About this file

This is a Value Engineering Form required by the State of Utah Division of Facilities Construction and Management (DFCM) for Design-Build contractors submitting cost proposals for the DNR/DWR Logan Fish Hatchery Residence project. The form mandates that any contractor submitting a cost proposal exceeding the stated project budget must provide value engineering options that reduce the total project cost to within the budgeted amount. Contractors may propose up to ten value engineering options on the form, with the ability to add additional options on supplementary pages using sequential numbering. Each value engineering option must clearly specify the dollar amount of savings it will generate.

The Design-Build project has a maximum budget of $500,000.00 for construction of a single-story, 2,000 square foot rambler residence on the Logan Fish Hatchery property. Contractors submitting cost proposals over the stated budget without accompanying value engineering proposals that bring costs within budget, or those submitting value engineering proposals that fail to achieve budget compliance, may be deemed non-responsive and disqualified from the selection process. The form requires numerical entries for savings amounts, indicated as negative values to reflect cost reductions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DFCM VBS Design-Value Engineering Proposal Form

This Value-Engineering Form is required for Contractors submitting Cost Proposals above the stated budget.

Cost Proposals submitted that are not within the stated budget must be submitted with a Value Engineering Proposal that includes options that will bring the project within the stated budget. Each Value Engineering option provided must include the amount the respective option will reduce the budget.

Contractors submitting Cost Proposals over the stated budget or Value Engineering Proposals that do not bring the cost within the stated budget may be deemed non-responsive and disqualified from this selection.

Enter Value Engineering Option #1 in this box

Value Engineering option #1 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #2 in this box

Value Engineering option #2 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #3 in this box

Value Engineering option #3 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #4 in this box

Value Engineering option #4 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #5 in this box

Value Engineering option #5 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #6 in this box

Value Engineering option #6 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #7 in this box

Value Engineering option #7 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #8 in this box

Value Engineering option #8 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #9 in this box

Value Engineering option #9 Savings $Enter numerical value here. This is a negative value.

Enter Value Engineering Option #10 in this box

Value Engineering option #10 Savings $Enter numerical value here. This is a negative value.

Contractors are not limited to 10 items. Use additional pages if needed and continue numbering in sequential order.