About this file

36C25219B0038 0003 000110 - Table of Contents.pdf

View the file

Other files for this federal contract opportunity

Other files attached to 556-305, Construct New Parking Garage, newest first.
File Type Posted
36C25219B0038-0007001.pdf PDF
36C25219B0038-0007000.docx DOCX document
36C25219B0038-0006000.docx DOCX document
36C25219B0038-0005000.docx DOCX document
36C25219B0038-0005001.pdf PDF
36C25219B0038-0005002.pdf PDF
36C25219B0038-0004000.docx DOCX document
36C25219B0038-0003005.pdf PDF
36C25219B0038-0003008.pdf PDF
36C25219B0038-0003002.pdf PDF
36C25219B0038-0003004.pdf PDF
36C25219B0038-0003006.pdf PDF
36C25219B0038-0003009.pdf PDF
36C25219B0038-0003010.pdf PDF
36C25219B0038-0003000.docx DOCX document
36C25219B0038-0003007.pdf PDF
36C25219B0038-0003003.pdf PDF
36C25219B0038-0002000.docx DOCX document
36C25219B0038-0001001.pdf PDF
36C25219B0038-0001000.docx DOCX document
36C25219B0038-003.pdf PDF
36C25219B0038-005.pdf PDF
36C25219B0038-004.pdf PDF
36C25219B0038-001.docx DOCX document
36C25219B0038-006.pdf PDF
36C25219B0038-002.pdf PDF
36C25219B0038-000.docx DOCX document
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construct New Parking Garage Bid Document Captain James A. Lovell (Amendment A00002) Federal Health Care Center Project No. 556-305

Revised April 17, 2019

00 01 10 - 1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 00 Certification Page 00 01 15 List of Drawing Sheets 07-15 00 31 32 Geotechnical Engineering Report 00 31 33 Soil Sampling and Laboratory Analysis Report 00 31 34 Limited Asbestos Assessment, Building 133 00 31 35 Limited Asbestos Assessment, Building 134

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 10-17 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13 01 33 00 Submittal Procedures 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 00 Quality Control 01-18 01 45 29 Testing Laboratory and Special Inspection Services 08-17 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17 02 82 13.31 Asbestos Transite Abatement 09-15

DIVISION 03 – CONCRETE

03 11 00 Concrete Formwork 03 15 00 Concrete Accessories 03 20 00 Concrete Reinforcement 03 30 00 Cast-in-Place Concrete 12-15 03 41 33 Precast Structural Pretension Concrete 07-11 03 45 00 Precast Architectural Concrete 10-15

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 02-16 04 20 00 Unit Masonry 08-17

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

00 01 10 - 2

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 02-16 05 31 00 Steel Decking 02-16 05 50 00 Metal Fabrications 07-14 05 70 00 Wire Metal Mesh

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 18 16 Traffic Coatings 07 19 16 Silane Water Repellents 07 21 13 Thermal Insulation 10-17 07 22 00 Roof and Deck Insulation 02-16 07 40 00 Roofing and Siding Panels 10-15 07 51 00 Built-Up Bituminous Roofing 07-14 07 60 00 Flashing and Sheet Metal 07-14 07 71 00 Roof Specialties 10-15 07 72 00 Roof Accessories 10-15 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Cover Assemblies 02-16

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 08-16 08 36 13 Sectional Doors 05-15 08 41 13 Aluminum-Framed Entrances and Storefronts 08-16 08 71 00 Door Hardware 01-16 08 71 13 Automatic Door Operators 02-16 08 80 00 Glazing 10-15

DIVISION 09 – FINISHES

09 06 00 Schedule for Finishes 04-15 09 30 13 Ceramic/Porcelain Tiling 09-15 09 91 00 Painting 01-16

DIVISION 10 – SPECIALTIES

10 14 00 Signage 10-15 10 44 13 Fire Extinguisher Cabinets 08-14

DIVISION 14– CONVEYING EQUIPMENT

14 21 00 Electric Traction Elevator 09-17

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

00 01 10 - 3

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 05 12 General Motor Requirements for Plumbing Equipment 09-15 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 14 00 Facility Storm Drainage 22 14 29 Sump Pumps 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17 23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment 02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15 23 07 11 HVAC and Boiler Plant Insulation 23 09 23 Direct-Digital Control System for HVAC 09-11 23 23 00 Refrigerant Piping 02-15 23 31 00 HVAC Ducts and Casings 03-13 23 34 00 HVAC Fans 02-15 23 37 00 Air Outlets and Inlets 02-15 23 81 00 Decentralized Unitary HVAC Equipment 02-11 23 82 00 Convection Heating and Cooling Units 04-11

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 13 Medium-Voltage Cables 01-17 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 05-14 26 05 41 Underground Electrical Construction 01-17 26 09 23 Lighting Controls 05-14 26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 12-15 26 22 00 Low-Voltage Transformers 12-15 26 24 16 Panelboards 05-14 26 27 26 Wiring Devices 01-16 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 33 53 Static Uninterruptible Power Supply / Central Lighting

Inverter 01-17

26 43 13 Surge Protective Devices 01-17 26 51 00 Interior Lighting 08-14 26 56 00 Exterior Lighting 05-14

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 06-15 27 05 26 Grounding and Bonding for Communications Systems 06-15

Federal Health Care Center Project No. 556-305

Revised April 17, 2019

00 01 10 - 4

27 05 33 Raceways and Boxes for Communications Systems 06-15 27 08 00 Commissioning of Communications Systems 11-16 27 10 00 Control, Communication and Signal Wiring 06-15 27 11 00 Telecommunication Room Fittings 06-15 27 15 00 Communications Structured Cabling 01-16

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 09-11 28 05 13 Conductors and Cables for Electronic Safety and

Security 09-11

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16 28 13 00 Physical Access Control System 28 23 00 Video Surveillance 09-11 28 26 00 Electronic Personal Protection System 09-11 28 31 00 Elevator Recall, Fire Detection and Alarm 10-11 28 52 31 Emergency Call System 06-15

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 07-16

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 17 23 Pavement Markings 08-16 32 31 19 Ornamental Metal Fence 32 90 00 Planting 08-16

DIVISION 33 – UTILITIES

33 10 00 Water Utilities 03-17 33 40 00 Storm Sewer Utilities 10-11 33 46 13 Foundation Drainage 10-11