A017_DID_SSR_CPSR.pdf

PDF 59 KB Posted

Attached to
F-16 Brake Control System Redesign (BCSR) Federal contract opportunity
Solicitation number
SPRHA1-21-R-7000
Issued by
Defense Logistics Agency Aviation

About this file

This document contains a Data Item Description and related federal contract opportunity solicitation. The Data Item Description outlines the format and required content for a Contractor's Progress and Status Report, including a cover sheet, results on previously identified issues, organizational changes, problem areas, cost curves, man-hour expenditures, and staffing plans. It provides templates for financial data by task, work completed by CLIN/SLIN, and staffing. The related federal contract opportunity is a solicitation for the F-16 Brake Control System Redesign program to support continued operations of the aircraft fleet. The contracting office is DLA Aviation at Hill AFB and pre-solicitation details can be found on SAM.gov. The opportunity is for the USAF to redesign the brake control system on F-16 aircraft.

View the file

Other files for this federal contract opportunity

Other files attached to F-16 Brake Control System Redesign (BCSR), newest first.
File Type Posted
Section L_REV04232021.pdf PDF
QA 19APR-23APR2021.pdf PDF
QA 12APR-16APR2021.pdf PDF
SPRHA1-21-R-7000-0003.pdf PDF
Section M_REV04162021.pdf PDF
Section L_REV04162021.pdf PDF
Section L.pdf PDF
Section M.pdf PDF
SPRHA121R7000_______0001.pdf PDF
QA 01MAR-05MAR2021.pdf PDF
22FEB-26FEB2021.pdf PDF
QA 11JAN thru 15JAN2021.pdf PDF
A016_DID_TIR_VACR.pdf PDF
A016_CDRL_TIR_VACR.pdf PDF
A008_CDRL_TIR_FMECA.pdf PDF
A011_TDP_CDMAL.pdf PDF
A007_CDRL_CDR.pdf PDF
A001_CDRL_IMS_BCSR.pdf PDF
A018_CDRL_TIR_THIR.pdf PDF
PPQ.pdf PDF
Subcont_Consent.pdf PDF
SPRHA121R7000.pdf PDF
A014_DID_TMCR_TO.pdf PDF
A015_LMI_Attachment3.pdf PDF
A015_LMI_Attachment1.pdf PDF
A012_TDP_SIE_DMAL.pdf PDF
A012_DID_SIE_EDDAL.pdf PDF
A004_CDRL_ContractorCMP.pdf PDF
A003_DID_ConfAgenda.pdf PDF
B001_CDRL_CGEP_DMAL.pdf PDF
B001_TDP_PDMAL_AD.pdf PDF
B001_DID_CGEP_CSPEI.pdf PDF
B001_DID_PDM_DMAL.PDF PDF
A018_DID_TIR_THIR.pdf PDF
Attachment_0001_DD2794_CSDR_Plan.xls XLS spreadsheet
Nongovernmental.pdf PDF
A004_DID_ContractorCMP.pdf PDF
CSDR_SOW_20201123.pdf PDF
A001_DID_IMS_BCSR.pdf PDF
A015_CDRL_LMI.pdf PDF
A015_LMI_Attachment2.pdf PDF
A013_CDRL_ST_DMAL.pdf PDF
A012_CDRL_SIE_DMAL.pdf PDF
A011_CDRL_CDMAL.pdf PDF
A013_TDP_ST_DMAL.pdf PDF
A009_DID_TRR.pdf PDF
A002_CDRL_SRR.pdf PDF
B001_DID_PDMAL_PEDDAL.pdf PDF
C002_CDRL_CHR_FF_signed.pdf PDF
C004_CBDR_CDRL_signed.pdf PDF
Show all 50

F-16 Brake Control System Redesign (BCSR) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: CONTRACTOR’S PROGRESS AND STATUS REPORT

Number: DI-MGMT-81928 Approval Date: 20130701 AMSC Number: N9391 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility: SH/PEO IWS F Applicable Forms: N/A

Use/Relationship: Contractor’s Progress, Status and Management Report provides the progress of work and the status of the Program and assigned task, report cost and informs management of existing or potential problem areas.

This Data Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.

Requirements:

1. Format. The Contractor’s Progress and Status Report shall be in format similar to that of Figures 1, 2 and 3 of this DID.

