Power for Temporary Air Handler.pdf

PDF 42 KB Posted

Attached to
Z2DA--Replace AHU's Impacting Pharmacy, Lab, IR Suites and Ground Floor
Solicitation number
36C25922R0009
Issued by

About this file

This document outlines a federal construction contract opportunity and related technical specifications. The Oklahoma City VA Medical Center requires a contractor to replace air handling units impacting the pharmacy, lab, IR suites and ground floor in accordance with provided plans, drawings and specifications. All work will be performed at the Oklahoma City VAMC located at 921 NE 13th St. Oklahoma City, OK. Additionally, the technical specifications call for providing power for a temporary air handler by connecting to a spare breaker at Substation #3, installing approximately 450 feet of 4-inch conduit and conductors to a new 400-amp panel at the temporary unit's discretionary location. The conduit between Substation #4 and the air handler can be above ground and temporary.

View the file

Other files

File Type Posted
Updated Bid Schedule.pdf PDF
262416 Panelboards.pdf PDF
Complete RFI Answers.pdf PDF
36C25922R0009 0002.pdf PDF
Project 535-14-103 Sheet E207 Path.pdf PDF
36C25922R0009 0001.pdf PDF
RFIs.pdf PDF
Pre-Bid Site Visit Attendance.pdf PDF
Mechanical Calculations.pdf PDF
635-20-102 Drawings stamped_Part1.pdf PDF
635-20-102 Drawings stamped_Part2.pdf PDF
635-20-102 Specifications.pdf PDF
2015-06-05 Past Performance Questionnaire.docx DOCX document
S02 - Calculation Worksheet for Self-Performed and Subcontracted Work.docx DOCX document
36C25922R0009_1.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Power for Temporary Air Handler – Provide instead of temporary generator

A pathway exists between Substation #3 and Substation #4. Connect to spare breaker and set to 400 amps. Install 4-inch conduit and 4-600 MCM THHN/THWN plus #3 grounding conductor approximately 450 feet from Substation #3 through Substation room #4 to new panel at temporary air handler. Install new 400-amp panel for feed to temporary air handling unit. Specific panel location at discretion of VA.

Conduit between Substation #4 and air handler can be above ground and will be temporary.