RFI 1 MRI.pdf

PDF 54 KB Posted

Attached to
Z2DA--MRI Site Prep (VA-21-00003189) Federal contract opportunity
Solicitation number
36C25920R0145
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

This document contains questions and answers regarding a solicitation for an MRI site preparation project at an Oklahoma Veterans Affairs medical center. Key details include that the scope of work involves demolishing and reconstructing MRI Suite 1 and its control room along with adjoining areas, while MRI Suite 2 remains operational. Work must comply with all infection control requirements and will have a period of performance of 300 calendar days from notice to proceed. The estimated value is between $1-2 million. Storage and office space will be limited to the construction site. Testing is recommended for asbestos flooring and testing is covered for radio frequency shielding design and installation. Allowed work times will require coordination to avoid interference with the control room. Material and color selections are specified. The solicitation will be a Service-Disabled Veteran-Owned Small Business set-aside issued by the Department of Veterans Affairs Veterans Health Administration VISN 19.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--MRI Site Prep (VA-21-00003189), newest first.
File Type Posted
RFI 4.pdf PDF
VENT 2.jpg JPG image
VENT FRONT LOCATION.jpg JPG image
36C25920R0145 0013.docx DOCX document
2021-02-01 VENT on third floor mech room.jpg JPG image
Drawing Vent.pdf PDF
36C25920R0145 PG 2.pdf PDF
36C25920R0145 0012.docx DOCX document
36C25920R0145 0012.pdf PDF
Mag Shield Design Info Siemens.pdf PDF
36C25920R0145 0011.docx DOCX document
RFI 3 Q 68 through 77.pdf PDF
MRI Site Prep 100_ Final Drawings.pdf PDF
36C25920R0145 0010.docx DOCX document
MRI Site Prep 100_ Final Specifications.pdf PDF
36C25920R0145 0009.docx DOCX document
2020 07 26 100_ Final for Construction OKC MRI Specifications.pdf PDF
MRI Site Prep AD 101 Addendum 1.pdf PDF
36C25920R0145 0008.docx DOCX document
General Decision Number OKC Jan 2021.docx DOCX document
RFI 3 1-67.pdf PDF
2020 07 26 100_ Final OKC MRI Drawings.pdf PDF
36C25920R0145 0007.docx DOCX document
36C25920R0145 0006.docx DOCX document
36C25920R0145 0005.docx DOCX document
36C25920R0145 0004.docx DOCX document
2020-11-02 Pre-Bid Sign-In Sheet MRI.pdf PDF
36C25920R0145 Revised Pg1.pdf PDF
36C25920R0145 0003.docx DOCX document
RFIs 1.pdf PDF
36C25920R0145 0002.docx DOCX document
36C25920R0145 0001.docx DOCX document
Final Combined Drawings.pdf PDF
S02 Past Performance Questionnaire.docx DOCX document
SELF-PERFORMED CALCULATIONS 9-5-2019.docx DOCX document
GE MRI Drawings.pdf PDF
Combined Final Specs.pdf PDF
36C25920R0145_1.docx DOCX document
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI #1

1. Should bidders include the costs associated with Submittal Exchange in Proposal That would be an allowable cost however that would also mean that the VA and the A/E would have full access to the program.

2. Can Project Superintendent fulfill the role of SSHO? Based on the assumption the Project Superintendent meets all qualifications for both listed in specifications. – Yes

3. Please confirm that this project will require a full time stand-alone QCM as defined by specification section 01 45 00 – 1.4. – Yes,

4. Please provide area that will be provided for contractor storage. If onsite storage is not available, should bidders include the costs associated with offsite storage? – No, space is extremely limited on our campus, only storage will be on construction site itself. Yes, include cost.

5. Please provide location for contractor field office. If onsite location is unavailable, should bidders include the costs associated with offsite field office? – No, space is extremely limited on our campus, only space will be on construction site itself. Yes, include cost.

6. Does the project site contain existing asbestos flooring mastic?

There are two types of flooring in MRI suite 2F109/2F110/2F111:

2F109: 12 X 12 non-asbestos tile/ mastic needs to be tested for asbestos

2F110: 12 X 12 non-asbestos tile/mastic needs to be tested for asbestos

2F111: Linoleum : I have no testing of the linoleum or the mastic for this room

Recommend contractor include this testing as part of the project

7. What are the allowed work times for this project? –The phasing plans do show access to areas that we integrated into the project for them to work normal hours without interfering with the control room. In the final phase there is no way around having some interference with the control room, it will require at that time alternate hours or a coordinated effort by the GC.

8. Please provide manufacturer and color selection of wallcovering shown on elevation 6/A-100. – Material selections and color selections are noted in spec section 09 06 00 Schedule for finishes. If there is a missing selection, please let us know.

9. Documents call for Contractor to provide design and installation of RF shielding system. It is very likely that RF shielding will be required on the bottom side of the slab on deck. This would require removal of ceilings and possibly removing tops of walls to install shielding from the area located directly below MRI #1 site improvement space. Please provide additional information on the space below the MRI project such as structural details, existing ductwork or mechanical systems and electrical systems in conflict. RF Shielding is covered under spec section 13 49 01 Radio Frequency Shielding. The current system is a box within the confines of the MRI 1 suite, there is no RF shielding below the structure.

Under this spec the RF supplier provides the design, material and installation.

10. Please confirm that no new structural upgrades are required to accommodate new equipment.

There are no pending structural design issues known.