36C25219B0038-0003009.pdf

PDF 75 KB Posted

Attached to
556-305, Construct New Parking Garage Federal contract opportunity
Solicitation number
36C25219B0038
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

36C25219B0038 0003 263353 - Static UPS Central Lighting Inverter.pdf

View the file

Other files for this federal contract opportunity

Other files attached to 556-305, Construct New Parking Garage, newest first.
File Type Posted
36C25219B0038-0007001.pdf PDF
36C25219B0038-0007000.docx DOCX document
36C25219B0038-0006000.docx DOCX document
36C25219B0038-0005000.docx DOCX document
36C25219B0038-0005001.pdf PDF
36C25219B0038-0005002.pdf PDF
36C25219B0038-0004000.docx DOCX document
36C25219B0038-0003004.pdf PDF
36C25219B0038-0003006.pdf PDF
36C25219B0038-0003005.pdf PDF
36C25219B0038-0003008.pdf PDF
36C25219B0038-0003002.pdf PDF
36C25219B0038-0003001.pdf PDF
36C25219B0038-0003010.pdf PDF
36C25219B0038-0003000.docx DOCX document
36C25219B0038-0003007.pdf PDF
36C25219B0038-0003003.pdf PDF
36C25219B0038-0002000.docx DOCX document
36C25219B0038-0001001.pdf PDF
36C25219B0038-0001000.docx DOCX document
36C25219B0038-006.pdf PDF
36C25219B0038-003.pdf PDF
36C25219B0038-005.pdf PDF
36C25219B0038-004.pdf PDF
36C25219B0038-001.docx DOCX document
36C25219B0038-002.pdf PDF
36C25219B0038-000.docx DOCX document
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construct New Parking Garage Bid Document Captain James A. Lovell (Amendment A00002) Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 1

SECTION 26 33 53

STATIC UNINTERRUPTIBLE POWER SUPPLY / CENTRAL LIGHTING INVERTER

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies the furnishing, installation, connection, and testing of the central lighting inverter/static uninterruptible power supply, indicated in this section as Lighting Inverter.

1.2 RELATED WORK

A. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:

Requirements that apply to all sections of Division 26.

B. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES:

Low-voltage conductors.

C. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS:

Requirements for personnel safety and to provide a low impedance path for possible fault currents.

D. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduits.

1.3 QUALITY ASSURANCE

A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS

(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS.

1.4 FACTORY TESTS

A. Central Lighting Inverter shall be thoroughly tested at the factory to assure that there are no electrical or mechanical defects.

B. Factory Tests shall be in accordance with Paragraph, MANUFACTURED

PRODUCTS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL

INSTALLATIONS, and the following requirements:

1. Central Lighting Inverter shall be factory full-load tested to meet the requirements specified using a test battery (not the battery to be supplied with the system) with AC input power and with battery power for a minimum of 8 hours, with meter readings taken every 30 minutes. If a malfunction occurs, the problem shall be corrected and the test shall be repeated. The tests shall encompass all aspects of operation, such as module failure, static bypass operation, battery failure, input power failure and overload ratings.

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 2

1.5 SUBMITTALS

A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:

1. Shop Drawings:

a. Submit sufficient information to demonstrate compliance with drawings and specifications.

b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, plan, front, side, and rear elevations, accessories, and device nameplate data.

c. Provide detailed and project-specific system diagram, showing maintenance bypass, module(s), battery cabinet(s) and batteries, major circuit protective devices, interconnecting power and control wiring, and connections to power sources and loads, as applicable. Indicate whether interconnections are factory-provided/factory-installed, factory-provided/field-installed, or field-provided/field installed.

2. Manuals:

a. Submit, simultaneously with the shop drawings, companion copies of complete maintenance and operating manuals including technical data sheets, wiring diagrams, and information for ordering replacement parts.

1) Wiring diagrams shall have their terminals identified to facilitate installation, maintenance, and operation.

2) Wiring diagrams shall indicate internal wiring for each item of equipment and the interconnection between the items of equipment.

3) Provide a clear and concise description of operation, which gives, in detail, the information required to properly operate the inverter, including bypass switchboard, inverter, key-type mechanical interlocks, remote devices, emergency power off buttons, fire alarm interface, and other components as applicable.

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 3

b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.

1) Include complete "As Installed" diagrams that indicate all pieces of equipment and their interconnecting wiring.

2) Include complete diagrams of the internal wiring for each piece of equipment, including "As Installed" revisions of the diagrams.

3) The wiring diagrams shall identify the terminals to facilitate installation, maintenance, operation, and testing.

3. Test Reports:

a. Submit certified factory design and production test reports for approval.

b. Two weeks prior to the final inspection, submit certified field test reports and data sheets to the COR.

4. Certifications: Two weeks prior to final inspection, submit the following.

a. Certification by the manufacturer that the unit conforms to the requirements of the drawings and specifications.

b. Certification by the Contractor that the unit has been properly installed, adjusted, and tested.

