36C25922R0009_1.pdf
PDF 831 KB Posted
- Solicitation number
- 36C25922R0009
About this file
This solicitation is for a construction project to replace air handling units at the Oklahoma City VA Medical Center. The contractor will provide all labor, materials, equipment, and supervision necessary to complete the project in accordance with provided plans, drawings, and specifications. Work will be performed at the Oklahoma City VAMC located at 921 NE 13th Street in Oklahoma City, Oklahoma. The project magnitude is estimated between $2,000,000 to $5,000,000. Responses are due by February 14, 2022. The solicitation is set aside for service-disabled veteran-owned small businesses, and awardees must be verified as eligible by the VA's Center for Verification and Evaluation. The contractor will have 300 calendar days from notice to proceed to complete the project.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
1 80
36C25922R0009
X
635-20-102
36C259
Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 robyn.young2@va.gov
Robyn Young 307-433-3728
The Oklahoma City VAMC has a requirement for a construction contractor to provide all labor, materials, equipment and supervision necessary to Replace AHU's Impacting Pharmacy, Lab, IR Suites and ground floor in accordance with all plans, drawings and specifications. All work will be performed at the Oklahoma VAMC located at 921 NE 13th St.
Oklahoma City, OK.
Project magnitude: between $2,000,000 and $5,000,000. The NAICS code is 236220 - Small Business size standard is $39.5M
Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
A site visit will be held on January 20, 2022 at 1:00 PM CT Attendees will meet at the North Entrance of the Oklahoma City VAMC, 921 NE 13th Street, Oklahoma City, OK. See Instructions to offerors for additional screening information.
All questions in relation to this solicitation must be submitted in writing via e-mail to robyn.young2@va.gov and received no later than 15 days prior to solicitation close in order to permit adequate time for the Government to reply to inquiries.
All submitted proposals must be received in email by the closing date and time. The solicitation closes February 14,2022 at 2:00 PM CT. The documents required to be received are outlined in the Instructions, Conditions, and Notices to Offerors.
Original Offer Guarantee must be received at the address in the instructions to offerors by closing date and time or proposal will not be considered.
10 300
X X 52.211-10
X 10 Days
1 14:00
02-14-2022
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C259
Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
Financial Service Center PO Box 149971 Austin TX 78714-9971
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
A.3 Bid Schedule A.4 Scope of Work
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE
OF THE WORK (MAY 2014)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE
EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS (MAY 2014)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
(FEB 2021)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
2.11 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE
RESOLUTION (OCT 2018)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)
(JUL 2020) (DEVIATION)
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS
AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
3.3 52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES—
REPRESENTATION (OCT 2020)
3.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
3.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—
CERTIFICATION (NOV 2021)
GENERAL CONDITIONS
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR
INFORMATION SYSTEMS (NOV 2021)
4.2 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING
RESPONSIBILITY MATTERS (OCT 2018)
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
4.4 52.219-14 LIMITATIONS ON SUBCONTRACTING (SEP 2021)
4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(SEP 2021)
4.6 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY
2014)
4.7 52.223-21 FOAMS (JUN 2016)
4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)
4.9 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.10 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.11 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
4.12 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR
PERSONNEL (MAY 2020)
4.13 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)
4.14 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND
COMPLIANCE (JUL 2018)
4.15 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021)
(DEVIATION)
4.16 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)
4.17 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND
VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)
4.18 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION
CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)
4.19 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV
2018)
4.20 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION
CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)
4.21 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(APR 2019)
4.22 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)
4.23 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)
4.24 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT
ADMINISTRATION (OCT 2020)
4.25 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT
(SEP 2019)
4.26 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN
2008)
4.27 Attachments, Specifications and Drawings
4.28 Wage Determination
A.3 Bid Schedule
Bid Schedule
The contractor shall furnish all labor, equipment, materials, and supervision for Replace AHU’s Impacting Pharmacy, Lab, IR Suites, and Ground Floor at the Oklahoma City VA Health Care System, 921 NE 13th St., Oklahoma City, OK 73104.
The contractor shall include prices for all items and include all costs associated for work in the SOW. Work will be accomplished at the Oklahoma City VA Health Care System, 921 NE 13th St., Oklahoma City, OK 73104.
CLIN Description Qty Unit of issue
Firm Fixed Price Lump Sum Total amount
0001 Base Pricing
(SEE SOW FOR DETAILS)
Provide all work as described by attached plans, specifications, and Wage Determinations for Veterans Administration project Replace AHU’s Impacting Pharmacy, Lab, IR Suites, and Ground Floor at the Oklahoma City VA Health Care System as described in the attached scope of work. Price includes all costs for construction. Cost shall include but not be limited to direct and indirect costs including profit, overhead, general and administration, insurance, labor, bonds, taxes, necessary for 100% completion of the project as indicated in the attached SOW. The construction performance period is 300 calendar days from receipt of notice to proceed.
