This document contains a risk, responsibility and performance matrix for an energy savings performance contract and information on a related federal contract opportunity with the Department of Veterans Affairs.
The risk, responsibility and performance matrix outlines how various financial, operational and performance risks would be allocated between the contractor and agency under an energy savings performance contract. It addresses issues like interest rates, construction costs, measurement and verification approaches, sources of cost savings, schedule delays, facility changes, operating hours, equipment loads, weather impacts, user participation, equipment performance, operations, preventative maintenance, and equipment repair and replacement.
The related federal contract opportunity is a pre-solicitation notice for an indefinite delivery indefinite quantity energy savings performance contract with the Department of Veterans Affairs. Only service disabled veteran owned small businesses verified through the Vets First Verification Program and on the Department of Energy's qualified energy service company list may respond. The solicitation number is 36E77619R0009 and is expected to be posted on January 15, 2019 via the Federal Business Opportunities website and VA Vendor Portal. Offers must be submitted through the VA Vendor Portal. The NAICS code is 236220 and small business size standard is $36.5 million.
The opportunity involves energy conservation measures at VA facilities with no upfront costs to the agency, where the energy service company guarantees energy savings to pay for the project from reduced utility and maintenance expenses over the term of the multi-year contract.
36E77619R0009 S02 ATTACHMENT J-7 -ESPC Risk, Responsibility, and Performance Matrix.pdf
View the file
Other files for this federal contract opportunity
Show all 50
ESPC IDIQ (VA-19-00001743) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT J-7
ENERGY SAVINGS PERFORMANCE CONTRACT RISK, RESPONSIBILITY AND PERFORMANCE MATRIX
RESPONSIBILITY/DESCRIPTION CONTRACTOR PROPOSED APPROACH
1. Financial
a. Interest rates: Neither the contractor nor the agency has significant control over prevailing interest rates. Higher interest rates will increase project cost, financing/project term, or both. The timing of the Contract signing may impact the available interest rate and project cost.
b. Construction costs: The contractor is responsible for determining construction costs and defining a budget. In a fixed-price design/build contract, the agency assumes little responsibility for cost overruns. However, if construction estimates are significantly greater than originally assumed, the contractor may find that the project or measure is no longer viable and drop it before contract award. In any design/build contract, the agency loses some design control. Clarify design standards and the design approval process (including changes) and how costs will be reviewed.
c. M&V confidence: The agency assumes the responsibility to determine the confidence that it desires to have in the M&V program and energy savings determinations. The desired confidence will be reflected in the resources required for the M&V program, and the ESCO must consider the requirement prior to submittal of the proposal. Clarify how project savings are being verified (e.g., equipment performance, operational factors, energy use) and the impact on M&V costs.
d. Energy Related Cost Savings: The agency and the contractor may agree that the project will include savings from recurring and/or one-time costs. This may include one-time savings from avoided expenditures for projects that were appropriated but will no longer be necessary.
Including one-time cost savings before the money has been appropriated may involve some risk to the agency. Recurring savings generally result from reduced O&M expenses or reduced water consumption. These O&M and water savings must be based on actual spending reductions.
Clarify sources of non-energy cost savings and how they will be verified.
e. Delays: Both the contractor and the agency can cause delays. Failure to implement a viable project in a timely manner costs the agency in the form of lost savings, and can add cost to the project (e.g., construction interest, re-mobilization). Clarify schedule and how delays will be handled.
f. Major changes in facility: The agency (or Congress) controls major changes in facility use, including closure. Clarify responsibilities in the event of a premature facility closure, loss of funding, or other major change.
2. Operational
a. Operating hours: The agency generally has control over operating hours. Increases and decreases in operating hours can show up as increases or decreases in “savings” depending on the M&V method (e.g., operating hours multiplied by improved efficiency of equipment vs. whole-building/utility bill analysis). Clarify whether operating hours are to be measured or stipulated and what the impact will be if they change. If the operating hours are stipulated, the baseline should be carefully documented and agreed to by both parties.
b. Load: Equipment loads can change over time. The agency generally has control over hours of operation, conditioned floor area, intensity of use (e.g., changes in occupancy or level of automation). Changes in load can show up as increases or decreases in “savings” depending on the M&V method. Clarify whether equipment loads are to be measured or stipulated and what the impact will be if they change. If the equipment loads are stipulated, the baseline should be carefully documented and agreed to by both parties.
c. Weather: A number of energy efficiency measures are affected by weather. Neither the contractor nor the agency has control over the weather. Should the agency agree to accept risk for weather fluctuations, it shall be contingent upon aggregate payments not exceeding aggregate savings. Clearly specify how weather corrections will be performed.
d. User participation: Many energy conservation measures require user participation to generate savings (e.g., control settings). The savings can be variable and the contractor may be unwilling to invest in these measures. Clarify what degree of user participation is needed and utilize monitoring and training to mitigate risk. If performance is stipulated, document and review assumptions carefully and consider M&V to confirm the capacity to save (e.g., confirm that the controls are functioning properly).
3. Performance
a. Equipment performance: The contractor has control over the selection of equipment and is responsible for its proper installation, commissioning, and performance. The contractor has responsibility to demonstrate that the new improvements meet expected performance levels including specified equipment capacity, standards of service, and efficiency. Clarify who is responsible for initial and long-term performance, how it will be verified, and what will be done if performance does not meet expectations.
b. Operations: Performance of the day-to-day operations activities is negotiable and can impact performance. However, the contractor bears the ultimate risk regardless of which party performs the activity. Clarify which party will perform equipment operations, the implications of equipment control, how changes in operating procedures will be handled, and how proper operations will be assured.
c. Preventive Maintenance: Performance of day-to-day maintenance activities is negotiable and can impact performance. However, the contractor bears the ultimate risk regardless of which party performs the activity. Clarify how long-term preventive maintenance will be assured, especially if the party responsible for long-term performance is not responsible for maintenance (e.g., contractor provides maintenance checklist and reporting frequency).
Clarify who is responsible for performing long-term preventive maintenance to maintain operational performance throughout the contract term. Clarify what will be done if inadequate preventive maintenance impacts performance.
d. Equipment Repair and Replacement: Performance of day-to-day repair and replacement of contractor-installed equipment is negotiable; however it is often tied to project performance. The contractor bears the ultimate risk regardless of which party performs the activity. Clarify who is responsible for performing replacement of failed components or equipment replacement throughout the term of the contract. Specifically address potential impacts on performance due to equipment failure. Specify expected equipment life and warranties for all installed equipment.
Discuss replacement responsibility when equipment life is shorter than the term of the contract.
NOTE: The column entitled “Contractor Proposed Approach” should be negotiated between the agency and the contractor for the contract and then the word “Proposed” removed from the title.