system projects at two Indian Health Service locations. The solicitation will award a firm fixed price construction contract to install a new fire sprinkler system at the Kyle Health Center in South Dakota and replace an existing dry sprinkler system at the Wanblee Health Center in South Dakota. Offerors must be small businesses with average annual revenue less than $39.5 million. The period of performance is 360 calendar days from notice to proceed. The construction magnitude is estimated between $250,000 and $500,000. The solicitation will be procured using lowest price technically acceptable procedures with price as the discriminating factor for award. The proposal due date is indicated on the SF1442 unless amended. Questions shall be submitted to the specified contracting officer by the date in the solicitation.

View the file

Other files

File Type Posted
B05 Amendment 2 Wanblee Health Center Addition.pdf PDF
B05 Amendment 2 Kyle Health Center Addition.pdf PDF
B05 Amendment 2 Kyle Hydrant Flow Test.pdf PDF
B05 Amendment 2.pdf PDF
B05 Amendment 2 Kyle Wet System.pdf PDF
B05 Amendment 1 Drawings Wanblee Health Center.pdf PDF
B05 Amendment 1 Drawings Kyle Health Center.pdf PDF
B05 Amendment 1.pdf PDF
Attachment 7 Appendix B Kyle Sprinkler Riser.pdf PDF
Attachment 2 Wage Determination - Wanblee.pdf PDF
Attachment 11 Appendix F Wanblee Demolition Plan.pdf PDF
Attachment 14 Appendix I Wanblee Existing Fire Suppression Plan.pdf PDF
Attachment 15 WH347 PAYROLL.pdf PDF
Attachment 4 Technical Experience Offeror Worksheet.docx DOCX document
Attachment 9 Appendix D Kyle Fire Suppression Plan.pdf PDF
Attachment 1 Wage Determination - Kyle.pdf PDF
Attachment 16 Release of Claims.pdf PDF
Attachment 3 Self Performed Calculation Sheet (Construction).docx DOCX document
Attachment 13 Appendix H Wanblee Existing Riser Nameplate.pdf PDF
Attachment 12 Appendix G Wanble Sprinkler Riser.pdf PDF
Attachment 8 Appendix C Kyle Existing Riser Nameplate.pdf PDF
Attachment 6 Appendix A Kyle Campus.pdf PDF
B01 75H70122R00050.pdf PDF
Attachment 10 Appendix E Wanblee Campus.pdf PDF
Attachment 5 Past Performance Questionnaire.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

KYLE AND WANBLEE FIRE SPRINKLER PROJECT Page 1 of 1

SCHEDULE OF SUBMISSIONS

Period of Performance: 360 Days (51 Weeks)

Table 1. Milestone and Deliverable Schedule

Item Duration Period

Design Contract Award

Notice to Proceed 10

10% Schematic Design Submittal 7 Days after previous milestone

Government Review 7 Days after previous milestone

65% Construction Documents Submittal 14 Days after previous milestone

Government Review 7 Days after previous milestone

95% Construction Documents Submittal 14 Days after previous milestone

Government Review 7 Days after previous milestone

Final Construction Documents Submittal 10 Days after previous milestone

Construction 284 Includes mobilization

TOTAL DESIGN DURATION 360 days