2. Content. The report shall contain a cover sheet identifying the following:

a. Title of the Report

b. Contractor’s name and address

c. Contract Number

d. Date of report and period by the report

e. Data Item Number listed on the CDRL DD FORM 1423-1

2.1. Results positive or negative obtained related to previously identified problem areas, with conclusions and recommendations shall be identified.

2.2. Any significant changes to the contractor’s organization or method of operation, to the project management network, or to the milestones shall be included.

2.3. Problem areas affecting cost elements, technical or scheduling elements, with background and any recommendations for solutions beyond the scope of the contract shall also include the following items:

a. Funding Issues

(1) Shortfalls

(2) Overfunding

b. Task Area Issues

Source: http://assist.dla.mil -- Downloaded: 2020-10-23T19:46Z Check the source to verify that this is the current version before use.

DI-MGMT-81928

2.4. The report shall contain cost curves showing actual projected conditions throughout the contract and any cost incurred for the reporting period and total contractual expenditures as of the reporting date.

2.5. The report shall contain Man-hours expended for the reporting period and cumulatively for the contract for the following areas:

a. Trip(s) outside the local area, site visited and purpose.

b. Contract schedule status.

c. Plans for activities during the following reporting period.

d. Name and telephone number of signer of the report.

e. Appendixes for any necessary tables, references, photographs, illustrations, and charts.

2.6 The report shall contain all of the information specified in Figure 3, and shall identify Employee movement, color coded/highlighted in comments column.

2.7. The report shall contain also all of the information specified in Figures 1, 2, and 3.

2.8. The report shall identify the following:

a. Title i.e.: Professional Support Services for the Program Executive Office (PEO) Integrated Warfare System (IWS)

b. Contract Number

c. Latest Contract Modification (# and Date)

d. Period of Performance

e. Reporting Period

f. Contractor’s POC

g. Government PM

h. Government COR

2.5 Financial/Labor Data. The report shall contain all of the information contained to Figure 1 including:

a. Contract Value

b. Funded to date

c. Cost of work performed during period (period to be defined as CY)

d. Planned travel for the upcoming Calendar Month to include location, number of contractor personnel and purpose.

e. Actual: Monthly Hours Burned by each contractor/employee

f. Invoice Date/Amount/Number

3. End of DI-MGMT-81928.

DI-MGMT-81927

Task Sub-task Nr. Task Description Customer Name/Employee Labor or ODCs

(Fully Burdened) Value Funded to Date

Funding Required to End of CY

(Cost)

Funding Required to End of CY

(Fixed Fee)

Funding Required to End of CY

(Total) ACTUAL: Mthly Hours Burned Invoice Number Invoiced Amount Invoiced To Date

Red indicates costs have exceeded funding

Yellow indicates costs are close to exceeding funding.

1.1 1.1.1 NMCI, NAVSEA CIO and Enterprise primary coordinator Jane Doe Labor

ODCs

1.1.2 Assist in Strategic Planning John Smith Labor

ODCs

1.1.3 Portfolio Management. John Doe Labor

ODCs

3.1 3.1.1 ACTD Operations Specialist support John Doe Labor ODCs

Totals

Page 3 of 5 Pages

FINANCIAL/LABOR HOUR DATA BY TASK- FIGURE 1

WORK COMPLETED BY TASK

CLIN/SLIN ACRN PR Number Ref Doc/ACRN MOD Appropriation Subhead OBJ PARM RFM AAA TT PPA Project Unit Funded Expended Balance

Totals $ - $ - $

Totals $ - $ - $

Totals $ - $ - $

Totals $ - $ - $

Totals $ - $ - $

Totals $ - $ - $

Grand Totals $ - $ - $

Page 4 of 5 pages

WORK COMPLETED BY CLIN/SLIN - FIGURE 2

STAFFING PLAN - FIGURE 3

NAME/EMPLOYEE LABOR TASK AREA CONTRACTOR / COMPANY GOVERNMENT FTE HOURS COMMENT

CATEGORY SUPPORTED SUBCONTRACTOR NAME SITE

Page 5 of 5 pages

Task 1 -

Task 2 -

Task3 -IWS Technical - Provide Support to PEO IWS Advanced Technology

DI-MGMT-81928 CONTRACTOR'S PROGRESS AND STATUS REPORT
a. Title i.e.: Professional Support Services for the Program Executive Office (PEO) Integrated Warfare System (IWS)
b. Contract Number
g. Government PM
h. Government COR
FIGURE 1.
Financial- Labor Hours
FIGURE 2
Work Completed By
FIGURE 3.
Staffing Plan