1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
1 of 36C25921Q0630 X None 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 Ilze Karklins-Powers 307-433-3727 The Rocky Mountain Regional VA Medical Center located at 1700 N Wheeling St., Aurora, CO 80045 has identified the need for repairs to fuel lines at the facility. See attached SOW for details.
NAICS 236220 with a business size standard of $39.5M.
The project magnitude is estimated between $50,000 and $100,000.
Offeror shall provide evidence of experience as outlined in the Statement of Work. The offeror shall also provide a current EMR rating with the quote.
A site visit is scheduled for August 9, 2021 at 10:00 AM Mountain Time (MT). Please meet by the Engineering Office after COVID screening.
All questions relating to this solicitation are due no later than close of business August 12, 2021. Please submit questions to ilze.karklins-powers@va.gov
The closing date for this solicitation is August 24, 2021 at 1:00 PM Mountain Time (MT) . Please email quotes to ilze.karklins-powers@va.gov
X X 52.211-10 X
1:00 PM
MDT
08-24-2021 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin
TX
78714-9971
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 Statement of Work | 5 |
| A.4 Bid Schedule | 14 |
| A.5 Instructions to Offerors | 15 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 20 |
| 2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 20 |
| 2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 20 |
| 2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 21 |
| 2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 22 |
| 2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 23 |
| REPRESENTATIONS AND CERTIFICATIONS | 24 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION) | 24 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020) | 27 |
| GENERAL CONDITIONS | 31 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 31 |
| 4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 31 |
| 4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (NOV 2020) | 31 |
| 4.4 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (FEB 2021) | 34 |
| 4.5 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000) | 38 |
| 4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 38 |
| 4.7 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 40 |
| 4.8 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020) | 40 |
| 4.9 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 41 |
| 4.10 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 43 |
| 4.11 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019) | 43 |
| 4.12 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 45 |
| 4.13 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 47 |
| 4.14 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 49 |
| 4.15 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 49 |
| 4.16 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 49 |
| 4.17 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 51 |
| 4.18 Wage Determination | 51 |
| 4.19 Attachments | 64 |
A.3 Statement of Work
Page 1 of Page 1 of
A. 259 GENERAL INFORMATION
1. Title of Project: Fuel line Repair
2. Scope of Work:
Contractor shall test all lines to find all points of failure and make all necessary repairs needed to ensure the integrity of the system of all polisher lines located behind Building L. The work shall include but is not limited to the following:
A. Contractor shall dig in a designated area behind Building L. to locate polishers pump lines that are approx. 10’ below the surface.
a. Shoring is required due to existing site conditions and OSHA requirements due to depth and soil type.
i. There is approximately 4’ of pea gravel over the buried lines.
B. Contractor shall test all polisher lines to locate leaks and shall make all necessary repairs to the lines. Repairs may include but are not limited to replacing whole sections of lines and repairing fittings. Once repairs to the lines are completed contractor must flush all the lines and test all lines for leaks to ensure all leaks have been repaired before work is completed. Testing including the startup of all polishers effected.
a. All work will be inspected by OPS in accordance with the State of Colorado regulations. Inspection before backfilling should be coordinated with the COR.
b. If hot work is required to fix the lines contractor shall purge the lines to ensure work can be completed safely. Contractor shall dispose of all hazardous waste in accordance with State of Colorado rules and regulations.
c. Contractor shall plan on having confined space entry equipment to enter the sumps underground.
C. Follow OSHA/Safety standards on excavation and area safety. Ensure that the building, fuel tanks, and nearby water tanks are not affected by the excavation.
D. After confirming repairs are complete, contractor will backfill the hole to the previously designed state.
E. Contractor will provide all material, equipment, manpower with 5-year knowledge of fuel system repair. According with OSHA. Colorado state and federal regulation. Contract will generate a report informing Colorado oil and public safety of the repairs.
3. Background: This is an EPA, OSHA, State and Federal repair to our fuel system. This repair will allow us to run the Polisher safely to remove water from our system. Access to the fuel tank is from the 17TH Fitzsimons Parkway between building K and L. Contractor must check in with the Energy Center first.
4. Performance Period: Fifteen (15) days after NTP
5. Place of Performance: Rocky Mountain Regional VA Medical Center (ECHCS) at 1700 N. Wheeling St., Aurora, CO 80045
B. CONTRACT AWARD MEETING
1. The contractor shall schedule, in advance, all work to be performed with the COR to prevent interference with other contract performance and Medical Center activities.
C. SPECIFIC MANDATORY TASKS AND ASSOCIATED DELIVERABLES
1. RESPONSIBILITIES OF THE CONTRACTOR
· Contractor to provide, and review with the COR, all reports, and findings. A suggested follow-up summation to be reviewed by COR and contractor.
E. GOVERNMENT RESPONSIBILITIES
1. The VA shall provide, to the contractor’s authorized personnel, access to the equipment and adequate working space during the periods which the contractor has scheduled with the VAMC to perform service.
F. CONTRACTOR RESPONSIBILITIES
1. SAFETY AND ENVIRONMENTAL PROTECTION
The Contractor shall be responsible to ensure all work shall be done in a manner that safeguards all VA visitors, employees, and public. The Contractor shall be solely responsible for any and all actions initiated and/or completed by his/her employees. Furthermore, the contractor and his/her employees shall have a clear understanding of, and be sensitive to, environmental issues, and be consistent and fully compliant with all applicable Federal, State, County and City laws, ordinances, Right-to-Know laws, EPA guidelines, and regulations.
Matters related to safety, and any actions of the Contractor shall meet all safety requirements, Department of Veterans Affairs, OSHA, and the State. It is incumbent upon the Contractor to be familiar with these requirements. All hazardous materials shall be handled, stored, and used in accordance with applicable NFPA, OSHA, and EPA standards appropriate for each material. An inventory of hazardous materials will be completed quarterly, and a copy will be available on site for COR review. Current Material Safety Data Sheets will be kept on hand for all materials.
Adequate warning devices, barricades, or other necessary precautions shall be provided by the Contractor at all work sites to eliminate hazards and for the protection, safety, and warning of all public visitors, pedestrians, cemetery employees, and vehicular traffic within the area.
Spill Prevention, Containment, and Clean-up: The Contractor shall contain, clean up, and report all spills on Government property in a manner that complies with all applicable Federal, State, and Local laws and regulations or otherwise stated herein, and the installation spill control plan at no cost to the Government.
2. FIRE SAFETY
Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
| 1. National Fire Protection Association (NFPA): | |
| a. Standard for Portable Fire Extinguishers | |
| b. Flammable and Combustible Liquids Code |
| 2. Occupational Safety and Health Administration (OSHA) | |
| a. 29 CFR 1926, Safety and Health Regulations for Construction |
Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926.
Means of Egress: Do not block exits for occupied buildings, including paths from exits to roads. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police, and other emergency response forces in accordance with NFPA 241.
Flammable and Combustible Liquids: No flammable and combustible liquids shall be stored within the Medical Center property. [Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.]
Smoking: Smoking is prohibited except in designated smoking rest areas approved by the COR.
3. OPERATIONS AND STORAGE AREAS
Working space and space available for storing materials will only be available at the approval of the COR or Contracting Officer. If approved, the location is to be where approved by the COR or where shown on drawings as the “Contractor Staging Area”. It is understood the VA will not be held responsible for any damage to the Contractor’s equipment, materials, supplies or the like which may result from vandalism, theft etc. while on site. Contractor shall base operations out of this staging area, using it for materials and equipment storage, administration, employee parking, employee lunch/break area, etc.
The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR or Contracting Officer. Do not store materials and equipment in other than approved areas. The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
The Contractor shall, under regulations prescribed by the Contracting Officer or COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the COR or Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
Execute work in such a manner as to interfere as little as possible with work being done by others. To minimize grounds maintenance activity interference with flow of Medical Center traffic, keep roads, walks and entrances to grounds, parking and occupied areas of buildings clear of materials, debris and standing equipment/vehicles at all times. At least one lane must be open to traffic at all times.
Coordination of work with COR or authorized designee: The Contractor shall cooperate and coordinate with the COR or authorized designee, in arranging schedule to cause the least possible interference with Medical Center activities.
4. PROTECTION OF EXISTING STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS
Damage to Government property: The Contractor (including his or her employees, subcontractors, consultants, or the like) shall be responsible for repair or replacement of any contractor damaged Medical Center structure, which are chipped, marred, damaged and/or ruined at the fault of the Contractor. The Contractor shall bear all costs associated with replacement and reinstallation. Any such damage shall be brought to the immediate attention of the COR prior to repair, replacement, or installation.
The Contractor shall preserve and protect all structures and equipment, on or adjacent to the work site that are not to be removed and which do not unreasonably interfere with the work required under this contract.
The Contractor shall protect from damage all existing utilities at or near the work site. The Contractor shall immediately notify the COR of any such occurrence and repair any damage to those facilities, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
Protection of Existing Utilities: Contractor shall be responsible for damages to utilities, above and below ground.
5. SUPERVISION:
Contractor Supervisor: A competent and experienced Contractor Supervisor shall be provided by the Contractor whenever work is being performed. The Contractor Supervisor must have not less than five (5) years’ experience in the Fuel line installation and repair industry and perform all necessary maintenance and repair of the fuel lines and tanks.
In the absence of the Supervisor, the Contractor shall appoint an crew foreman or an employee who shall be responsible to insure that the work is being accomplished in an expeditious manner, is performed in accordance with the contract specifications and that the work will progress without undue delay.
6. EMPLOYEE REQUIREMENTS
The Contractor shall be responsible to ensure Contractor employees providing work on this contract are fully trained and completely competent to perform the required work.
Should the need arise for unlisted, unproved contractor personnel to provide maintenance and/or repair on Government owned equipment, the contractor will email a copy of the above required documentation to the Contracting Officer simultaneously, prior to the performance of said work.
No unqualified individual will be allowed to perform maintenance and/or repair of any equipment under this contract. Technician trainees or other unqualified individuals may assist or observe only, however, may not be allowed to do so if their presence delays the progress of the work to be accomplished. The Government will NOT pay for unqualified individuals or technician trainees present.
Person Protective Equipment (PPE): Contractors and their subcontractors of any tier are required to wear personal protective equipment (PPE) in accordance with OSHA Act, 1971 and other Federal, State and Local regulations. Personnel observed in violation of these regulations may be subject to removal from the medical center. The Government assumes no responsibility for injury of contract personnel or subcontractors of any tier if the injury is a direct result of noncompliance or disregard for these regulations.
Labor Force and Equipment: Contractor shall be responsible to provide all labor and equipment as necessary to meet deadlines. The Contractor will provide all necessary resources to complete the efforts assigned under the scope of this contract.
Employee Listing: The Contractor shall maintain and provide the COR a current list of all employees on site including subcontractor personnel. The list shall include the employee’s name, job title, and driver’s license number.
Employee Identification: The Contractor's employees shall always wear visible identification while on the premises of the Medical Center. This could be in the form of a company shirt which displays the company name and/or logo or by some other means suitable to this type of work.
Contractor personnel shall park only in the COR approved area identified for this project. Workers are not allowed to park throughout the Medical Center.
The Contractor shall be responsible to ensure that his/her employees (including contractor’s consultants, subcontractors, etc.) are aware of all the terms and conditions regarding their performance and conduct during the performance period of this contract.
Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation/summons answerable in the United States (Federal) District Court, or another appropriate agency/jurisdiction.
7. PERMITS AND LICENSES
The Contractor shall be responsible for obtaining all necessary and current licenses, permits, vehicular insurance and registration, Workman’s Compensatory Liability Insurance, property liability insurance etc., prior to the commencement of work. The contractor shall provide the Contracting Officer copies of these required documents with his/her proposal or at other times where the COR deems necessary during the duration of the project.
8. CONTRACTOR-FURNISHED ITEMS
The Contractor shall be responsible for supplying all equipment, personnel, tools, supplies and materials necessary to perform the services required by this contract. Contractor-furnished items necessary to perform work as required under this contract shall be furnished, maintained, and operated by the contractor and shall be consistent and fully compliant with all applicable OSHA, Federal, State, County, City laws, ordinances, and regulations.
The Contractor shall be responsible for the supply, maintenance, and repair of all contractor-owned equipment. This includes minor maintenance/repair and minor operating parts for equipment to keep all equipment in good operational condition throughout the period of performance of this contract. No contractor equipment maintenance repairs of any kind can be done on Medical Center property without the COR(s) approval.
The Contractor shall be responsible for ensuring that all his/her motor vehicles and equipment meet State inspection, safety, licensing, registration, and insurance requirements.
9. HOURS OF WORK
The normal hours of work shall take place during Normal Business hours of 0730-1600, Monday through Friday, Federal Holidays excluded. Request for weekend, after-hour, and Federal holiday work is permitted with a request in writing submitted beforehand. “Inspections” will require a prior five-day notification submitted to the Contract Officer Representative (COR) or government representative.
A.4 Bid Schedule
The contractor shall furnish all labor, equipment, materials, supervision, and tools to perform fuel line repairs at the Rocky Mountain Regional VA Medical Center. Contractor will dig in a designated area behind Building L, Energy Center. Contractor will locate polishers 2 and 3 pump lines, test lines for leaks, repair or replace broken pipes or lines as required, and retest lines for leaks. After confirming satisfactory completion of repairs, contractor will fill the hole to the normal state. Contractor will provide all material, equipment, supervision, and manpower. Contractor to have minimum 5-year knowledge of fuel system repair. All repairs shall be in accordance with OSHA, Colorado state and federal regulations. Contractor shall produce a report informing Colorado Oil and Public Safety of completion of repairs
| CLIN |
| Description |
| Qty |
| Unit of issue |
Firm Fixed Price Lump Sum amount
| 0001 |
| Base Pricing |
(SEE SOW FOR DETAILS)
Provide all work as described by attached plans, specifications, and Wage Determinations for Veterans Administration project Fuel Line Repair for the Rocky Mountain Regional VA Medical Center as described in the attached scope of work. Price includes all costs for construction. Cost shall include but not be limited to direct and indirect costs including profit, overhead, general and administration, insurance, labor, bonds, taxes, necessary for 100% completion of the project as indicated in the attached SOW. The construction performance period is 30 calendar days from receipt of notice to proceed.
| 1 |
| Job |
| $_________ |
Grand Total $______________
A.5 Instructions to Offerors
PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PART I/SECTION A – REQUEST FOR QUOTE
This is a Request for Quote in accordance with FAR Part 13. Potential offerors must follow all instructions in order to be compliant with the solicitation.
It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.
The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance, Safety and Price.
I.1A JOINT VENTURES
If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ.
I.3A SITE VISIT
See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please ensure that you do a COVID pre-screen at the main entrance before meeting for the site visit.
I.4A SELECTION CRITERIA/QUOTE PREPARATION INSTRUCTIONS
Quotes will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures Award will be made based on the following factors:
Factor 1 – Past Performance Factor 2 - Price Offerors are encouraged to provide their best offers with the past performance information requested for evaluation. The Government, based on the offered material presented, will award to the offeror that best demonstrates to be most advantageous for the Government.
Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size and complexity. For purposes of this evaluation, a relevant project is further defined as experience with fire dampers in a hospital environment. Project shall have a minimum amount of $25,000.00 or more and completed within the past five years from the date of issuance of this RFP. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the quote. The Government may also evaluate recent and relevant past performance, based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THE OFFEROR CANNOT PROVIDE A CPARS FOR PROJECTS LISTED IN FACTOR 1, then the offeror shall submit Past Performance Questionnaires (PPQ).
Completed PPQs should be submitted directly from your client via email to Ilze Karklins-Powers at ilze.karklins-powers@va.gov. If you have any questions, please contact Ilze Karklins-Powers at ilze.karklins-powers@va.gov.. If the offeror is unable to contact a client for a project(s) before closing date, the offeror should complete and submit with the quote the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.
Basis of Evaluation: Past Performance will be evaluated in accordance with FAR 13.106-2 and award will be made to the offeror presenting the best value to the Government.
Factor 2 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF1442 Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
| • | Comparison of quoted prices received in response to the RFQ |
| • | Comparison of quoted prices with the IGCE. |
| • | Comparison of quoted prices with available historical information. |
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.
Special Standard of Responsibility Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
(1) OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years
(2) Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.
PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
I.1B COST RANGE: Between $50,000 and $100,000 I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.
I.3B METRIC PRODUCTS:
Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.
If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.
I.4B REQUESTS FOR INFORMATION:
All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.
I.5B QUOTE REQUIREMENTS
General – Both past performance information and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email to ilze.karklins-powers@va.gov Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, and one attachment for past performance information) not to exceed 15MB. Proposal cam be submitted in one email if 15MB or less. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. An original Bid Bond, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the bid price shall be mailed to the address listed in block 8 of the SF1442 and be received at the address no later than the closing date and time. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation. Electronic copies of the proposals will be time/date stamped by Microsoft Outlook upon receipt of email. Further details on electronic submission are outlined below.
Quotes shall be received by 1:00 PM MT on August 24, 2021. There will be no public opening. Submit quotes to: ilze.karklins-powers@va.gov
Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
I.6B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER
Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.
In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.
Acceptable Electronic Formats (Software) for Submission of Offers
1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Print or scan images of spreadsheets are not acceptable. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files)
1. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.
1. Other electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.
1. Please note that we can no longer accept .zip files due to increasing security concerns.
1. E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.
a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, or Bid depending on the solicitation type.
b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.
c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.
Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)
The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipients “inbox” is the official record of receipt.
Security Issues, Late Bids, Unreadable Offers
1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.
1. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.
1. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).
1. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your quote is readable.
1. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 13.9 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Adams County CO
(End of Provision)
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— August 9, 2021 at 10:00 AM MT
(c) Participants will meet at— RMRVAMC - Engineering Office (End of Provision)
2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| AUG 2020 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION) (a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $39.5 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition…