Attachment 5 - B-Pages Instructions and Proposal Schedule for Seed Project.pdf
PDF 613 KB Posted
- Solicitation number
- 693C73-26-R-000047
About this file
This document contains proposal schedule instructions and bid schedules for federal construction project PA ERFO FW TCM 2020-1(1), Rehabilitation of Trolley Bed Road and Haul Road. Offerors must submit unit bid prices with two decimal places for all pay items listed in the schedules and calculate line item amounts by multiplying unit prices by quantities. The proposal consists of two separate schedules: Schedule A (Base Task Order) containing 14 line items and Schedule B (Government Option 1) containing 21 line items. Schedule A includes mobilization, construction survey, contractor testing, soil erosion control (silt fence and fiber roll), tree removal, roadside cleanup, embankment construction, riprap placement, aggregate surface course, topsoil furnishing, turf establishment, erosion control products, temporary traffic control, and field office. Schedule B includes similar items plus additional work such as headwall and pipe culvert removal, roadway excavation, ditch excavation, geotextile separation, asphalt concrete pavement, and stone masonry headwall construction. Offerors must submit prices for every pay item to be eligible for award. Award will be made to the responsive, responsible offeror with the lowest Evaluation Total Price of Project, calculated as Schedule A Proposal Total plus Schedule B Proposal Total. The Government may award Schedule A alone with Schedule B exercisable as an option, or both schedules simultaneously. Performance periods are 63 calendar days if both schedules are awarded together, 63 calendar days for Schedule A alone, or 30 calendar days for Schedule B if exercised separately after Schedule A award. Block 17 of the SF 1442 form must separately identify dollar amounts for Schedule A and Schedule B.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPOSAL SCHEDULE INSTRUCTIONS
PROJECT: PA ERFO FW TCM 2020-1(1)
OFFERORS PLEASE NOTE: Before preparing the proposal, carefully read the
Instructions to Offerors. When preparing the proposal, comply with the following:
COMPLETING THE PROPOSAL SCHEDULE
Complete the Proposal Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Proposal Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid
Price and Amount Bid have been inserted by the Government for a pay item, do not change the
Unit Bid Price and Amount Bid for the pay item. Determine the Proposal Total for each specific individual Schedule of Work by adding the amounts of the listed items and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.
To be eligible for award, offerors must submit prices for each pay item.
Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.
Fill in the Proposal Total(s) for each individual Schedule of Work as directed on the Proposal
Summary page. Fill in the Evaluation Total Price of Project in the space provided on the
Proposal Summary page.
The amount in Block 17 of the SF 1442 should be completed as follows:
Schedule A - $ .
Schedule B - $ .
SCHEDULES OF WORK
The Proposal Schedule is comprised of the following separate schedules and options:
Schedule A (Base Task Order) - Page B-1
Schedule B (Government Option 1) - Pages B-2 through B-3
The Government will award the project as a Base Task Order (Schedule A) with the option to award Schedule B (Government Option 1); see FAR Provisions 52.217-4 and 52.217-5.
The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price by proper utilization of programmed funds and upon receipt of any additional funds required to award the task order. If complete funding is in place at the time of award of Schedule A (Base Task
Order), the Government may award Schedule B (Government Option 1) at that time. If additional funding is required for the award of Schedule B (Government Option 1), and is received after the award of Schedule A (Base Task Order), the Government has the right to exercise Schedule B (Government Option 1) at the unit prices bid no later than the task order completion date of Schedule A (Base Task Order).
COMPLETION OF WORK
The Government has estimated the number of calendar days necessary to complete all work from the effective date of the Notice to Proceed to task order completion for the various award scenarios. The maximum number of calendar days allowed (i.e., the task order performance period) is shown in Block 11 of the SF-1442 and described below.
If the Government awards the task order as Schedules A + B, the performance period to complete all work will be 63 calendar days.
If the Government awards the task order as Schedule A only, the performance period to complete all Schedule A work will be 63 calendar days and will start on the effective date of
Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original task order, the performance period to complete all Schedule B work will be 30 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and
Special Contract Requirements (SCRs). Specific work limitations may be (but are not limited to):
National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc.); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc.); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc.). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection 104.03 of the FP and SCRs).
