This document is a solicitation for construction services for a building upgrade project at a Veterans Affairs medical center. The Department of Veterans Affairs is seeking a general contractor to provide all labor, equipment, materials, and expertise to upgrade a warehouse building. Key project details include removing and replacing an existing roll-up door and man door with larger units, installing new electrical and HVAC components, repairing concrete, and painting floors. The response due date is November 17, 2023. The contract is set aside for a certified Service-Disabled Veteran-Owned Small Business and has an anticipated value between $100,000 and $250,000. The selected contractor must complete all work within 60 calendar days of the notice to proceed.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25924R0016

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5.

REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL

SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25924R0016 X 10-26-2023 436-23-123 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Robyn Young robyn.young2@va.gov The contractor shall furnish all labor, equipment, materials, and supervision to for project 436-23-123 Building 170 Warehouse Upgrades at the Fort Harrison VA Medical Center, 3687 Veterans Drive, Fort Harrison, Montana 59636.

Project magnitude: between $100,000 and $250,000. The NAICS code is 236220 - Small Bus iness size standard is $45 M.

All Questions in relation to this solicitation must be submitted in writing via e-mail to Robyn.Young2@va.gov and received no later than 11/06/2023 at 2:00 PM. Mountain Time (MT).

A site visit will be held on at 11/02/2023 at 1:00 PM (MT) Please meet at the Administrative Building 141, second floor, Engineering Conference Room 208, Fort Harrison VAMC. Leading the site visit will be held by Joseph Bilodeau.

Proposals Shall be submitted via e-mail in accordance with Part I / Section B, to be considered for this project.

P roposals received in any other format will result in the offeror's proposal not receiving further consideration.

In accordance with P.L. 116-283, this acquisition is 100% set-aside for Serv ice-Disabled Veteran Owned Small Business Concerns. See VAAR 852.219-73, VA Notice of Total Set-Aside for Verified Service-Disabled Veteran-Owned Small Business For information in regards to requirements in order to be considered. Offerors must be bo th VISIBLE and VERIFIED by The Small Business Administration (SBA) prior to proposal receipt. Failure to be both VERIFIED, and VISIBLE by the SBA Prior to contract award will result in the offerors proposal being deemed non-compliant. ALL offerors are urged to Contact the SBA and submit the aforementioned required documents to obtain SBA (VetCert) verification of their SDVOSB Status if they have not already done so.

Instructions, Conditions, and Notices to offerors. All submitted quotes must be received in email by the closing date and time. This solicitation closes November 17, 2023 at 2:00PM Mountain Time (MT).

x 52.211-10 X 14:00

MST

11-17-2023 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMEN

DMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND

TITLE OF CONTRACTOR OR PERSON AUTHORIZED

31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or pr int) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE10
ITEM INFORMATION10
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS10
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS15
2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)15
2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)15
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)16
2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)17
2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)18
REPRESENTATIONS AND CERTIFICATIONS19
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)19
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)23
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)25
GENERAL CONDITIONS28
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)28
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)29
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2023)29
4.4 52.223-21 FOAMS (JUN 2016)32
4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)33
4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)38
4.7 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)40
4.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)40
4.9 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023)40
4.10 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)49
4.11 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)52
4.12 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)54
4.13 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)57
4.14 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)60
4.15 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)61
4.16 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)62
4.17 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)63
4.18 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)63
4.19 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)64
Attachments73

Rocky Mountain Network 19 | Montana VA Health Care System (436) 3687 Veterans Drive | P.O. Box 1500 Fort Harrison, MT 59636-1500

