Attachment 4 - Statement of Work for Seed Project.pdf

PDF 149 KB Posted

Attached to
Northeast Region Construction Multiple Award Task Order Contract (MATOC)
Solicitation number
693C73-26-R-000047
Issued by

About this file

This is a Statement of Work for Seed Project No. PA ERFO FW TCM 2020-1(1), a road rehabilitation project in Philadelphia County, Pennsylvania. The project involves the rehabilitation of two roads: Trolley Bed Road (Route 404) and Haul Road (Route 405). Work activities include embankment construction, aggregate base and surface course installation, asphalt concrete pavement work, pipe culvert removal and installation, stone masonry headwall removal and installation, riprap placement, and miscellaneous related work.

The solicitation is restricted to certified Small Business Concerns. The total project cost is expected to fall within the $500,000 to $1,000,000 price range and will be split into multiple work schedules or contract options. The performance period for completing all task order work is 63 calendar days from the issuance of the Notice to Proceed. A critical scheduling constraint prohibits all work activities between April 1 and August 31, limiting execution to the remaining nine months of the year.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Seed Project No. PA ERFO FW TCM 2020-1(1)

Statement of Work

Proposals from certified Small Business Concerns will be accepted for the Rehabilitation of

Trolley Bed Road and Haul Road, Project PA ERFO FW TCM 2020-1(1), located in

Philadelphia County, Pennsylvania. The project consists of rehabilitation of Trolley Bed Road

(Route 404) and Haul Road (Route 405). The project work includes embankment construction, aggregate base, aggregate surface course, asphalt concrete pavement work, remove and install pipe culverts, removal and install stone masonry headwalls, place riprap and other miscellaneous work.

The seed project will be split into multiple work schedules/contract options, with the cost of the entire project expected to fall within the price range of $500,000 to $1,000,000.

The performance period to complete all seed project task order work will 63 calendar days after the issuance of the Notice to Proceed.

No work will be permitted from April 1 through August 31.