BASIS FOR AWARD
The task order will be awarded to the responsive, responsible offeror with the lowest Evaluation
Total Price of Project, which is defined as:
Schedule A (Base Task Order) Proposal Total +
Schedule B (Government Option 1) Proposal Total +
BID SCHEDULE
Source Selection Information – See FAR 2.101 and 3.104
Project No : PA ERFO FW TCM 2020-1(1) Schedule : A
Project Name : Rehabilitation of Trolley Bed Road and Haul Road
Schedule Type : Base
Contract Quantity Pay Items
No Contract Quantity Pay Items
AMD# Line Item Number
Pay Item Number
Description Supplemental Description
Quantity Unit Unit Price Amount
A1000 15101-0000 MOBILIZATION ALL LPSM
A1010 15201-0000
CONSTRUCTION
SURVEY AND
STAKING
ALL LPSM
A1020 15401-0000 CONTRACTOR
TESTING ALL LPSM
A1030 15705-0100
SOIL EROSION
CONTROL, SILT
FENCE
4,000.000 LNFT
A1040 15705-1400
SOIL EROSION
CONTROL, FIBER
ROLL
550.000 LNFT
A1050 20120-1000 REMOVAL,
INDIVIDUAL TREE 75.000 EACH
A1060 20214-0000 ROADSIDE CLEANUP ALL LPSM
A1070 20420-0000 EMBANKMENT
CONSTRUCTION 1,500.000 CUYD
A1080 25102-0300 PLACED RIPRAP,
METHOD A, CLASS 3 110.000 TON
A1090 30110-0000 AGGREGATE
SURFACE COURSE 1,200.000 TON
A1100 62401-0300
FURNISHING AND
PLACING TOPSOIL, 4-
INCH DEPTH
2,700.000 SQYD
A1110 62502-0000 TURF
ESTABLISHMENT 2,700.000 SQYD
A1120 62901-1000
ROLLED EROSION
CONTROL PRODUCT,
TYPE 3.B
2,700.000 SQYD
A1130 63501-0000 TEMPORARY TRAFFIC
CONTROL ALL LPSM
A1140 63701-0000 FIELD OFFICE 1.000 EACH
Submitted By: Schedule Total:
B-1Bid Schedule Project: PA ERFO FW TCM 2020-1(1), Rehabilitation of Trolley Bed Road and Haul Road
BID SCHEDULE
Source Selection Information – See FAR 2.101 and 3.104
Project No : PA ERFO FW TCM 2020-1(1) Schedule : B
Project Name : Rehabilitation of Trolley Bed Road and Haul Road
Schedule Type : Option
Contract Quantity Pay Items
No Contract Quantity Pay Items
AMD# Line Item Number
Pay Item Number
Description Supplemental Description
Quantity Unit Unit Price Amount
B2000 15101-0000 MOBILIZATION ALL LPSM
B2010 15201-0000
CONSTRUCTION
SURVEY AND
STAKING
ALL LPSM
B2020 15401-0000 CONTRACTOR
TESTING ALL LPSM
B2030 15705-0100
SOIL EROSION
CONTROL, SILT
FENCE
150.000 LNFT
B2040 15705-1400
SOIL EROSION
CONTROL, FIBER
ROLL
40.000 LNFT
B2050 15706-0200
SOIL EROSION
CONTROL, CHECK
DAM
1.000 EACH
B2060 20120-1000 REMOVAL,
INDIVIDUAL TREE 2.000 EACH
B2070 20301-1200 REMOVAL OF
HEADWALL 2.000 EACH
B2080 20302-0700 REMOVAL OF FENCE (WOOD) 15.000 LNFT
B2090 20302-2100 REMOVAL OF PIPE
CULVERT 32.000 LNFT
B2100 20401-0000 ROADWAY
EXCAVATION 25.000 CUYD
B2110 20425-1000 DITCH, EXCAVATION 40.000 LNFT
B2120 20701-0700
SEPARATION-
STABILIZATION
GEOTEXTILE, CLASS
2, TYPE B
140.000 SQYD
B2130 25102-0200 PLACED RIPRAP,
METHOD A, CLASS 2 8.000 TON
B2140 30101-4000 AGGREGATE BASE
GRADING C OR D 45.000 TON
B2150 40301-0100 ASPHALT CONCRETE
PAVEMENT, TYPE 1
(3/4-INCH NMSA) 23.000 TON
B2160 40301-0100 ASPHALT CONCRETE
PAVEMENT, TYPE 1
(3/8-INCH NMSA) 12.000 TON
B2170 60201-0800 24-INCH PIPE
CULVERT
(CMP) 22.000 LNFT
B2180 60202-0200
18-INCH EQUIVALENT
DIAMETER ARCH OR
ELLIPTICAL PIPE
CULVERT
(RCP)
10.000 LNFT
B2190 61901-0000 FENCE (WOOD) 15.000 LNFT
B2200 62011-0500
STONE MASONRY
HEADWALL FOR 24-
INCH PIPE CULVERT
2.000 EACH
B2210 62401-0300
FURNISHING AND
PLACING TOPSOIL, 4-
INCH DEPTH
70.000 SQYD
B2220 62502-0000 TURF
ESTABLISHMENT 70.000 SQYD
B-2Bid Schedule
B2230 62901-1000
ROLLED EROSION
CONTROL PRODUCT,
TYPE 3.B
70.000 SQYD
B2240 63501-0000 TEMPORARY TRAFFIC
CONTROL ALL LPSM
Submitted By: Schedule Total:
B-3Bid Schedule
B-4
PROPOSAL SUMMARY
Project PA ERFO FW TCM 2020-1(1)
(1) Schedule A (Base Task Order) Proposal Total (from Page B-1) = (1) $______________________
(2) Schedule B (Government Option 1) Proposal Total (from Page B-3) = (2) $______________________
Total Price of Project (for evaluation purposes only)
EVALUATION TOTAL PRICE OF PROJECT =
(1) + (2) $______________________
Maximum Time Allowed for the Task Order if Schedules A and B are Awarded at the Same Time:
If the Government awards the task order as Schedules A + B, the performance period to complete all task order work will be 63 calendar days.
Maximum Time Allowed for Each Schedule of Work if Awarded Separately:
If the Government awards the task order as Schedule A only, the performance period to complete all
Schedule A work will be 63 calendar days and will start on the effective date of Schedule A’s Notice to
Proceed.