1.877.468.8387 | 406.442.6410

Scope of Work

Project: 436-23-123 Project Name: Building 170 Warehouse Upgrades Project Scope

The VA Montana Healthcare System requires the services of a qualified General Contracting firm to provide construction services at the Fort Harrison Campus of the Montana VA Health Care System, located at 3687 Veterans Drive, Fort Harrison, MT 59636.Comment by Moeller, Benjamin D. (Bacik Group, LLC): At Bldg 170,
The Contractor shall perform all work and provide all services, materials, labor, supervision, safety, certification, and expertise for items described in this scope of work and the provided attachments. The government shall not loan or provide any labor or equipment. The government is not responsible for costs incurred due to mismanagement of labor or lack of proper equipment. Work shall be phased in a manner that mitigates disruption to warehouse operations.Comment by Moeller, Benjamin D. (Bacik Group, LLC): any

The scope of this project includes, but is not limited to, the following improvements:

· Remove existing 6’8” x 6’8” double door assembly and frame.

· Remove existing metal exterior siding to accommodate new roll up door size.

· Demolish existing interior wall to accommodate new roll up door size (drywall, studs, etc.).

· Remove all effected electrical, data, fire alarm system, etc. that will interfere with the size of the new roll up door. Items to be relocated at the discretion of the COR.Comment by Moeller, Benjamin D. (Bacik Group, LLC): and relocate allComment by Moeller, Benjamin D. (Bacik Group, LLC): , as per
· Install government furnished roll up door, 6’8” x 8’ (Brand is Wayne Dalton, Model is 16043794 - 1).Comment by Moeller, Benjamin D. (Bacik Group, LLC): Installation of
· Install power head, to be compatible with roll up door. Ensure power head can be manually operated as an alternate function, in the case of power failure or malfunction.Comment by Moeller, Benjamin D. (Bacik Group, LLC): alternative function, in the

· Install new electrical conduit and cable for new power door.

· Remove existing metal siding to accommodate new man door.

· Demolish existing interior wall to accommodate new man door (drywall, studs, etc.).

· Remove all effected electrical, data, fire alarm system, etc. that will interfere with the new man door. Items to be relocated at the discretion of the COR.

· Install new man door. Door to be of metal construction and include a large security glass window for viewing dock leveler operation from inside Building 170.

· Reroute all effected electrical, data, fire alarm system, etc.

· Frame, drywall, mud, tape, paint, and seal around the new man door and roll up door on the interior. New construction shall match surrounding finishes unless indicated otherwise.

· Install metal siding on the exterior. Construction shall match surrounding finishes unless indicated otherwise.

· Install eight (8) bollards for wall and door protection. Bollards shall be surface mounted to the concrete floor, four (4) bollards at each opening. Bollards shall be rated to withstand forklift/pallet truck impact. See provided schematic drawings for additional information.

· Repair and seal concrete floor cracks in Room 105.

· Paint the floor with an epoxy-based paint, include anti-skid additive in Room 105.

· Install new caution floor adhesive around existing equipment in Room 105.

· Install new coil packs into AHU to provide cooling to Building 170.

· Install/update control unit on building louvers to optimize conditions inside Building 170

· Remove existing 3hp fan and air box inside existing AHU to install new components in the same space

· Install new cooling condenser unit outside the south side of the Bldg. On a housekeeping pad. Coordinate with COR for final placement.

· Install 1 Trane Performance Climate Changer (CSAA) or approved equal.

Install 1Trane Odyssey System Outdoor Unit or approved equal.

The final construction shall conform to all VA requirements outlined in the FGI Guidelines for Design and Construction of Hospitals, Facilities Guideline Institute (FGI), ADA, Joint Commission Accreditation Standards, ANSI, SMACNA, IBC, NEC, NFPA as well all requirements of the VA design manuals posted by discipline in the VA Technical Information Library at the following web address: http://www.cfm.va.gov/til/dManual.asp Existing Conditions All associated work, as part of the scope, is limited to Building 170 Warehouse. The existing roll up door is not large enough to allow a forklift into the building. Building 170 does not have a man door to be able to operate the dock lift gates. VA needs to have cooling in Building 170. Currently there is no A/C in the building. The Contractor is expected to be familiar with the existing conditions and the work to be performed. The Contractor shall verify all areas requiring work as stated in the project scope prior to the commencement of work.

