36E77619B0003-004.pdf
PDF 3 MB Posted
- Solicitation number
- 36E77619B0003
About this file
36E77619B0003 ATTACHMENT 4 - Specifications Volume 3 of 3.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36E77619C0023-000.docx | DOCX document | |
| 36E77619B0003-0003002.pdf | ||
| 36E77619B0003-0003003.pdf | ||
| 36E77619B0003-0003004.pdf | ||
| 36E77619B0003-0003005.pdf | ||
| 36E77619B0003-0003000.docx | DOCX document | |
| 36E77619B0003-0003006.pdf | ||
| 36E77619B0003-0003001.pdf | ||
| 36E77619B0003-0002000.docx | DOCX document | |
| 36E77619B0003-0001001.pdf | ||
| 36E77619B0003-0001000.docx | DOCX document | |
| 36E77619B0003-000.docx | DOCX document | |
| 36E77619B0003-013.docx | DOCX document | |
| 36E77619B0003-005.pdf | ||
| 36E77619B0003-012.pdf | ||
| 36E77619B0003-002.pdf | ||
| 36E77619B0003-006.pdf | ||
| 36E77619B0003-009.pdf | ||
| 36E77619B0003-007.pdf | ||
| 36E77619B0003-011.pdf | ||
| 36E77619B0003-001.pdf | ||
| 36E77619B0003-003.pdf | ||
| 36E77619B0003-010.pdf | ||
| 36E77619B0003-008.pdf | ||
| 36E77619B0003.docx | DOCX document |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCT TWO GREEN HOMES
PROJECT 550-316
DEPARTMENT OF VETERANS AFFAIRS
Construction Documents June 21, 2017
Project Manual 100% Bid Documents
Volume 3
Construct Two Green Homes - Project No. 550-316 00 01 10
Department of Veterans Affairs Table of Contents
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
VOLUME ONE
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 10 Table of Contents 12-04
00 01 15 List of Drawing Sheets 09-11
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-14
01 12 16 Work Schedules 01-11
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 04-13
01 33 23 Shop Drawings, Product Data, and Samples 03-12
01 33 24 Electronic Submittal Procedures 05/16
01 35 26 Safety Requirements 05-16
01 42 19 Reference Standards 09-11
01 45 29 Testing Laboratory Services 07-13
01 57 19 Temporary Environmental Controls 01-11
01 74 19 Construction Waste Management 09-13
01 81 13 Sustainable Design Requirements 09-15
01 91 00 General Commissioning Requirements 06-13
01 92 00 Stormwater Data
Storm Water Management Report
DIVISION 02 – EXISTING CONDITIONS
02 21 00 Site Surveys 05-13
02 41 00 Demolition 05-13
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 10-14
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 09-11
04 05 16 Masonry Grouting 09-11
04 20 00 Unit Masonry 05-12
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-12
05 36 00 Composite Metal Decking 07-11
05 50 00 Metal Fabrications 07-14
05 51 00 Metal Stairs 09-11
00 01 10-2
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 09-11
06 16 63 Cementitious Sheathing 05-12
06 17 53 Shop- Fabricated Wood Trusses 10-15
06 20 00 Finish Carpentry 06-13
06 65 00 Polymer Countertops 12-15
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 Bituminous Damproofing 10-11
07 13 00 Sheet Waterproofing 04-13
07 21 13 Thermal Insulation 06-12
07 24 00 Adhered Masonry Systems 10-11
07 31 13 Asphalt Shingles 05-12
07 46 43 Fiber-Reinforced Cementitious Siding
07 60 00 Flashing and Sheet Metal 07-14
07 84 00 Firestopping 10-11
07 92 00 Joint Sealants 12-11
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-13
08 14 00 Interior Wood Doors 10-12
08 31 13 Access Doors and Frames 10-11
08 36 13 Sectional Doors 10-11
08 52 15 Aluminum Clad Wood Windows 10-15
08 71 00 Door Hardware 11-14
08 71 13 Automatic Door Operators 12-13
08 80 00 Glazing 05-14
08 90 00 Louvers and Vents 10-11
DIVISION 09 – FINISHES
09 06 00 Schedule For Finishes 07-13
09 29 00 Gypsum Board 11-14
09 30 13 Ceramic/Porcelain Tiling 11-14
09 51 00 Acoustical Ceilings 12-13
09 65 13 Resilient Base and Accessories 10-11
09 65 16 Resilient Sheet Flooring 07-13
09 65 19 Resilient Tile Flooring 03-11
09 68 00 Carpeting 10-11
09 72 16 Vinyl-Coated Fabric Wall Covering 10-15
09 91 00 Painting 07-13
DIVISION 10 – SPECIALTIES
10 21 23 Cubicle Curtain Tracks 11-11
10 26 00 Wall and Door Protection 01-11
10 28 00 Toilet, Bath, and Laundry Accessories 11-11
00 01 10-3
10 30 90 Electric Fireplaces 12-15
10 44 13 Fire Extinguisher Cabinets 08-14
DIVISION 11 – EQUIPMENT
11 73 00 Ceiling Mounted Patient Lift System 09-14
11 79 13 Hydrotherapy Equipment 11-11
DIVISION 12 – FURNISHINGS
12 22 16 Drapery Track and Accessories 11-11
12 24 00 Window Shades 11-11
12 32 00 Manufactured Wood Casework 11-11
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
VOLUME TWO
DIVISION 21- FIRE SUPPRESSION
21 05 11 Common Work Results for Fire Suppression 11-09
21 08 00 Commissioning of Fire Suppression System 06-13
21 13 13 Wet-Pipe Sprinkler Systems 05-08
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-14
22 05 23 General-Duty Valves for Plumbing Piping 07-14
22 07 11 Plumbing Insulation 05-11
22 08 00 Commissioning of Plumbing Systems 06-13
22 11 00 Facility Water Distribution 01-14
22 11 23 Domestic Water Pumps 01-14
22 13 00 Facility Sanitary and Vent Piping 07-14
22 13 23 Sanitary Waste Interceptors 07-14
22 31 11 Water Softeners 01-14
22 34 00 Fuel-Fired Domestic Water Heaters 07-14
22 40 00 Plumbing Fixtures 01-14
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 11-10
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
11-10
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
11-10
23 05 93 Testing, Adjusting, and Balancing for HVAC 05-11
23 07 11 HVAC and Boiler Plant Insulation 05-11
23 08 00 Commissioning of HVAC Systems 06-13
23 09 23 Direct-Digital Control System for HVAC 09-11
00 01 10-4
23 11 23 Facility Natural-Gas Piping 05-11
23 23 00 Refrigerant Piping 02-10
23 31 00 HVAC Ducts and Casings 03-13
23 34 00 HVAC Fans 11-09
23 37 00 Air Outlets and Inlets 11-09
23 38 13 Commercial-Kitchen Hoods 01-11
23 40 00 HVAC Air Cleaning Devices 02-12
23 70 00 Variable Refrigerant Flow System 12-15
23 72 00 Air-to-Air Energy Recovery Equipment 05-11
23 73 00 Indoor Central-Station Air-Handling Units 04-11
23 82 00 Convection Heating and Cooling Units 04-11
23 82 16 Air Coils 04-11
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 12-12
26 05 13 Medium-Voltage Cables 12-12
26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-13
26 05 26 Grounding and Bonding for Electrical Systems 12-12
26 05 33 Raceways and Boxes for Electrical Systems 05-14
26 05 41 Underground Electrical Construction 12-12
26 05 73 Overcurrent Protective Device Coordination Study 12-12
26 08 00 Commissioning of Electrical Systems 06-13
26 09 23 Lighting Controls 05-14
26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 12-12
26 24 16 Panelboards 05-14
26 27 26 Wiring Devices 08-14
26 29 11 Motor Controllers 08-14
26 29 21 Enclosed Switches and Circuit Breakers 12-12
26 32 13 Engine Generators 12-12
26 33 53 Static Uninterruptible Power Supply 12-12
26 36 23 Automatic Transfer Switches 12-12
26 41 00 Facility Lightning Protection 12-12
26 43 13 Surge Protective Devices 12-12
26 51 00 Interior Lighting 08-14
26 56 00 Exterior Lighting 05-14
VOLUME THREE
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 05-10
27 05 26 Grounding and Bonding for Communications Systems 05-10
27 05 33 Raceways and Boxes for Communications Systems 05-10
27 08 00 Commissioning of Communications Systems 06-13
27 10 00 Structured Cabling 12-05
27 11 00 Communications Equipment Room Fittings 06-13
27 15 00 Communications Horizontal Cabling 06-13
27 41 31 Master Antenna Television Equipment and Systems 06-13
27 52 23 Nurse Call and Code Blue Systems 06-13
27 52 31 Security Emergency Call, Duress Alarm, and
Telecommunications
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
00 01 10-5
28 05 00 Common Work Results for Electronic Safety and Security 09-11
28 05 13 Conductors and Cables for Electronic Safety and
Security
09-11
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 06-13
28 13 00 Physical Access Control System 10-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection And Alarm 07-13
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 10-12
31 23 19 Dewatering 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 05-13
32 12 16 Asphalt Paving 10-09
32 17 23 Pavement Markings 04-10
32 31 19 Decorative Metal Fences and Gates 11-16
32 90 00 Planting 10-11
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 01-14
33 30 00 Sanitary Sewer Utilities 06-13
33 40 00 Storm Sewer Utilities 10-11
33 51 00 Natural-Gas Distribution 10-11
Construct Two Green Homes - Project 550-316
Department of Veterans Affairs
27 05 11
Requirements For Communications
Installations
270511 - 1
SECTION 27 05 11
REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS
PART 1 – GENERAL
1.1 DESCRIPTION
A. This Section, Requirements for Communications Installations, applies to all sections of Division 27.
B. Furnish and install communications cabling, systems, equipment, and accessories in accordance with the specifications and drawings.
Capacities and ratings of transformers, cable, and other items and arrangements for the specified items are shown on drawings.
1.2 MINIMUM REQUIREMENTS
A. References to industry and trade association standards and codes are minimum installation requirement standards.
B. Drawings and other specification sections shall govern in those instances where requirements are greater than those specified in the above standards.
1.3 QUALIFICATIONS (PRODUCTS AND SERVICES)
A. Manufacturers Qualifications: The manufacturer shall regularly and presently produce, as one of the manufacturer's principal products, the equipment and material specified for this project, and shall have manufactured the item for at least three years.
B. Product Qualification:
1. Manufacturer's product shall have been in satisfactory operation, on three installations of similar size and type as this project, for approximately three years.
2. The Government reserves the right to require the Contractor to submit a list of installations where the products have been in operation before approval.
C. Service Qualifications: There shall be a permanent service organization maintained or trained by the manufacturer which shall render satisfactory service to this installation. The service organization shall respond within four hours of receipt of notification that service is needed and deploy service technicians within a time frame suited to meet the government’s requirement for service. Submit name and address of service organizations.
27 05 11
270511 - 2
1.4 MANUFACTURED PRODUCTS
A. Materials and equipment furnished shall be of current production by manufacturers regularly engaged in the manufacture of such items, for which replacement parts shall be available.
B. When more than one unit of the same class of equipment is required, such units shall be the product of a single manufacturer.
C. Equipment Assemblies and Components:
1. Components of an assembled unit need not be products of the same manufacturer.
2. Manufacturers of equipment assemblies, which include components made by others, shall assume complete responsibility for the final assembled unit.
3. Components shall be compatible with each other and with the total assembly for the intended service.
4. Constituent parts which are similar shall be the product of a single manufacturer.
D. Factory wiring shall be identified on the equipment being furnished and on all wiring diagrams.
E. When Factory Testing Is Specified:
1. The Government shall have the option of witnessing factory tests. The contractor shall notify the VA through the COR a minimum of 15 working calendar days prior to the manufacturers making the factory tests.