1.6 APPLICABLE PUBLICATIONS

A. Publications listed below (including amendments, addenda, revisions, supplements, and errata), form a part of this specification to the extent referenced. Publications are referenced in the text by basic designation only.

B. Institute of Engineering and Electronic Engineers (IEEE):

C57.110-08 .............Recommended Practice for Establishing

Transformer Capability When Supplying Non-sinusoidal Load Currents

C62.41.1-02 ............Surge Environment in Low-Voltage (1000 V and

Less) AC Power Circuits

C62.41.2-02 ............Characterization of Surges in Low-Voltage (1000

V and Less) AC Power Circuits

450-10 .................Maintenance, Testing, and Replacement of Vented

Lead-Acid Batteries for Stationary Applications

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 4

485-10 .................Sizing Lead-Acid Batteries for Stationary

Applications

C. International Code Council (ICC):

IBC-15 .................International Building Code

D. National Electrical Manufacturers Association (NEMA):

PE 1-12 ................Uninterruptible Power Systems - Specification and Performance Verification

E. National Fire Protection Association (NFPA):

70-17 ..................National Electrical Code (NEC)

PART 2 - PRODUCTS

2.1 GENERAL REQUIREMENTS

A. System Capacity: Unless stated otherwise, the parameters listed are under full rated output load at a minimum of 0.9 power factor, with batteries fully charged and floating on the DC bus and with nominal input voltage. Overall 20 kW, non redundant, at 40 C.

B. Battery Capacity: Discharge time to end voltage: 90 minutes, at 25 C

(77 F). Battery shall be capable of delivering 125 percent of full rated output load at initial start-up.

C. System Bus Bracing: Braced for amperes symmetrical interrupting capacity as shown on drawings.

D. AC Input:

1. Voltage 480 volts line-to-line.

2. Number of phases: 3-phase, 4-wire, plus ground.

3. Voltage Range: Plus 10 percent, minus 15 percent, without affecting battery float voltage or output voltage.

4. Frequency: 60 Hz, plus or minus 5 percent.

5. Total harmonic current distortion (THD) reflected into the primary line: 10 percent maximum.

E. AC Output

1. Voltage 480 volts line-to-line, 277 volts line-to-neutral.

2. Number of phases: 3-phase, 4-wire, plus ground.

3. Voltage regulation:

a. Balanced load: Plus or minus 1.0 percent.

b. 100 percent load imbalance, phase-to-phase: Plus or minus 3 percent.

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 5

4. Frequency: 60 Hz.

5. Frequency regulation: Plus or minus 0.05 percent.

6. Harmonic content (RMS voltage): 5 percent maximum total harmonic distortion with 100% nonlinear load.

7. Load power factor operating range: 1.0 to 0.8 lagging.

8. Phase displacement:

a. Balanced load: Plus or minus 1 degree of bypass input.

9. Overload capability (at full voltage) (excluding battery):

a. 125 percent load for 10 minutes.

b. 150 percent load for 1 minute.

F. Voltage Transient Response:

1. 100 percent load step: Plus or minus 5 percent.

2.2 INVERTER

A. General Description: Inverter module shall consist of a rectifier/charger unit and a 3-phase inverter module unit with their associated transformers, synchronizing equipment, input and output circuit breakers, and accessories as required for operation.

B. Rectifier/Charger Unit: Rectifier/charger unit shall be solid state and shall provide direct current to the DC bus.

1. Input Circuit Breaker: Rectifier/charger unit shall be provided with an input circuit breaker. The circuit breaker shall be sized to accept simultaneously the full-rated load and the battery recharge current.

2. Sizing: Rectifier/charger unit shall be sized for the following two simultaneous operating conditions:

a. Supplying the full rated load current to the inverter.

b. Recharging a fully-discharged battery to 95 percent of rated ampere-hour capacity within ten times the discharge time after normal AC power is restored, with the input protective device closed.

C. Inverter Unit: Inverter unit shall be a solid-state device capable of accepting power from the DC bus and providing AC power within specified limits.

1. Output Overload: The inverter shall be able to sustain an overload as specified across its output terminals.

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 6

2. Synchronism: The inverter shall normally operate in phase-lock and synchronism with the bypass source.

3. Modular Construction: Each control logic printed circuit board shall be electrically and physically packaged on an individual plug-in module with separate indication and adjustments.

4. Output Circuit Breaker: The output circuit breaker shall be capable of shunt tripping and shall have interrupting capacity as specified.

Circuit breaker shall have provision for locking in the "off" position.D. External Protection: Lighting Inverter module shall have built-in self-protection against under voltage, overvoltage, overcurrent and surges introduced on the AC input source and/or the bypass source. The system shall sustain input surges without damage in accordance with IEEE C62.41.1 and IEEE C62.41.2. The lighting inverter shall also have built-in self-protection against overvoltage and voltage surges introduced at the output terminals by paralleled sources, load switching, or circuit breaker operation in the critical load distribution system.

E. Internal Protection: Lighting inverter module shall be self-protected against overcurrent, sudden changes in output load and short circuits at the output terminals. Module shall be provided with output reverse power detection which shall cause that module to be disconnected from the critical load bus when output reverse power is present. Lighting

Inverter module shall have built-in protection against permanent damage to itself and the connected load for predictable types of failure within itself and the connected load. At the end of battery discharge limit, the module shall shut down without damage to internal components.

2.3 BATTERY SYSTEM

A. General: A storage battery with sufficient ampere-hour rating to maintain unit output at full capacity for the specified duration shall be provided for each unit module.

B. Battery Type: Lead calcium.

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 7

C. Battery Construction: The battery shall be of the valve-regulated, sealed, non-gassing, recombinant type.

D. Battery Cabinet: The batteries shall be furnished in a battery cabinet matching the Lighting Inverter. The battery cabinet shall be provided with smoke and high temperature alarms.

E. Battery Cables: Battery-to-battery connections shall be stranded cable with proper cable supports.

F. Battery Disconnect: Each battery cabinet or rack shall have a fused disconnect switch or circuit breaker, lockable in the “off” position, provided in a NEMA 1 enclosure.

PART 3 - EXECUTION

3.1 INSTALLATION

A. The Lighting Inverter shall be set in place, wired, and connected in accordance with the approved shop drawings and manufacturer's instructions.

3.2 ACCEPTANCE CHECKS AND TESTS

A. An authorized representative of the manufacturer shall technically supervise and participate during all of the field adjustments and tests. Major adjustments and field tests shall be witnessed by the COR.

The manufacturer’s representative shall certify in writing that the equipment has been installed, adjusted, and tested in accordance with the manufacturer’s recommendations.

B. Perform manufacturer’s required field tests in accordance with the manufacturer's recommendations. In addition, include the following:

1. Visual Inspection and Tests:

a. Compare equipment nameplate data with specifications and approved shop drawings.

b. Inspect physical, electrical, and mechanical condition.

c. Verify appropriate anchorage, required area clearances, and correct alignment.

d. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method, or performing thermographic survey after energization.

e. Verify grounding connections.

f. Vacuum-clean enclosure interior. Clean enclosure exterior.

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 8

g. Verify the correct operation of all alarms and indicating devices.

h. Attach a phase rotation meter to the unit input, output, and bypass buses, and observe proper phase sequences.

i. Check and test controls for proper operation.

j. Check doors for proper alignment and operation.

k. Check and test each protective device for proper mechanical and electrical operation.

2. Load Test: The Lighting Inverter shall be load tested for a continuous 24 hour period by means of resistive load banks, sized for full rated output load and provided by the manufacturer. The unit shall be continuously tested at 1/2 load for 8 hours, 3/4 load for 8 hours and full load for 8 hours. If a failure occurs during the burn-in period, the tests shall be repeated. Instrument readings shall be recorded every half hour for the following:

a. Input voltage and current (all three phases, for each module).

b. Input and output frequency.

c. Battery voltage for each module.

d. Output voltage and current (all three phases, for each module).

e. Output kilowatts for each module.

f. Output voltage and current (all three phases).

g. Output kilowatts.

3. Full Load Burn in Test: The unit shall undergo an additional full load burn-in period of 24 continuous hours by means of resistive load banks, sized for full rated output load and provided by the manufacturer. If a failure occurs during the burn-in period, the tests shall be repeated. Instrument readings shall be recorded every half hour as above. The following tests shall be performed:

a. With the Lighting Inverter carrying full rated output load and supplied from the normal source, switch 50 percent of load bank capacity on and off a minimum of five times within the burn-in period.

4. Battery Discharge and Recharge Test: With the battery fully charged, the Lighting Inverter shall undergo a complete battery discharge test to full depletion followed by a full recharge.

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

26 33 53 - 9

Instrument readings shall be recorded every minute during discharge for the following:

a. Battery voltage and current for each module.

b. Output voltage and current (all three phases) for each module.

c. Output kilowatts for each module.

d. Output voltage and current (all three phases).

e. Output kilowatts (system).

f. Output frequency.

3.3 FOLLOW-UP VERIFICATION

A. After completion of acceptance checks and tests, the Contractor shall show by demonstration in service that the unit is in good operating condition and properly performing the intended function.

3.4 ONE LINE DIAGRAM AND SEQUENCE OF OPERATION

A. At final inspection, an as-built one line diagram shall be laminated or mounted under acrylic glass, and installed in a frame mounted near the

Lighting Inverter.

B. Furnish a written sequence of operation for the unit and connected line side/load side electrical distribution equipment. The sequence of operation shall be laminated or mounted under acrylic glass and installed in a frame mounted near the Lighting Inverter.

C. Deliver an additional four copies of the as-built one line diagram and sequence of operation to the COR.

3.5 INSTRUCTION

A. Furnish the services of a factory-trained technician for one 4-hour training period for instructing personnel in the maintenance and operation of the Lighting Inverter, on the dates requested by the COR.

- - - E N D - - -

File details come from the government source that posted it.