Site Investigation is required for this project to ensure accuracy. The Contractor shall be responsible for field verifying all conditions and quantities that may affect the project work prior to bid of this project. Prior to conducting the site investigation, the Contractor shall check in with the VA Facilities Management Services department and will be escorted by the VA Contracting Officer’s Representative (COR), or their designated individual. This work can be done in advance and is intended to limit unforeseen site conditions not indicated on the drawings.

Period of Performance Prior to the Notice to Proceed (NTP) all required pre-construction submittals (safety plans, quality control plan, schedules, materials, etc.) shall be provided to the VA for review and approval. This contract is expected to start upon Notice to Proceed (NTP) and be completed within 60 calendar days of issuance.

Construction Schedule and Working Hours Normal working hours are from 8:00 AM to 4:00 PM, Mountain Time. The Contractor shall discuss work hours with the COR prior to the commencement of work. To maintain schedule, work performed over the weekend may be allowed. Contractor shall coordinate these efforts with VA COR with a minimum 48-hour notice.

The Contractor shall provide to the VA a construction schedule indicating workflow and impact. Work progress shall be discussed weekly, at a minimum. Any impacts to VA operations must clearly be identified on the construction schedule.

Infection Control Risk Assessment There will be Infection Control Risk Assessment (ICRA) procedures and requirements for this project. The Contractor must adhere to the ICRA classifications assigned, and to the mitigation requirements of, the associated ICRA classifications. The Contractor shall identify their mitigation procedures as part of their daily reporting. The VA will perform regular walkthroughs and audits of the Contractor’s compliance with the requirements. Stated ICRA classifications are per the direction of the VA and are non-negotiable.

Daily Work Reports The Contractor shall complete and submit Daily Work Reports to the VA. The daily reports shall be completed on forms prepared by the Contractor, acceptable to the COR, and shall be submitted to the COR no later than the next working day. Daily reports should include photographs of existing conditions, a detailed description of work in progress, and the finished conditions.

Request for Information Any deviations in required work items from the Construction Documents and this scope shall come in the form of an RFI through electronic means, i.e., email, directly to the Contracting Officer (CO) and COR. The Contractor may choose to use a construction management software if it is accessible by VA personnel using the VA network. The CO is the only entity that can approve changes that impact the Scope of Work and contract cost. Any contractual changes will come in writing from the CO.

Submittals, Inspection, and Acceptance The Contractor will not be able to mobilize onsite until all critical submittals have been approved by the VA COR. The Contractor shall use an electronic submittal tracking system for management of submittal status. All submittals for each item must be approved prior to purchase and/or installation, per the specifications.

The submittal list below will be required and is not limited to:

•Project Safety Plan
•OSHA Certifications
•Letter of Superintendence
•Quality Assurance/Quality Control (QAQC) Plan
•Demolition Debris Management Plan
•Infection Control Plan
•Project Schedule

All submittals/samples required by the contract documents include, but are not limited to:

•Description of each product
•Submittal drawings and/or manufacturer’s literature/data as required by the specifications
•Samples as required by the specifications
•Test reports as required by the specifications
•Material certificates of compliance
•Buy American Act compliance
•Contractor certification
•Installer qualifications
•Warranties
•Operations and Maintenance (O&M) Manuals
•Additional submittals may be required at the request of the CO or COR. A comparison of products for QA/QC may be requested by the COR and CO

The COR will review and approve/disapprove Contractor submittals. Any submittal that is disapproved shall be addressed by the Contractor in a timely manner. If more time is needed to address disapproved submittals, the Contractor may ask, in writing, for additional time from the COR. The VA has a pre-determined number of working days to review submittals once they are received by the Contractor. Information regarding number of days for the submittal process can be found in the project specifications.

The COR will accomplish inspection and acceptance of the work on behalf of the CO. Any work that is found to be unacceptable by the COR shall be removed and replaced at no cost to the Government. All workmanship/quality of work is subject to acceptance.

Safety / Security The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel inside and immediately surrounding the work area, prevents damage to property, and avoids normal work or patient flow interruptions. To accomplish this end, the Contractor shall provide an OSHA certified Competent Person to be always onsite while work is being performed, erect appropriate safety barricades, signs, signal lights, etc. as well as comply with the requirements of all Federal, State, and Local safety laws, rules, and regulations. The Contractor must submit copies of certifications for safety training of the Competent Person stationed onsite to the COR before work begins. Temporary egress and life safety signage to be provided by Contractor and any Interim Life Safety Measures (ILSMs) required shall be coordinated with VA COR and the VA Safety Department.

Site Cleanup and Restoration The Contractor shall remove waste generated from the worksite on a scheduled basis. Waste shall be deposited in an appropriate dumpster provided by the Contractor, located in an area approved by the COR and removed from the grounds weekly or when full. The Contractor is responsible for the procurement of waste services, and no government leased, or owned dumpster shall be used to dispose of construction waste.

Damage of interior and exterior items such as lawns, floors, walls, ceiling tile, and any other Government owned equipment shall be repaired/replaced at no cost to the Government.

Upon completion of work, the Contractor is responsible for any punch list items accrued during the final walkthrough by the COR. This contract will not be fulfilled until all items are addressed in a timely manner, inspected by the COR, and have written approval.

Liability of Contractor Any damage to government property caused by the Contractor shall be repaired or replaced by the Contractor at no cost to the government.

The Contractor shall not disconnect any service or utilities without prior approval of the COR. Proper notice shall be given to the COR if interruption is needed. The government will not be held liable for any costs incurred due to time constraints needed for service or utility interruptions.

Privacy Statement – Certification and Accreditation **The Certification and Accreditation (C&A) does not apply, a Security Accreditation Package is not required** In accordance with the Contract Security Checklist required by VA Directives 6500 and 6500.6. Contractor owned laptop computers or remote connections from a Contractor system to a VA internal trusted (i.e., non-public) network will not be required or involved in this project. As a result, C&A (Certification and Accreditation) requirements do not apply, and a Security Accreditation Package is not required.

Warranty The Contractor shall provide a two week notice to the COR for the onsite final walkthrough and punch list for acceptance as well as other planned milestones.

The Contractor shall provide a 1-year warranty on all items within the Scope of this Project, subject to latent defects, per 52.246-21 Warranty of Construction.

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

All work and services, materials, labor, supervision, safety, certification, and expertise for items described in scope of work for Project 436-23-123, Building 170 Warehouse Upgrades.

Contract Period: Base POP Begin:

POP End:

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries

GRAND TOTAL
__________________

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR QUOTE

This is a Request for Quote in accordance with FAR Part 13. Potential offerors must follow all instructions to be compliant with the solicitation.

It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.

The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance and Price.

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4. Certified SDVOSB/VOSB listed in the SBA certification database at https://veterans.certify.sba.gov/ (see 13 CFR 128). A joint venture may be considered eligible if it meets the requirements in 13 CFR part 128, and the managing joint venture partner makes the representations under VAAR 819.7003 paragraph (b). An offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETCERT.

I.3A SITE VISIT

See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation.

I.4A SELECTION CRITERIA/QUOTE PREPARATION INSTRUCTIONS

Quotes will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures Award will be made based on the following factors:

Factor 1 - Past Performance Factor 2 - Price Offerors are encouraged to provide their best offers with the past performance information requested for evaluation. The Government, based on the offered material presented, will award to the offeror that best demonstrates to be most advantageous for the Government.

Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size, and complexity. For purposes of this evaluation, a relevant project is further defined as completing construction modifications in a medical facility environment. Project shall have a minimum amount of $25,000.00 or more and completed within the past five years from the date of issuance of this RFQ. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the quote. The Government may also evaluate recent and relevant past performance, based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THE OFFEROR CANNOT PROVIDE A CPARS FOR PROJECTS LISTED IN FACTOR 1, then the offeror shall submit Past Performance Questionnaires (PPQ).

Completed PPQs should be submitted directly from your client via email to Robyn Young at robyn.young2@va.gov. If you have any questions, please contact Robyn Young at robyn.young2@va.gov. If the offeror is unable to contact a client for a project(s) before closing date, the offeror should complete and submit with the quote the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.

Basis of Evaluation: Past Performance will be evaluated in accordance with FAR 13.106-2 and award will be made to the offeror presenting the best value to the Government.

The Government also reserves the right to award to the lower priced offeror with lower past performance rating if the Contracting Officer (CO) determines the price difference does not merit awarding to the higher priced offeror. In that event, the CO shall make an integrated assessment best value award decision.

Factor 2 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF 1442 Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

•Comparison of quoted prices received in response to the RFQ
•Comparison of quoted prices with the IGCE.
•Comparison of quoted prices with available historical information.

The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.

Special Standard of Responsibility Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.

2. Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0. If an offeror’s EMR is above 1.0, the offeror must submit a written explanation of the EMR from its insurance carrier on the insurance carrier’s letterhead, describing the reasons for the EMR and the anticipated date the EMR may be reduced to 1.0 or below.

Offerors who fail to meet any special standard of responsibility may not be eligible to receive contract award.

PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

I.1B COST RANGE: Between $100,000 and $250,000.

I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.

I.3B METRIC PRODUCTS:

Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

I.4B REQUESTS FOR INFORMATION:

All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the SF 1442, Solicitation, Offer and Award.

I.5B QUOTE REQUIREMENTS

General – Both past performance information and price proposal shall be submitted in response to this solicitation. Quotes shall be submitted via email to robyn.young2@va.gov. Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, one attachment for LOS certification, and one attachment for past performance information) not to exceed 15MB. Quote can be submitted in one email if 15MB or less. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. Electronic copies of the quotes will be time/date stamped by Microsoft Outlook upon receipt of email. Further details on electronic submission are outlined below.

Quotes shall be received by 2:00 pm MT on November 17, 2023. There will be no public opening. Submit quotes to: robyn.young2@va.gov.

Important Notice: Apparent successful offerors must apply for and receive verification from the Small Business Administration (SBA) through the SBA certification database via 13 CFR Part 128, VAAR 819.7011, and VAAR 819.7003 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the SBA certification database at the time of offer submission. Failure to be both VERIFIED by SBA and VISIBLE on the SBA certification database at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the SBA and submit the required documents to obtain verification of their SDVOSB status if they have not already done so.

I.6B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER

Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.

In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.

Acceptable Electronic Formats (Software) for Submission of Offers

1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Print or scan images of spreadsheets are not acceptable. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF (purpose: contracting can open the PDF version and engineering can open AutoCAD files).

1. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.

1. Other electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.

1. Please note that we can no longer accept .zip files due to increasing security concerns.

1. E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.

a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, or Bid depending on the solicitation type.

b. Size: Maximum size of the e-mail message shall not exceed 15 megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.

c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.

Each electronic offer must also include a signed and scanned SF 1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)

The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipients “inbox” is the official record of receipt.

Security Issues, Late Bids, Unreadable Offers

1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.

1. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.

1. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus, or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).

1. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your quote is readable.

1. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
4.1 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision)

2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— 11/02/2023 at 1:00 PM MT

(c) Participants will meet at— Admin Bldg, 141, second floor, Engineering Conference Room (End of Provision)

2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
AUG 2020
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $45 Million.

(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—

(i) Is set aside for small business and has a value above the simplified acquisition threshold;

(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or

(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.

(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(C) The provision with its Alternate II applies to…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .