230593_Testing Adjusting Balancing_For_HVAC.pdf

PDF 47 KB Posted

Attached to
RECOVERY - HVAC System for Camino Real Office Project
Solicitation number
AG-9702-S-10-0335
Issued by

About this file

specifications

View the file

Other files

File Type Posted
CONSTRUCTION_IFB.docx DOCX document
sf25a_e.pdf PDF
sf25.pdf PDF
233713_Diffusers Registers Grilles.pdf PDF
230553_Identification_For_HVAC_Piping Equipment.pdf PDF
230513_Common_Motor_Requirements_For_HVAC_Equipment.pdf PDF
sf25b.pdf PDF
230529_Hangers Supports_For_HVAC_Piping Equipment.pdf PDF
M100 100 .pdf PDF
233300_Air_Duct_Accessories.pdf PDF
233113_Metal_Ducts.pdf PDF
230100 HVAC System.doc DOC document
230700_HVAC_Insulation.pdf PDF
CONSTRUCTION_IFB.docx DOCX document
231126_Facility_Liquefied-Petroleum_Gas_Piping.pdf PDF
sf24_e.pdf PDF
Titlesheet —
M201 100 .pdf PDF
232300_Refrigerant_Piping.pdf PDF
USFS CR MECH CUTSHEETS.PDF PDF
DB General Decision Number.docx DOCX document
M301 100 .pdf PDF
230548_Vibration Seismic_Controls_For_HVAC_Piping Equipment.pdf PDF
Camino_ Real_titlesheet Layout1 —
235400_Furnaces.pdf PDF
238126_Split-System_Air-Conditioners.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service – Camino Real Office Building 230593 - 1

TESTING, ADJUSTING, AND BALANCING FOR HVAC

SECTION 230593

TESTING, ADJUSTING, AND BALANCING FOR HVAC

PART 1 – GENERAL

1.1 SUMMARY

A. Section Includes:

1. Balancing Air Systems:

a. Constant-volume air systems.

b. Variable-flow hydronic systems.

1.2 DEFINITIONS

A. AABC: Associated Air Balance Council.

B. NEBB: National Environmental Balancing Bureau.

C. TAB: Testing, adjusting, and balancing.

D. TABB: Testing, Adjusting, and Balancing Bureau.

E. TAB Specialist: An entity engaged to perform TAB Work.

1.3 SUBMITTALS

A. Certified TAB reports.

1.4 QUALITY ASSURANCE

A. TAB Contractor Qualifications: Engage a TAB entity certified by AABC NEBB or

TABB.

1. TAB Field Supervisor: Employee of the TAB contractor and certified by AABC

NEBB or TABB.

2. TAB Technician: Employee of the TAB contractor and who is certified by

AABC NEBB or TABB as a TAB technician.

B. Certify TAB field data reports and perform the following:

1. Review field data reports to validate accuracy of data and to prepare certified

TAB reports.

2. Certify that the TAB team complied with the approved TAB plan and the proce-dures specified and referenced in this Specification.

C. TAB Report Forms: Use standard TAB contractor's forms approved by Government.

USDA Forest Service – Camino Real Office Building 230593 - 2

D. Instrumentation Type, Quantity, Accuracy, and Calibration: As described in

ASHRAE 111, Section 5, "Instrumentation."

PART 2 – PRODUCTS (NOT APPLICABLE)

PART 3 – EXECUTION

3.1 EXAMINATION

A. Examine the Contract Documents to become familiar with Project requirements and to discover conditions in systems' designs that may preclude proper TAB of systems and equipment.

B. Examine systems for installed balancing devices, such as test ports, gage cocks, ther-mometer wells, flow-control devices, balancing valves and fittings, and manual vo-lume dampers. Verify that locations of these balancing devices are accessible.

C. Examine the approved submittals for HVAC systems and equipment.

D. Examine design data including HVAC system descriptions, statements of design as-sumptions for environmental conditions and systems' output, and statements of philos-ophies and assumptions about HVAC system and equipment controls.

E. Examine equipment performance data including fan and pump curves.

1. Relate performance data to Project conditions and requirements, including sys-tem effects that can create undesired or unpredicted conditions that cause re-duced capacities in all or part of a system.

F. Examine system and equipment installations and verify that field quality-control test-ing, cleaning, and adjusting specified in individual Sections have been performed.