1 Job $_________
Grand Total $_______________
A.4 Scope of Work
Scope of Work
635-20-102
Replace AHU’s Impacting Pharmacy, Lab, IR Suites, and Ground Floor
GENERAL CONSTRUCTION Work includes general construction, alterations, site prep and necessary removal of existing equipment and construction and certain other items. Phasing and coordination with commissioning agent shall be required to accomplish the scope of work. Floor penetrations and minor finishes are required to complete this project. See drawing and specification for more details.
Mechanical work includes all labor, material, equipment, and supervision to perform the required Mechanical construction work on this project including replacement of air handlers, fan coils, select terminal boxes and supporting piping and duct work. Select demolition of duct work, piping, controls, etc. shall be conducted to demolish AHU-7 and AHU-14 and prepare the space for the new work. Provide AHU-7 and AHU-14 and required duct work, piping, controls, pump, exhaust fan, air terminals and air terminal unit, etc. to provide a complete and functional HVAC system. Minor fire protection scope is required to accommodate new HVAC equipment.
Temporary HVAC equipment shall be provided to minimize downtime in space. See drawing and specification for more details.
Electrical work includes but is not limited to the following: Demolish VFDs serving AHU-7 and AHU-14. Provide new VFDs and provide new power circuits (breakers, wire, conduit, disconnects, etc.) for 480-volt and 120-volt loads. Provide power for circulation pump including VFD and disconnect. Provide power to exhaust fan along with necessary disconnect.
Provide power for controls to steam to steam generation humidifier. Provide 50VA 120/24VAC control transformers and power circuits for air terminal units. See drawing and specification for more details.
The estimated Period of Performance (POP) is set for 300 days from Notice to Proceed (NTP).
The VA would sign an administrative NTP to order the long lead items, and then do a Construction NTP once equipment is ready for delivery, to limit the actual construction time.
VHA Supplemental Contract Requirements for Combatting COVID-19
1. Contractor employees who work in or travel to VHA locations must comply with the following:
a. Documentation requirements:
1) If fully vaccinated, contractors shall show proof of vaccination.
i. NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination.
2) If unvaccinated, contractors shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor’s order or an FDA approved over-the-counter test that includes an affiliated telehealth service.
3) Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.
4) Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
2. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the COVID-19 Screening Tool. Check regularly for updates.
a. Contractor employees who work away from VA locations, but who will have direct contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance, each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
3. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PART I/SECTION A – REQUEST FOR PROPOSAL
I.1A JOINT VENTURES
If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ prior to award.
I.2A SELECTION PROCEDURES
This acquisition will be a competitive acquisition utilizing FAR Part 15 source selection employing tradeoff source selection procedures. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, representations, and certifications. All such offers shall be treated equally except for their prices and performance records. Failure to meet a requirement may result in an offer being determined non-compliant. It is the intent of the Government to award without discussions; however, the Government will reserve the right to have discussions if such are needed.
I.3A PRE-PROPOSAL SITE VISIT
See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please leave extra time to complete COVID-19 screening process when entering the building. Masks are required to be worn by all employees and contractors while on VA property.
I.4A SELECTION CRITERIA
This acquisition will utilize the tradeoff process in accordance with FAR 15.101-1. This process permits tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest rated proposal to achieve a best value contract award based on established evaluation criteria. Inherent in this process is the necessity to make tradeoffs considering the non-cost strengths and weaknesses, risks, and the cost (or price) offered in each proposal.
The source selection process will be conducted utilizing FAR part 15.101-1 Trade-off Process Source Selection Procedures with Special Standards of Responsibility. Offers will be evaluated using the following evaluation factors:
Factor 1 – Past Performance Factor 2 – Price http://www.vetbiz.gov/library/jtventure.pdf
In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.
Past performance will be evaluated on a basis of significantly more important than, cost or price.
Past Performance Evaluation
For Factor 1, based on the evaluation of all recent and relevant past performance for an offeror, an overall performance confidence rating shall be assigned. The performance confidence ratings are defined below:
ASSESSMENT DESCRIPTION
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral)
No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
Note: In the case of an offeror without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall receive an unknown confidence (neutral) performance confidence rating.
(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.
(1) The first is to evaluate whether the offeror’s present/past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection.
(2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all
CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
(b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment.
Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.
Factor 1-Past Performance
(a) Solicitation Submittal Requirements:
Offerors shall provide a maximum of five (5) recent and relevant projects (as defined below) to demonstrate their ability to perform the proposed work identified within the Specifications, drawings and Statement of Work. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Robyn Young, robyn.young2@va.gov.
Recency – a recent project is defined as being completed within five years of the due date of this solicitation.
Relevant – includes performance of efforts in a project to replace and install air handling units and accessories at an active medical facility that are similar or greater in scope, magnitude, and complexity than the effort described in this solicitation.
Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical mailto:robyn.young2@va.gov errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.
(b) – Basis of Evaluation:
The contracting officer shall review recent and relevant performance information on each offeror based on past efforts provided by the offeror and may obtain data independently from other government and commercial sources. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Offerors with no past performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.
Initially offers shall be ranked according to price, including any option prices if applicable. The lowest price offer’s past performance shall be evaluated to determine its performance confidence rating.
If the lowest priced evaluated offer is judged to have a Substantial Confidence performance assessment, that offer represents the best value for the government and the evaluation process stops at this point.
Award shall be made to that offeror without further consideration of any other offers.
If the lowest price offer does not receive a Substantial Confidence performance confidence rating, the past performance evaluation continues until an offeror’s past performance is judged to have a Substantial Confidence performance rating. The Government reserves the right to award a contract to other than the lowest priced offeror if the lowest priced offeror is judged to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision.
Factor 2 – Price:
(a) Solicitation Submittal Requirements:
• Standard Form 1442, Solicitation Offer and Award
• All pages of the SF1442 Continuation Sheet
(b) Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
• Comparison of proposed prices received in response to the RFP
• Comparison of proposed prices with the IGCE.
• Comparison of proposed prices with available historical information.
Special Standard of Responsibility
Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
(1) OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.
(2) Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
(3) Limitation on Subcontracting:
IAW VAAR 852.219-77 each offeror will review the clause and complete the certificate included in the clause. This certificate will be complete prior to solicitation closing and submitted with the proposal documents. Failure to comply with this requirement will result in removal of proposal for consideration for award.
Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.
PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
I.1B COST RANGE: Between $2,000,000.00 and $5,000,000.00
I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.
I.3B METRIC PRODUCTS:
Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met. If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.
I.4B REQUESTS FOR INFORMATION:
All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.
I.5B PROPOSAL REQUIREMENTS
General – Both past performance information and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email robyn.young2@va.gov. Emails are limited to 15 MB.
The proposal, in its entirety, shall be one email (one attachment for price proposal, and one attachment for past performance information) not to exceed 15MB. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. An original Bid Bond, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the bid price shall be mailed to the address listed in block 8 of the SF1442 and be received at the address no later than the closing date and time. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for due date, will require rejection of the proposal in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation.
Electronic copies of the proposals will be time/date stamped by Microsoft Outlook upon receipt of email.
Further details on electronic submission are outlined below.
Proposals shall be received by 2:00 PM CT on February 14, 2022. There will be no public opening of the proposals. Submit proposals to: robyn.young2@va.gov.
Submit bid bonds to:
Cheyenne VA Medical Center 442-90C ATTN: Robyn Young 2360 E Pershing Blvd.
Cheyenne WY 82001
Past performance information and price sections of the offeror’s proposal will be evaluated independently. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.
Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with
38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
I.6B PROPOSAL REVISIONS
If it is determined to be necessary, proposal revisions will be requested from the offers received. The Contracting Officer may identify those offerors, whose proposals are within the competitive range based upon the selection criteria identified in this solicitation. Negotiations may be conducted with those firms falling within the competitive range, after which proposal revisions may be requested. Offerors submitting proposal revisions will not be required to re-submit any documents which are unchanged from their proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with the Table of Contents that clarifies where within the initial proposal the additional information and/or changed document would be placed. A new bid bond shall be submitted only if the final cost proposal revisions are greater than its initial cost proposal.
1.7B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER
Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.
In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.
Acceptable Electronic Formats (Software) for Submission of Offers
1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files).
2. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.
3. Another electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.
4. Please note that we can no longer accept .zip files due to increasing security concerns.
E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.
http://contracting.tacom.army.mil/acqinfo/ebidnotice.htm#email#email
a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, Proposal, or Bid depending on the solicitation type.
b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.
c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents.
Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.
Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)
The Microsoft Outlook © Email time/date stamp will be used to date, and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipient’s “inbox” is the official record of receipt.
Security Issues, Late Bids, Unreadable Offers
1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.
2. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.
3. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).
4. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your proposal is readable.
5. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—
SECONDARY SITE OF THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO
ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
(FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
10.2 % 6.9 %
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
Oklahoma
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—
CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID
GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Hand-Carried Address:
Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Mailing Address:
Department of Veterans Affairs
Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I
(FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
See Block 10
(c) Participants will meet at—
See Block 10
(End of Provision)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY
REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .