Attachment 4_Trainer Repair Clause.pdf

PDF 45 KB Posted

Attached to
Joint Terminal Control Training and Rehearsal System (JTC TRS) Program Federal contract opportunity
Solicitation number
FA8621-20-R-0003
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

This document outlines requirements for a trainer repair time clause in a federal contract solicitation for the Joint Terminal Control Training and Rehearsal System (JTC TRS) Program and Joint Theater Air Ground Simulation System (JTAGSS). The solicitation requires contractors to repair Category 1 discrepancies within 48 hours for CONUS sites and 96 hours for OCONUS sites to return trainers to fully mission capable status. Category 2 discrepancies must be repaired, resolved, or dispositioned within 45 duty days. Failure to meet repair time requirements will result in a reduction in monthly payments. The contract will provide for the procurement, fielding, and sustainment of high-fidelity JTC TRS and JTAGSS training systems used by the Air Force, Navy, Marines, and special operations forces to train terminal attack controllers.

View the file

Other files for this federal contract opportunity

Other files attached to Joint Terminal Control Training and Rehearsal System (JTC TRS) Program, newest first.
File Type Posted
JTC_TRS Questions for 25 June2020.pdf PDF
Q and A_09 Jun 2020.xlsx XLSX spreadsheet
Attachment 1_PWS_Revised 15 Jun 20.pdf PDF
Q and A_08 Jun 2020.xlsx XLSX spreadsheet
Q and A_05 Jun 2020.xlsx XLSX spreadsheet
Attachment 3_Price Matrix_Revised_10 Jun 20.xlsx XLSX spreadsheet
Attachment 1_PWS_Revised 10 Jun 20.pdf PDF
Attachment 7_Asset List_Revised_10 Jun 20.pdf PDF
15-5443_Kirtland AFB NM.txt TXT text file
15-5237_Ft. Hood TX.txt TXT text file
15-4531_Hurlburt FL.txt TXT text file
15-5593_Nellis AFB NV.txt TXT text file
15-5417_Ft. Carson CO.txt TXT text file
15-5343_Ft. Riley KS.txt TXT text file
15-5027_Peoria IL.txt TXT text file
15-5457_Cannon AFB NM.txt TXT text file
15-4731_Wright Patt AFB OH.txt TXT text file
15-5629_Ft. Irwin CA.txt TXT text file
15-4701_Ft. Campbell KY.txt TXT text file
15-4377_Pope_Ft. Bragg NC.txt TXT text file
15-5775_Ft. Drum NY.txt TXT text file
15-5539_JBLM_Camp Murray WA.txt TXT text file
15-5315_Will Rogers ANG OK.txt TXT text file
15-4485_Ft. Stewart GA.txt TXT text file
Draft Model Contract_Rev 1.pdf PDF
Attachment 3_Price Matrix_Revised_01 Jun 20.xlsx XLSX spreadsheet
Attachment 1_PWS_Revised_01 Jun 20.pdf PDF
Complete Q and A_01 Jun 2020.xlsx XLSX spreadsheet
JTC_TRS General Instructions 20200515_Update.pdf PDF
Draft Model Contract.pdf PDF
Exhibit A_JTC TRS CDRL_5-15-20.pdf PDF
Attachment 11_Section L_Final.pdf PDF
Attachment 3_Price Matrix_11 May 20.xlsx XLSX spreadsheet
Proposal Adequacy Checklist.pdf PDF
Attachment 10_DDForm 1653.pdf PDF
Attachment 11_Section L_Final.pdf PDF
L-1_Past Performance Questionnaire.pdf PDF
Attachment 8_GFP List.pdf PDF
Attachment 2_FoS_PSpec.pdf PDF
Attachment 9_AFMCForm158 JTC TRS.pdf PDF
L-4_PPI Tool.pdf PDF
L-3-Client Authorization Letter.pdf PDF
M1 TEST PLAN AND TEST POINTS.pdf PDF
M6 SUPPLEMENTAL AND EME TEST POINTS.pdf PDF
RFP_Cover_Letter_11 May.pdf PDF
JTC_TRS General Instructions 20200430_DRAFT.pdf PDF
Attachment 6_IUID JTC TRS.pdf PDF
Attachment 7_Asset List.pdf PDF
Exhibit A_JTC TRS CDRL_4_21_20.pdf PDF
M2 SCENARIO 1 DESCRIPTION AND TEST POINTS.pdf PDF
Show all 50

Joint Terminal Control Training and Rehearsal System (JTC TRS) Program has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8621-20-R-0003

Section H, Trainer Repair Time Requirement Clause

30 April 2020

9AFLCMC/YWK-H001 Trainer Repair Time Requirement (Apr 2020)

Joint Terminal Control Training and Rehearsal System (JTC TRS) and Joint Theater Air Ground Simulation System (JTAGSS) Requirement for Meeting Trainer Repair Time

1. Definitions and Assumptions

a. Fully Mission Capable (FMC) – is defined as a trainer which is operating and able to accomplish all performance requirements as defined in the Performance Work Statement and Performance Specification.

b. Duty Days - defined as the days on which the Air Force Unit operating the training devices is on an active duty status. For calculation purposes, duty days are Monday - Friday (at the unit location) of each month unless one is designated a federal holiday.

c. Downtime – is defined as the total number of duty days required to restore a training device to

FMC status once a failure has been reported to and acknowledged by the contractor.

d. Excusable delays – Any delay beyond the control and without the fault of the contractor. This includes instances when there is no response from the site to contractor follow-up or any time period of delay when the contractor was not granted access to the base/facility.

a. Category 1 Discrepancy: The discrepancy prevents training from occurring on a JTC TRS or

JTAGSS device. The discrepancy must be corrected before training can resume.

b. Category 2 Discrepancy: This encompasses all other unscheduled discrepancies on a JTC

TRS or JTAGSS device.

c. Category 3 Discrepancy: This encompasses planned maintenance actions to include but limited to the following: software patches, software upgrades, general administration and housekeeping, cyber security updates and scans.

d. Priority 1 Unit: The Special Tactics Training Squadron (STTS) at Hurlburt Field, Florida and the 6th Combat Training Squadron (CTS) at Nellis AFB, Nevada.

e. Priority 2 Unit: Any other unit where a JTC TRS or JTAGSS device is located.

2. Upon failure of a training device, the designated government representative shall notify the contractor of the failure, utilizing the help desk, and provide as much information as possible at that time regarding the failure. If the problem cannot be resolved and the contractor needs to travel, the government representative will advise the contractor of scheduled duty days for building access for the repair effort.

The day of failure notification shall not count as downtime. Downtime begins at the start of the first duty day after the contractor acknowledges notification and continues until the contractor has returned the training device to the FMC status. Any portion of a duty day when the training device is not at FMC, other than the reporting day, will be treated as a full day of downtime. In the event of failures at multiple units, the Priority 1 units shall be fixed first.

3. For training devices at O-CONUS sites, the time allowed for repair or resolution of Category 1 discrepancies is 96 hours. At CONUS sites, the time allowed for repair or resolution of Category 1 discrepancies is 48 hours. Resolution is defined as a Contracting Officer (CO) course of action if a repair is not necessary. In the event the same Category 1 discrepancy repeats on the same device within 30 duty days, the allowable repair time of the device is zero. Downtime will be calculated as described in paragraph 2 above.

FA8621-20-R-0003

Section H, Trainer Repair Time Requirement Clause

30 April 2020

4. Category 2 discrepancies shall be repaired, resolved or dispositioned within 45 duty days or as tasked by the CO. Disposition is defined as a documented course of action in the Help Desk Electronic Data Management System if a repair is not complete in the allotted time frame.

5. Failure to restore the training device to FMC status within the time limitations shall result in a reduction of the monthly CLS payment per device per duty day for each duty day the device is not restored. The following calculation will be used to determine the reduction in monthly CLS payment per device.

Monthly CLS Reduction = (1 – (A/B)) x Monthly CLS Price per Device

A = Number of Downtime Duty Days Outside of Allowable Repair Time B = Number of Duty Days per Month

Example: Assume CONUS Category 1 discrepancy in March 2016 with a total downtime of 3 duty days.

A = 1 Duty Day Outside of Allowable Repair Time B = 27 Duty Days in March 2016

Calculation: (1-(1/27) = 96.3% x Monthly CLS price per device, Contractor would receive 96.3% of monthly CLS price for the device in March 2016

6. In the event of a disagreement, the Contractor shall document the complete details of the dispute and elevate it to the CO for resolution. The CO’s decision shall be final.

7. This clause does not limit the Government's rights under FAR 52.249-8 Default (Fixed-Price Supply and Service), incorporated in Section I of this contract. The Government may find the Contractor in default for any deficiencies in services.

File details come from the government source that posted it. Updated .