G. Examine test reports specified in individual system and equipment Sections.

H. Examine HVAC equipment and filters and verify that bearings are greased, belts are aligned and tight, and equipment with functioning controls is ready for operation.

I. Report deficiencies discovered before and during performance of TAB procedures.

Observe and record system reactions to changes in conditions. Record default set points if different from indicated values.

3.2 PREPARATION

A. Prepare a TAB plan that includes strategies and step-by-step procedures.

B. Complete system-readiness checks and prepare reports. Verify the following:

USDA Forest Service – Camino Real Office Building 230593 - 3

1. Permanent electrical-power wiring is complete.

2. Automatic temperature-control systems are operational.

3. Equipment and duct access doors are securely closed.

4. Balance, smoke, and fire dampers are open.

5. Ceilings are installed in critical areas where air-pattern adjustments are required and access to balancing devices is provided.

6. Windows and doors can be closed so indicated conditions for system operations can be met.

3.3 GENERAL PROCEDURES FOR TESTING AND BALANCING

A. Perform testing and balancing procedures on each system according to the procedures contained in ASHRAE 111 and in this Section.

B. Cut insulation, ducts, pipes, and equipment cabinets for installation of test probes to the minimum extent necessary for TAB procedures.

1. After testing and balancing, patch probe holes in ducts with same material and thickness as used to construct ducts.

2. Install and join new insulation that matches removed materials. Restore insula-tion, coverings, vapor barrier, and finish according to Division 23 Section

"HVAC Insulation."

C. Mark equipment and balancing devices, including damper-control positions, valve po-sition indicators, fan-speed-control levers, and similar controls and devices, with paint or other suitable, permanent identification material to show final settings.

3.4 GENERAL PROCEDURES FOR BALANCING AIR SYSTEMS

A. Prepare test reports for both fans and outlets. Obtain manufacturer's outlet factors and recommended testing procedures. Crosscheck the summation of required outlet vo-lumes with required fan volumes.

B. Prepare schematic diagrams of systems' "as-built" duct layouts.

C. Determine the best locations in main and branch ducts for accurate duct-airflow mea-surements.

D. Check airflow patterns from the outdoor-air louvers and dampers and the return- and exhaust-air dampers through the supply-fan discharge and mixing dampers.

E. Locate start-stop and disconnect switches, electrical interlocks, and motor starters.

F. Verify that motor starters are equipped with properly sized thermal protection.

G. Check dampers for proper position to achieve desired airflow path.

H. Check for airflow blockages.

USDA Forest Service – Camino Real Office Building 230593 - 4

I. Check condensate drains for proper connections and functioning.

J. Check for proper sealing of air-handling-unit components.

K. Verify that air duct system is sealed as specified in Division 23 Section "Metal Ducts."

3.5 PROCEDURES FOR CONSTANT-VOLUME AIR SYSTEMS

A. Adjust fans to deliver total indicated airflows within the maximum allowable fan speed listed by fan manufacturer.

1. Measure total airflow.

a. Where sufficient space in ducts is unavailable for Pitot-tube traverse mea-surements, measure airflow at terminal outlets and inlets and calculate the total airflow.

2. Measure fan static pressures as follows to determine actual static pressure:

a. Measure outlet static pressure as far downstream from the fan as practical and upstream from restrictions in ducts such as elbows and transitions.

b. Measure static pressure directly at the fan outlet or through the flexible connection.

c. Measure inlet static pressure of single-inlet fans in the inlet duct as near the fan as possible, upstream from the flexible connection, and down-stream from duct restrictions.

d. Measure inlet static pressure of double-inlet fans through the wall of the plenum that houses the fan.

3. Measure static pressure across each component that makes up an air-handling unit, rooftop unit, and other air-handling and -treating equipment.

a. Report the cleanliness status of filters and the time static pressures are measured.

4. Measure static pressures entering and leaving other devices, such as sound traps, heat-recovery equipment, and air washers, under final balanced conditions.

5. Review Record Documents to determine variations in design static pressures versus actual static pressures. Calculate actual system-effect factors. Recom-mend adjustments to accommodate actual conditions.

6. Obtain approval from CO for adjustment of fan speed higher or lower than indi-cated speed. Comply with requirements in Division 23 Sections for air-handling units for adjustment of fans, belts, and pulley sizes to achieve indicated air-handling-unit performance.