2. Four copies of certified test reports containing all test data shall be furnished to the COR prior to final inspection and not more than
90 calendar days after completion of the tests.
3. When equipment fails to meet factory test and re-inspection is required, the contractor shall be liable for all additional expenses, including expenses of the Government.
1.5 EQUIPMENT REQUIREMENTS
Where variations from the contract requirements are requested in accordance with the GENERAL CONDITIONS and Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, AND SAMPLES, the connecting work and related components shall include additions or changes to branch circuits, circuit protective devices, conduits, wire, feeders, controls, panels and installation methods.
27 05 11
270511 - 3
1.6 EQUIPMENT PROTECTION
A. Equipment and materials shall be protected during shipment and storage against physical damage, dirt, moisture, cold and rain:
1. During installation, enclosures, equipment, controls, controllers, circuit protective devices, and other like items, shall be protected against entry of foreign matter; and be vacuum cleaned both inside and outside before testing and operating and repainting if required.
2. Damaged equipment shall be, as determined by the COR, placed in first class operating condition or be returned to the source of supply for repair or replacement.
3. Painted surfaces shall be protected with factory installed removable heavy kraft paper, sheet vinyl or equal.
4. Damaged paint on equipment and materials shall be refinished with the same quality of paint and workmanship as used by the manufacturer so repaired areas are not obvious.
1.7 WORK PERFORMANCE
A. Job site safety and worker safety is the responsibility of the contractor.
B. For work on existing stations, arrange, phase and perform work to assure communications service for other buildings at all times. Refer to
Article OPERATIONS AND STORAGE AREAS under Section 01 00 00, GENERAL
REQUIREMENTS.
C. New work shall be installed and connected to existing work neatly and carefully. Disturbed or damaged work shall be replaced or repaired to its prior conditions, as required by Section 01 00 00, GENERAL
REQUIREMENTS.
D. Coordinate location of equipment and pathways with other trades to minimize interferences. See the GENERAL CONDITIONS.
1.8 EQUIPMENT INSTALLATION AND REQUIREMENTS
A. Equipment location shall be as close as practical to locations shown on the drawings.
B. Inaccessible Equipment:
1. Where the Government determines that the Contractor has installed equipment not conveniently accessible for operation and maintenance, the equipment shall be removed and reinstalled as directed at no additional cost to the Government.
2. "Conveniently accessible" is defined as being capable of being reached without the use of ladders, or without climbing or crawling
27 05 11
270511 - 4 under or over obstacles such as motors, pumps, belt guards, transformers, piping, ductwork, conduit and raceways.
1.9 EQUIPMENT IDENTIFICATION
A. Install an identification sign which clearly indicates information required for use and maintenance of equipment.
B. Nameplates shall be laminated black phenolic resin with a white core with engraved lettering, a minimum of 6 mm (1/4 inch) high. Secure nameplates with screws. Nameplates that are furnished by manufacturer as a standard catalog item, or where other method of identification is herein specified, are exceptions.
1.10 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. The Government's approval shall be obtained for all equipment and material before delivery to the job site. Delivery, storage, or installation of equipment or material which has not had prior approval shall not be permitted at the job site.
C. All submittals shall include adequate descriptive literature, catalog cuts, shop drawings, and other data necessary for the Government to ascertain that the proposed equipment and materials comply with specification requirements. Catalog cuts submitted for approval shall be legible and clearly identify equipment being submitted.
D. Submittals for individual systems and equipment assemblies which consist of more than one item or component shall be made for the system or assembly as a whole. Partial submittals shall not be considered for approval.
1. Mark the submittals, "SUBMITTED UNDER SECTION__________________".
2. Submittals shall be marked to show specification reference including the section and paragraph numbers.
3. Submit each section separately.
E. The submittals shall include the following:
1. Information that confirms compliance with contract requirements.
Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, pictures, nameplate data and test reports as required.
2. Elementary and interconnection wiring diagrams for communication and signal systems, control system and equipment assemblies. All terminal points and wiring shall be identified on wiring diagrams.
27 05 11
270511 - 5
3. Parts list which shall include those replacement parts recommended by the equipment manufacturer, quantity of parts, current price and availability of each part.
F. Manuals: Submit in accordance with Section 01 00 00, GENERAL
REQUIREMENTS.
1. Maintenance and Operation Manuals: Submit as required for systems and equipment specified in the technical sections. Furnish four copies, bound in hardback binders, (manufacturer's standard binders) or an approved equivalent. Furnish one complete manual as specified in the technical section but in no case later than prior to performance of systems or equipment test, and furnish the remaining manuals prior to contract completion.
2. Inscribe the following identification on the cover: the words
"MAINTENANCE AND OPERATION MANUAL," the name and location of the system, equipment, building, name of Contractor, and contract number.
Include in the manual the names, addresses, and telephone numbers of each subcontractor installing the system or equipment and the local representatives for the system or equipment.
3. Provide a "Table of Contents" and assemble the manual to conform to the table of contents, with tab sheets placed before instructions covering the subject. The instructions shall be legible and easily read, with large sheets of drawings folded in.
4. The manuals shall include:
a. Internal and interconnecting wiring and control diagrams with data to explain detailed operation and control of the equipment.
b. A control sequence describing start-up, operation, and shutdown.
c. Description of the function of each principal item of equipment.
d. Installation and maintenance instructions.
e. Safety precautions.
f. Diagrams and illustrations.
g. Testing methods.
h. Performance data.
i. Pictorial "exploded" parts list with part numbers. Emphasis shall be placed on the use of special tools and instruments. The list shall indicate sources of supply, recommended spare parts, and name of servicing organization.
27 05 11
270511 - 6
j. Appendix; list qualified permanent servicing organizations for support of the equipment, including addresses and certified qualifications.
G. Approvals shall be based on complete submission of manuals together with shop drawings.
H. After approval and prior to installation, furnish the COR with one sample of each of the following:
1. A 300 mm (12 inch) length of each type and size of wire and cable along with the tag from the coils of reels from which the samples were taken.
2. Each type of conduit and pathway coupling, bushing and termination fitting.
3. Raceway and pathway hangers, clamps and supports.
4. Duct sealing compound.
I. In addition to the requirement of SUBMITTALS, the VA reserves the right to request the manufacturer to arrange for a VA representative to see typical active systems in operation, when there has been no prior experience with the manufacturer or the type of equipment being submitted.
1.11 SINGULAR NUMBER
A. Where any device or part of equipment is referred to in these specifications in the singular number (e.g., "the switch"), this reference shall be deemed to apply to as many such devices as are required to complete the installation as shown on the drawings.
1.12 TRAINING
A. Training shall be provided in accordance with Article, INSTRUCTIONS, of
Section 01 00 00, GENERAL REQUIREMENTS.
B. Training shall be provided for the particular equipment or system as required in each associated specification.
C. A training schedule shall be developed and submitted by the contractor and approved by the COR at least 30 calendar days prior to the planned training.
- - - E N D - - -
27 05 26
Grounding And Bonding For
Communications Systems
270526 - 1
SECTION 27 05 26
GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies general grounding and bonding requirements of telecommunication installations for equipment operations.
B. “Grounding electrode system” refers to all electrodes required by NEC, as well as including made, supplementary, telecommunications system grounding electrodes.
C. The terms “connect” and “bond” are used interchangeably in this specification and have the same meaning.
1.2 RELATED WORK
A. Section 27 05 11, REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS:
General electrical requirements and items that are common to more than one section of Division 27.
B. Section 27 10 00, STRUCTURED CABLING: Low Voltage power and lighting wiring.
C. Section 26 41 00, FACILITY LIGHTNING PROTECTION: Requirements for a lightning protection system.
1.3 SUBMITTALS
A. Submit in accordance with Section 27 05 11, REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS.
B. Shop Drawings:
1. Sufficient information, clearly presented, shall be included to determine compliance with drawings and specifications.
2. Include the location of system grounding electrode connections and the routing of aboveground and underground grounding electrode conductors.
C. Test Reports: Provide certified test reports of ground resistance.
D. Certifications: Two weeks prior to final inspection, submit four copies of the following to the COR:
1. Certification that the materials and installation is in accordance with the drawings and specifications.
2. Certification, by the Contractor, that the complete installation has been properly installed and tested.
27 05 26
270526 - 2
1.4 APPLICABLE PUBLICATIONS
Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only.
A. American Society for Testing and Materials (ASTM):
B1-2001.................Standard Specification for Hard-Drawn Copper
Wire
B8-2004.................Standard Specification for Concentric-Lay-
Stranded Copper Conductors, Hard, Medium-Hard, or Soft
B. Institute of Electrical and Electronics Engineers, Inc. (IEEE):
81-1983.................IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System
C. National Fire Protection Association (NFPA):
70-2005.................National Electrical Code (NEC)
D. Telecommunications Industry Association, (TIA)
J-STO-607-A-2002........Commercial Building Grounding (Earthing) and
Bonding Requirements for Telecommunications
E. Underwriters Laboratories, Inc. (UL):
44-2005 ................Thermoset-Insulated Wires and Cables
83-2003 ................Thermoplastic-Insulated Wires and Cables
467-2004 ...............Grounding and Bonding Equipment
486A-486B-2003 .........Wire Connectors
PART 2 - PRODUCTS
2.1 GROUNDING AND BONDING CONDUCTORS
A. Equipment grounding conductors shall be UL 83 insulated stranded copper, except that sizes 6 mm² (10 AWG) and smaller shall be solid copper. Insulation color shall be continuous green for all equipment grounding conductors, except that wire sizes 25 mm² (4 AWG) and larger shall be permitted to be identified per NEC.
B. Bonding conductors shall be ASTM B8 bare stranded copper, except that sizes 6 mm² (10 AWG) and smaller shall be ASTM B1 solid bare copper wire.
C. Isolated Power System: Type XHHW-2 insulation with a dielectric constant of 3.5 or less.
27 05 26
270526 - 3
D. Telecom System Grounding Riser Conductor: Telecommunications Grounding
Riser shall be in accordance with J STO-607A. Use a minimum 50mm² (1/0
AWG) insulated stranded copper grounding conductor unless indicated otherwise.
2.2 GROUND RODS
A. Copper clad steel, 19 mm (3/4-inch) diameter by 3000 mm (10 feet) long, conforming to UL 467.
B. Quantity of rods shall be as required to obtain the specified ground resistance.
2.3 SPLICES AND TERMINATION COMPONENTS
Components shall meet or exceed UL 467 and be clearly marked with the manufacturer, catalog number, and permitted conductor size(s).
2.4 TELECOMMUNICATION SYSTEM GROUND BUSBARS
A. Provide solid copper busbar, pre-drilled from two-hole lug connections with a minimum thickness of 6 mm (1/4 inch) for wall and backboard mounting using standard insulators sized as follows:
1. Room Signal Grounding: 300 mm x 100 mm (12 inches x 4 inch).
2. Master Signal Ground: 600 mm x 100 mm (24 inches x 4 inch).
2.5 GROUND CONNECTIONS
A. Below Grade: Exothermic-welded type connectors.
B. Above Grade:
1. Bonding Jumpers: compression type connectors, using zinc-plated fasteners and external tooth lockwashers.
2. Ground Busbars: Two-hole compression type lugs using tin-plated copper or copper alloy bolts and nuts.
3. Rack and Cabinet Ground Bars: one-hole compression-type lugs using zinc-plated or copper alloy fasteners.
C. Cable Shields: Make ground connections to multipair communications cables with metallic shields using shield bonding connectors with screw stud connection.
2.6 EQUIPMENT RACK AND CABINET GROUND BARS
Provide solid copper ground bars designed for mounting on the framework of open or cabinet-enclosed equipment racks with minimum dimensions of
4 mm thick by 19 mm wide (3/8 inch x ¾ inch).
27 05 26
270526 - 4
2.7 GROUND TERMINAL BLOCKS
At any equipment mounting location (e.g. backboards and hinged cover enclosures) where rack-type ground bars cannot be mounted, provide screw lug-type terminal blocks.
2.8 SPLICE CASE GROUND ACCESSORIES
Splice case grounding and bonding accessories shall be supplied by the splice case manufacturer when available. Otherwise, use 16 mm² (6 AWG) insulated ground wire with shield bonding connectors.
PART 3 - EXECUTION
3.1 GENERAL
A. Ground in accordance with the NEC, as shown on drawings, and as hereinafter specified.
B. System Grounding:
1. Secondary service neutrals: Ground at the supply side of the secondary disconnecting means and at the related transformers.
2. Separately derived systems (transformers downstream from the service entrance): Ground the secondary neutral.
3. Isolation transformers and isolated power systems shall not be system grounded.
C. Equipment Grounding: Metallic structures (including ductwork and building steel), enclosures, raceways, junction boxes, outlet boxes, cabinets, machine frames, and other conductive items in close proximity with electrical circuits shall be bonded and grounded.
3.2 INACCESSIBLE GROUNDING CONNECTIONS
Make grounding connections, which are buried or otherwise normally inaccessible (except connections for which periodic testing access is required) by exothermic weld.
3.3 SECONDARY EQUIPMENT AND CIRCUITS
A. Main Bonding Jumper: Bond the secondary service neutral to the ground bus in the service equipment.
B. Metallic Piping, Building Steel, and Supplemental Electrode(s):
1. Provide a grounding electrode conductor sized per NEC between the service equipment ground bus and all metallic water and gas pipe systems, building steel, and supplemental or made electrodes. Jumper insulating joints in the metallic piping. All connections to electrodes shall be made with fittings that conform to UL 467.
27 05 26
270526 - 5
2. Provide a supplemental ground electrode and bond to the grounding electrode system.
C. Conduit Systems:
1. Ground all metallic conduit systems. All metallic conduit systems shall contain an equipment grounding conductor.
2. Non-metallic conduit systems shall contain an equipment grounding conductor, except that non-metallic feeder conduits which carry a grounded conductor from exterior transformers to interior or building-mounted service entrance equipment need not contain an equipment grounding conductor.
3. Conduit containing only a grounding conductor, and which is provided for mechanical protection of the conductor, shall be bonded to that conductor at the entrance and exit from the conduit.
D. Feeders and Branch Circuits: Install equipment grounding conductors with all feeders and power and lighting branch circuits.
E. Boxes, Cabinets, Enclosures, and Panelboards:
1. Bond the equipment grounding conductor to each pullbox, junction box, outlet box, device box, cabinets, and other enclosures through which the conductor passes (except for special grounding systems for intensive care units and other critical units shown).
2. Provide lugs in each box and enclosure for equipment grounding conductor termination.
3. Provide ground bars in panelboards, bolted to the housing, with sufficient lugs to terminate the equipment grounding conductors.
F. Receptacles shall not be grounded through their mounting screws. Ground with a jumper from the receptacle green ground terminal to the device box ground screw and the branch circuit equipment grounding conductor.
G. Raised Floors: Provide bonding of all raised floor components.
3.4 CORROSION INHIBITORS
When making ground and ground bonding connections, apply a corrosion inhibitor to all contact surfaces. Use corrosion inhibitor appropriate for protecting a connection between the metals used.
3.5 CONDUCTIVE PIPING
A. Bond all conductive piping systems, interior and exterior, to the building to the grounding electrode system. Bonding connections shall be made as close as practical to the equipment ground bus.
27 05 26
270526 - 6
B. In operating rooms and at intensive care and coronary care type beds, bond the gases and suction piping, at the outlets, directly to the room or patient ground bus.
3.6 TELECOMMUNICATIONS SYSTEM
A. Bond telecommunications system grounding equipment to the electrical grounding electrode system.
B. Furnish and install all wire and hardware required to properly ground, bond and connect communications raceway, cable tray, metallic cable shields, and equipment to a ground source.
C. Ground bonding jumpers shall be continuous with no splices. Use the shortest length of bonding jumper possible.
D. Provide ground paths that are permanent and continuous with a resistance of 1 ohm or less from raceway, cable tray, and equipment connections to the building grounding electrode. The resistance across individual bonding connections shall be 10 milli ohms or less.
E. Below-Grade Grounding Connections: When making exothermic welds, wire brush or file the point of contact to a bare metal surface. Use exothermic welding cartridges and molds in accordance with the manufacturer’s recommendations. After welds have been made and cooled, brush slag from the weld area and thoroughly cleaned the joint area.
Notify the COR prior to backfilling any ground connections.
F. Above-Grade Grounding Connections: When making bolted or screwed connections to attach bonding jumpers, remove paint to expose the entire contact surface by grinding where necessary; thoroughly clean all connector, plate and other contact surfaces; and apply an appropriate corrosion inhibitor to all surfaces before joining.
G. Bonding Jumpers:
1. Use insulated ground wire of the size and type shown on the
Drawings or use a minimum of 16 mm² (6 AWG) insulated copper wire.
2. Assemble bonding jumpers using insulated ground wire terminated with compression connectors.
3. Use compression connectors of proper size for conductors specified. Use connector manufacturer’s compression tool.
H. Bonding Jumper Fasteners:
1. Conduit: Fasten bonding jumpers using screw lugs on grounding bushings or conduit strut clamps, or the clamp pads on push-type
27 05 26
270526 - 7 conduit fasteners. When screw lug connection to a conduit strut clamp is not possible, fasten the plain end of a bonding jumper wire by slipping the plain end under the conduit strut clamp pad; tighten the clamp screw firmly. Where appropriate, use zinc-plated external tooth lockwashers.
2. Wireway and Cable Tray: Fasten bonding jumpers using zinc-plated bolts, external tooth lockwashers, and nuts. Install protective cover, e.g., zinc-plated acorn nuts on any bolts extending into wireway or cable tray to prevent cable damage.
3. Ground Plates and Busbars: Fasten bonding jumpers using two-hole compression lugs. Use tin-plated copper or copper alloy bolts, external tooth lockwashers, and nuts.
4. Unistrut and Raised Floor Stringers: Fasten bonding jumpers using zinc-plated, self-drill screws and external tooth lockwashers.
3.7 COMMUNICATION ROOM GROUNDING
A. Telecommunications Ground Busbars:
1. Provide communications room telecommunications ground busbar hardware at 950 mm (18 inches) at locations indicated on the
Drawings.
2. Connect the telecommunications room ground busbars to other room grounding busbars as indicated on the Grounding Riser diagram.
B. Telephone-Type Cable Rack Systems: aluminum pan installed on telephone-type cable rack serves as the primary ground conductor within the communications room. Make ground connections by installing the following bonding jumpers:
1. Install a 16 mm² (6 AWG) bonding between the telecommunications ground busbar and the nearest access to the aluminum pan installed on the cable rack.
2. Use 16 mm² (6 AWG) bonding jumpers across aluminum pan junctions.
C. Self-Supporting and Cabinet-Mounted Equipment Rack Ground Bars:
1. When ground bars are provided at the rear of lineup of bolted together equipment racks, bond the copper ground bars together using solid copper splice plates supplied by the ground bar manufacturer.
2. Bond together nonadjacent ground bars on equipment racks and cabinets with 16 mm² (6 AWG) insulated copper wire bonding jumpers attached at each end with compression-type connectors and mounting bolts.
27 05 26
270526 - 8
3. Provide a 16 mm² (6 AWG) bonding jumper between the rack and/or cabinet ground busbar and the aluminum pan of an overhead cable tray or the raised floor stringer as appropriate.
D. Backboards: Provide a screw lug-type terminal block or drilled and tapped copper strip near the top of backboards used for communications cross-connect systems. Connect backboard ground terminals to the aluminum pan in the telephone-type cable tray using an insulated 16 mm²
(16 AWG) bonding jumper.
E. Other Communication Room Ground Systems: Ground all metallic conduit, wireways, and other metallic equipment located away from equipment racks or cabinets to the cable tray pan or the telecommunications ground busbar, whichever is closer, using insulated 16 mm² (6 AWG) ground wire bonding jumpers.
3.8 COMMUNICATIONS CABLE GROUNDING
A. Bond all metallic cable sheaths in multipair communications cables together at each splicing and/or terminating location to provide 100 percent metallic sheath continuity throughout the communications distribution system.
1. At terminal points, install a cable shield bonding connector provide a screw stud connection for ground wire. Use a bonding jumper to connect the cable shield connector to an appropriate ground source like the rack or cabinet ground bar.
2. Bond all metallic cable shields together within splice closures using cable shield bonding connectors or the splice case grounding and bonding accessories provided by the splice case manufacturer.
When an external ground connection is provided as part of splice closure, connect to an approved ground source and all other metallic components and equipment at that location.
3.9 COMMUNICATIONS CABLE TRAY SYSTEMS:
A. Bond the metallic structures of one cable tray in each tray run following the same path to provide 100 percent electrical continuity throughout this cable tray systems as follows:
1. Splice plates provided by the cable tray manufacturer can be used for providing a ground bonding connection between cable tray sections when the resistance across a bolted connection is 10 milliohms or less. The Subcontractor shall verify this loss by
27 05 26
270526 - 9 testing across one slice plate connection in the presence of the
Contractor.
2. Install a 16 mm² (6 AWG) bonding jumper across each cable tray splice or junction where splice plates cannot be used.
3. When cable tray terminations to cable rack, install 16 mm² (6 AWG) bonding jumper between cable tray and cable rank pan.
3.10 COMMUNCIATIONS RACEWAY GROUNDING
A. Conduit: Use insulated 16 mm² (6 AWG) bonding jumpers to ground metallic conduit at each end and to bond at all intermediate metallic enclosures.
B. Wireway: use insulated 16 mm² (6 AWG) bonding jumpers to ground or bond metallic wireway at each end at all intermediate metallic enclosures and across all section junctions.
C. Cable Tray Systems: Use insulated 16 mm² (6 AWG) bonding jumpers to ground cable tray to column-mounted building ground plates (pads) at each end and approximately every 16 meters (50 feet).
3.11 GROUND RESISTANCE
A. Grounding system resistance to ground shall not exceed 5 ohms. Make necessary modifications or additions to the grounding electrode system for compliance without additional cost to the Government. Final tests shall assure that this requirement is met.
B. Resistance of the grounding electrode system shall be measured using a four-terminal fall-of-potential method as defined in IEEE 81. Ground resistance measurements shall be made before the electrical distribution system is energized and shall be made in normally dry conditions not less than 48 hours after the last rainfall. Resistance measurements of separate grounding electrode systems shall be made before the systems are bonded together below grade. The combined resistance of separate systems shall be used to meet the required resistance, but the specified number of electrodes shall still be provided.
C. Services at power company interface points shall comply with the power company ground resistance requirements.
D. Below-grade connections shall be visually inspected by the COR prior to backfilling. The Contractor shall notify the COR 24 hours before the connections are ready for inspection.
27 05 26
270526 - 10
3.12 GROUND ROD INSTALLATION
A. Drive each rod vertically in the earth, not less than 3000 mm (10 feet) in depth.
B. Where permanently concealed ground connections are required, make the connections by the exothermic process to form solid metal joints. Make accessible ground connections with mechanical pressure type ground connectors.
C. Where rock prevents the driving of vertical ground rods, install angled ground rods or grounding electrodes in horizontal trenches to achieve the specified resistance.
27 05 33
Raceways And Boxes For
270533 - 1
SECTION 27 05 33
RACEWAYS AND BOXES FOR COMMUNICATIONS SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation, and connection of conduit, fittings, and boxes to form complete, coordinated, raceway systems. Raceways are required for all communications cabling unless shown or specified otherwise.
B. Definitions: The term conduit, as used in this specification, shall mean any or all of the raceway types specified.
1.2 RELATED WORK
A. Bedding of conduits: Section 31 20 00, EARTH MOVING.
B. Mounting board for communication closets: Section 06 10 00, ROUGH
CARPENTRY.
C. Sealing around penetrations to maintain the integrity of fire rated construction: Section 07 84 00, FIRESTOPPING.
D. Fabrications for the deflection of water away from the building envelope at penetrations: Section 07 60 00, FLASHING AND SHEET METAL.
E. Sealing around conduit penetrations through the building envelope to prevent moisture migration into the building: Section 07 92 00, JOINT
SEALANTS.
F. Identification and painting of conduit and other devices: Section 09 91
00, PAINTING.
G. General electrical requirements and items that is common to more than one section of Division 27: Section 27 05 11, REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS.
H. Requirements for personnel safety and to provide a low impedance path for possible ground fault currents: Section 27 05 26, GROUNDING AND
BONDING FOR COMMUNICATIONS SYSTEMS.
1.3 SUBMITTALS
In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES, furnish the following:
A. Shop Drawings:
1. Size and location of panels and pull boxes
2. Layout of required conduit penetrations through structural elements.
3. The specific item proposed and its area of application shall be identified on the catalog cuts.
27 05 33
270533 - 2
B. Certification: Prior to final inspection, deliver to the COR four copies of the certification that the material is in accordance with the drawings and specifications and has been properly installed.
1.4 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, addenda, revisions, supplements and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only.
B. National Fire Protection Association (NFPA):
70-05...................National Electrical Code (NEC)
C. Underwriters Laboratories, Inc. (UL):
1-03....................Flexible Metal Conduit
5-01....................Surface Metal Raceway and Fittings
6-03....................Rigid Metal Conduit
50-03...................Enclosures for Electrical Equipment
360-03..................Liquid-Tight Flexible Steel Conduit
467-01..................Grounding and Bonding Equipment
514A-01.................Metallic Outlet Boxes
514B-02.................Fittings for Cable and Conduit
514C-05.................Nonmetallic Outlet Boxes, Flush-Device Boxes and
Covers
651-02..................Schedule 40 and 80 Rigid PVC Conduit
651A-03.................Type EB and A Rigid PVC Conduit and HDPE Conduit
797-03..................Electrical Metallic Tubing
1242-00.................Intermediate Metal Conduit
D. National Electrical Manufacturers Association (NEMA):
TC-3-04.................PVC Fittings for Use with Rigid PVC Conduit and
Tubing
FB1-03..................Fittings, Cast Metal Boxes and Conduit Bodies for Conduit, Electrical Metallic Tubing and
Cable
PART 2 - PRODUCTS
2.1 MATERIAL
A. Conduit Size: In accordance with the NEC, but not less than 13 mm
(1/2 inch) unless otherwise shown. Where permitted by the NEC, 13 mm
(1/2 inch) flexible conduit shall be used for tap connections to recessed lighting fixtures.
B. Conduit:
1. Rigid galvanized steel: Shall Conform to UL 6, ANSI C80.1.
27 05 33
270533 - 3
2. Rigid aluminum: Shall Conform to UL 6A, ANSI C80.5.
3. Rigid intermediate steel conduit (IMC): Shall Conform to UL 1242, ANSI C80.6.
4. Electrical metallic tubing (EMT): Shall Conform to UL 797, ANSI
C80.3. Maximum size not to exceed 105 mm (4 inch) and shall be permitted only with cable rated 600 volts or less.
5. Flexible galvanized steel conduit: Shall Conform to UL 1.
6. Liquid-tight flexible metal conduit: Shall Conform to UL 360.
7. Direct burial plastic conduit: Shall conform to UL 651 and UL 651A, heavy wall PVC or high density polyethylene (PE).
8. Surface metal raceway: Shall Conform to UL 5.
C. Conduit Fittings:
1. Rigid steel and IMC conduit fittings:
a. Fittings shall meet the requirements of UL 514B and ANSI/ NEMA
FB1.
b. Standard threaded couplings, locknuts, bushings, and elbows: Only steel or malleable iron materials are acceptable. Integral retractable type IMC couplings are also acceptable.
c. Locknuts: Bonding type with sharp edges for digging into the metal wall of an enclosure.
d. Bushings: Metallic insulating type, consisting of an insulating insert molded or locked into the metallic body of the fitting.
Bushings made entirely of metal or nonmetallic material are not permitted.
e. Erickson (union-type) and set screw type couplings: Approved for use in concrete are permitted for use to complete a conduit run where conduit is installed in concrete. Use set screws of case hardened steel with hex head and cup point to firmly seat in conduit wall for positive ground. Tightening of set screws with pliers is prohibited.
f. Sealing fittings: Threaded cast iron type. Use continuous drain type sealing fittings to prevent passage of water vapor. In concealed work, install fittings in flush steel boxes with blank cover plates having the same finishes as that of other electrical plates in the room.
2. Rigid aluminum conduit fittings:
a. Standard threaded couplings, locknuts, bushings, and elbows:
Malleable iron, steel or aluminum alloy materials; Zinc or cadmium
27 05 33
270533 - 4 plate iron or steel fittings. Aluminum fittings containing more than 0.4 percent copper are prohibited.
b. Locknuts and bushings: As specified for rigid steel and IMC conduit.
c. Set screw fittings: Not permitted for use with aluminum conduit.
3. Electrical metallic tubing fittings:
a. Fittings shall meet the requirements of UL 514B and ANSI/ NEMA
FB1.
b. Only steel or malleable iron materials are acceptable.
c. Couplings and connectors: Concrete tight and rain tight, with connectors having insulated throats. Use gland and ring compression type couplings and connectors for conduit sizes 50 mm
(2 inches) and smaller. Use set screw type couplings with four set screws each for conduit sizes over 50 mm (2 inches). Use set screws of case-hardened steel with hex head and cup point to firmly seat in wall of conduit for positive grounding.
d. Indent type connectors or couplings are prohibited.
e. Die-cast or pressure-cast zinc-alloy fittings or fittings made of
"pot metal" are prohibited.
4. Flexible steel conduit fittings:
a. Conform to UL 514B. Only steel or malleable iron materials are acceptable.
b. Clamp type, with insulated throat.
5. Liquid-tight flexible metal conduit fittings:
a. Fittings shall meet the requirements of UL 514B and ANSI/ NEMA
FB1.
b. Only steel or malleable iron materials are acceptable.
c. Fittings shall incorporate a threaded grounding cone, a steel or plastic compression ring, and a gland for tightening. Connectors shall have insulated throats.
6. Direct burial plastic conduit fittings:
a. Fittings shall meet the requirements of UL 514C and NEMA TC3.
b. As recommended by the conduit manufacturer.
7. Surface metal raceway fittings: As recommended by the raceway manufacturer.
8. Expansion and deflection couplings:
a. Conform to UL 467 and UL 514B.
27 05 33
270533 - 5
b. Accommodate, 19 mm (0.75 inch) deflection, expansion, or contraction in any direction, and allow 30 degree angular deflections.
c. Include internal flexible metal braid sized to guarantee conduit ground continuity and fault currents in accordance with UL 467, and the NEC code tables for ground conductors.
d. Jacket: Flexible, corrosion-resistant, watertight, moisture and heat resistant molded rubber material with stainless steel jacket clamps.
D. Conduit Supports:
1. Parts and hardware: Zinc-coat or provide equivalent corrosion protection.
2. Individual Conduit Hangers: Designed for the purpose, having a pre-assembled closure bolt and nut, and provisions for receiving a hanger rod.
3. Multiple conduit (trapeze) hangers: Not less than 38 mm by 38 mm
(1-1/2 by 1-1/2 inch), 12 gage steel, cold formed, lipped channels;
with not less than 9 mm (3/8 inch) diameter steel hanger rods.
4. Solid Masonry and Concrete Anchors: Self-drilling expansion shields, or machine bolt expansion.
E. Outlet, Junction, and Pull Boxes:
1. UL-50 and UL-514A.
2. Cast metal where required by the NEC or shown, and equipped with rustproof boxes.
3. Sheet metal boxes: Galvanized steel, except where otherwise shown.
4. Flush mounted wall or ceiling boxes shall be installed with raised covers so that front face of raised cover is flush with the wall.
Surface mounted wall or ceiling boxes shall be installed with surface style flat or raised covers.
F. Wireways: Equip with hinged covers, except where removable covers are shown.
G. Warning Tape: Standard, 4-Mil polyethylene 76 mm (3 inch) wide tape detectable type, red with black letters, and imprinted with “CAUTION
BURIED COMMUNICATIONS CABLE BELOW”.
PART 3 - EXECUTION
3.1 PENETRATIONS
A. Cutting or Holes:
27 05 33
270533 - 6
1. Locate holes in advance where they are proposed in the structural sections such as ribs or beams. Obtain the approval of the COR prior to drilling through structural sections.
2. Cut holes through concrete and masonry in new and existing structures with a diamond core drill or concrete saw. Pneumatic hammer, impact electric, hand or manual hammer type drills are not allowed, except where permitted by the COR as required by limited working space.
B. Fire Stop: Where conduits, wireways, and other communications raceways pass through fire partitions, fire walls, smoke partitions, or floors, install a fire stop that provides an effective barrier against the spread of fire, smoke and gases as specified in Section 07 84 00, FIRESTOPPING, with rock wool fiber or silicone foam sealant only.
Completely fill and seal clearances between raceways and openings with the fire stop material.
C. Waterproofing: At floor, exterior wall, and roof conduit penetrations, completely seal clearances around the conduit and make watertight as specified in Section 07 92 00, JOINT SEALANTS.
3.2 INSTALLATION, GENERAL
A. Install conduit as follows:
1. In complete runs before pulling in cables or wires.
2. Flattened, dented, or deformed conduit is not permitted. Remove and replace the damaged conduits with new undamaged material.
3. Assure conduit installation does not encroach into the ceiling height head room, walkways, or doorways.
4. Cut square with a hacksaw, ream, remove burrs, and draw up tight.
5. Mechanically continuous.
6. Independently support conduit at 8’0” on center. Do not use other supports i.e., (suspended ceilings, suspended ceiling supporting members, lighting fixtures, conduits, mechanical piping, or mechanical ducts).
7. Support within 300 mm (1 foot) of changes of direction, and within
300 mm (1 foot) of each enclosure to which connected.
8. Close ends of empty conduit with plugs or caps at the rough-in stage to prevent entry of debris, until wires are pulled in.
9. Conduit installations under fume and vent hoods are prohibited.
10. Secure conduits to cabinets, junction boxes, pull boxes and outlet boxes with bonding type locknuts. For rigid and IMC conduit installations, provide a locknut on the inside of the enclosure, made
27 05 33
270533 - 7 up wrench tight. Do not make conduit connections to junction box covers.
11. Flashing of penetrations of the roof membrane is specified in Section
07 60 00, FLASHING AND SHEET METAL.
12. Do not use aluminum conduits in wet locations.
13. Unless otherwise indicated on the drawings or specified herein, all conduits shall be installed concealed within finished walls, floors and ceilings.
B. Conduit Bends:
1. Make bends with standard conduit bending machines.
2. Conduit hickey shall be used for slight offsets, and for straightening stubbed out conduits.
3. Bending of conduits with a pipe tee or vise is prohibited.
C. Layout and Homeruns:
1. Deviations: Make only where necessary to avoid interferences and only after drawings showing the proposed deviations have been submitted approved by the COR.
3.3 CONCEALED WORK INSTALLATION
A. In Concrete:
1. Conduit: Rigid steel, IMC or EMT. Do not install EMT in concrete slabs that are in…