7. Do not make fan-speed adjustments that result in motor overload. Consult equipment manufacturers about fan-speed safety factors. Modulate dampers and measure fan-motor amperage to ensure that no overload will occur. Measure

USDA Forest Service – Camino Real Office Building 230593 - 5 amperage in full-cooling, full-heating, economizer, and any other operating mode to determine the maximum required brake horsepower.

B. Adjust volume dampers for main duct, submain ducts, and major branch ducts to indi-cated airflows within specified tolerances.

1. Measure airflow of submain and branch ducts.

a. Where sufficient space in submain and branch ducts is unavailable for Pi-tot-tube traverse measurements, measure airflow at terminal outlets and in-lets and calculate the total airflow for that zone.

2. Measure static pressure at a point downstream from the balancing damper, and adjust volume dampers until the proper static pressure is achieved.

3. Remeasure each submain and branch duct after all have been adjusted. Contin-ue to adjust submain and branch ducts to indicated airflows within specified to-lerances.

C. Measure air outlets and inlets without making adjustments.

1. Measure terminal outlets using a direct-reading hood or outlet manufacturer's written instructions and calculating factors.

D. Adjust air outlets and inlets for each space to indicated airflows within specified toler-ances of indicated values. Make adjustments using branch volume dampers rather than extractors and the dampers at air terminals.

1. Adjust each outlet in same room or space to within specified tolerances of indi-cated quantities without generating noise levels above the limitations prescribed by the Contract Documents.

2. Adjust patterns of adjustable outlets for proper distribution without drafts.

3.6 PROCEDURES FOR MOTORS

A. Motors, 1/2 HP and Larger: Test at final balanced conditions and record the following data:

1. Manufacturer's name, model number, and serial number.

2. Motor horsepower rating.

3. Motor rpm.

4. Efficiency rating.

5. Nameplate and measured voltage, each phase.

6. Nameplate and measured amperage, each phase.

7. Starter thermal-protection-element rating.

B. Motors Driven by Variable-Frequency Controllers: Test for proper operation at speeds varying from minimum to maximum. Test the manual bypass of the controller

USDA Forest Service – Camino Real Office Building 230593 - 6 to prove proper operation. Record observations including name of controller manu-facturer, model number, serial number, and nameplate data.

3.7 TOLERANCES

A. Set HVAC system's air flow rates and water flow rates within the following toler-ances:

1. Supply, Return, and Exhaust Fans and Equipment with Fans: Plus 10 or minus 5 percent.

2. Air Outlets and Inlets: Plus 10 or minus 5 percent..

3.8 FINAL REPORT

A. General: Prepare a certified written report; tabulate and divide the report into separate sections for tested systems and balanced systems.

1. Include a certification sheet at the front of the report's binder, signed and sealed by the certified testing and balancing engineer.

2. Include a list of instruments used for procedures, along with proof of calibration.

B. Final Report Contents: In addition to certified field-report data, include the following:

1. Fan curves.

2. Manufacturers' test data.

3. Field test reports prepared by system and equipment installers.

4. Other information relative to equipment performance; do not include Shop

Drawings and product data.

C. General Report Data: In addition to form titles and entries, include the following data:

1. Title page.

2. Name and address of the TAB contractor.

3. Project name.

4. Project location.

5. CO's name and address.

6. Engineer's name and address.

7. Contractor's name and address.

8. Report date.

9. Signature of TAB supervisor who certifies the report.

10. Table of Contents with the total number of pages defined for each section of the report. Number each page in the report.

11. Summary of contents including the following:

a. Indicated versus final performance.

b. Notable characteristics of systems.

c. Description of system operation sequence if it varies from the Contract

Documents.

USDA Forest Service – Camino Real Office Building 230593 - 7

12. Nomenclature sheets for each item of equipment.

13. Data for terminal units, including manufacturer's name, type, size, and fittings.

14. Notes to explain why certain final data in the body of reports vary from indi-cated values.

15. Test conditions for fans and pump performance forms including the following:

a. Settings for outdoor-, return-, and exhaust-air dampers.

b. Conditions of filters.

c. Settings for supply-air, static-pressure controller.

d. Other system operating conditions that affect performance.

END OF SECTION 230593