Attachment 14 - Addendum-01_Phase-3B_Drawing_G002_Phasing-Plan.pdf

PDF 452 KB Posted

Attached to
HVAC Repair Phase 2B, 3A, 3B Federal contract opportunity
Solicitation number
1232SA26Q0056
Issued by
Department of Agriculture Agricultural Research Service

About this file

This is a General Notes page from a construction contract document for a USDA facility renovation project that includes a phasing plan with construction sequencing requirements. The document establishes critical operational requirements for work conducted within an occupied federal building where non-work areas remain operational throughout the renovation.

The contractor must maintain building occupancy and operations in all non-work areas and coordinate all activities with the Contracting Officer to prevent conflicts with facility operations. Key requirements include: erecting barriers and protective measures for personnel safety; covering and protecting furnishings and equipment; providing barriers and signage for wayfinding and building occupant safety; submitting a work plan before commencing work; field-verifying all dimensions and conditions; and coordinating staging areas with USDA personnel. The contractor must complete all dimension verification before work begins. Construction must follow a mandatory phasing sequence of Phase 2A → Phase 2B Sequence 1 → Phase 2B Sequence 2 → Phase 3A → Phase 3B, with no deviation permitted without prior written Contracting Officer approval. All work associated with a given phase must be completed, including testing, restoration, and acceptance, before any subsequent phase begins. The contractor is responsible for removing and reinstalling light fixtures to accommodate hydronic heating equipment and piping work, protecting fire alarm and sprinkler systems daily from dust and debris with temporary coverings that must be removed each workday and when the facility is unattended for more than four hours. Any damage to existing fire alarm, suppression systems, or other building components resulting from construction activities must be repaired or replaced by the contractor at no additional cost to the government, with all systems restored to full operational status prior to reoccupancy.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PHASE 3B

AREA OF

WORK

PHASE 1A, 1B AND 1C (NOT IN CONTRACT):

PHASE 2A (NOT IN CONTRACT)

PHASE 2B SEQUENCE 2 (NOT IN CONTRACT)

PHASE 3A (NOT IN CONTRACT)

PHASE 3B

PHASE 2B SEQUENCE 1

(NOT IN CONTRACT)

PHASING LEGEND

A. ALL NON-WORK AREAS IN THE BUILDING WILL REMAIN OCCUPIED AND OPERATIONAL

DURING THE WORK. USDA WILL VACATE AREAS OF THE BUILDING WHERE WORK IS

BEING PERFORMED. THE CONTRACTOR MUST COORDINATE HIS/HER WORK

ACTIVITIES WITH THE CONTRACTING OFFICER TO AVOID CONFLICTS WITH FACILITY

OPERATIONS. THE CONTRACTOR MUST ERECT BARRIERS AND EMPLOY NECESSARY

MEASURES TO PROTECT PERSONNEL IN THE AREA FROM INJURY.

B. COVER AND PROTECT ALL FURNISHINGS AND EQUIPMENT REMAINING IN THE

SPACES.

C. THE CONTRACTOR MUST PROVIDE BARRIERS AND SIGNAGE TO SECURE THE WORK

AREAS, TO DIRECT PERSONNEL IN WAYFINDING, AND TO ENSURE THE SAFETY OF

BUILDING OCCUPANTS AND VISITORS. THE CONTRACTOR MUST PROVIDE A WORK

PLAN BEFORE BEGINNING THE WORK EXPLAINING AND ILLUSTRATING THE MEANS TO

BE IMPLEMENTED TO ALLOW THE BUILDING TO REMAIN OCCUPIED AND OPERATIONAL

DURING THE WORK. THE CONTRACTOR MUST FIELD VERIFY ALL DIMENSION AND

CONDITIONS BEFORE BEGINNING WORK.

D. CONTRACTOR MUST COORDINATE STAGING AREAS WITH USDA PERSONNEL.

E. THE HATCHED “AREA OF WORK” SHOWN ON THE PHASING PLAN INDICATES THE

PRIMARY RENOVATION LIMITS FOR EACH PHASE. WORK REQUIRED BY THE DRAWINGS

AND SPECIFICATIONS MAY EXTEND INTO ADJACENT AREAS OUTSIDE OF THE

HATCHED LIMITS (INCLUDING WORK ABOVE CEILINGS SUCH AS DUCTWORK, PIPING,

AND ASSOCIATED SYSTEMS). WHERE ACCESS IS REQUIRED IN THESE ADJACENT

AREAS, THE CONTRACTOR SHALL REMOVE AND REINSTALL CEILINGS AND FINISHES

AS NECESSARY TO PERFORM THE WORK AND SHALL RESTORE ALL AFFECTED AREAS

TO MATCH EXISTING CONDITIONS. ALL WORK INDICATED IN THE CONTRACT

DOCUMENTS SHALL BE INCLUDED IN THE SCOPE OF THE RESPECTIVE PHASE

REGARDLESS OF WHETHER IT OCCURS STRICTLY WITHIN THE HATCHED AREA.

F. THE CONTRACTOR MUST COMPLETE ALL WORK ASSOCIATED WITH A GIVEN PHASE

PRIOR TO COMMENCEMENT OF WORK IN ANY SUBSEQUENT PHASE. WORK FOR A

NEW PHASE MUST NOT BEGIN UNTIL ALL WORK, TESTING, RESTORATION, AND

ACCEPTANCE REQUIREMENTS OF THE PREVIOUS PHASE ARE COMPLETE. THE

REQUIRED ORDER OF CONSTRUCTION PHASING MUST BE AS FOLLOWS:

PHASE 2A → PHASE 2B SEQUENCE 1→ PHASE 2B SEQUENCE 2→ PHASE 3A → PHASE 3B

G. DEVIATION FROM THE ESTABLISHED PHASING SEQUENCE MUST NOT OCCUR

WITHOUT PRIOR WRITTEN APPROVAL FROM THE CONTRACTING OFFICER.

H. CONTRACTOR MUST REMOVE AND RETAIN LIGHT FIXTURES (NOT SHOWN DRAWING)

AS REQUIRED TO ACCOMMODATE THE REMOVAL AND REPLACEMENT OF HYDRONIC

HEATING EQUIPMENT AND PIPING INSULATION AS SHOWN ON THE MECHANICAL

DRAWINGS. CONTRACTOR MUST DISCONNECT AND SAFELY TERMINATE ALL CONDUIT

AND WIRING WITH APPROVED WIRE NUTS AND ELECTRICAL TAPE. FIXTURES MUST BE

PROTECTED FROM DAMAGE AND STORED FOR REINSTALLATION. UPON COMPLETION

OF PIPING AND INSULATION WORK, CONTRACTOR MUST REINSTALL ALL FIXTURES IN

ORIGINAL LOCATIONS AND VERIFY PROPER OPERATION. ANY FIXTURES OR

ASSOCIATED COMPONENTS DAMAGED DURING THIS WORK MUST BE REPAIRED OR

REPLACED IN KIND AT NO COST TO THE GOVERNMENT.

I. PRIOR TO THE START OF WORK EACH DAY IN ACTIVE CONSTRUCTION AREAS, THE

CONTRACTOR MUST TEMPORARILY PROTECT FIRE ALARM INITIATING AND

NOTIFICATION DEVICES AS WELL AS SPRINKLER HEADS (NOT SHOWN ON DRAWING)

FROM DUST, DEBRIS, AND DAMAGE USING APPROVED METHODS. ALL TEMPORARY

COVERINGS MUST BE REMOVED AT THE END OF EACH WORKDAY AND AT ANY TIME

THE FACILITY WILL BE LEFT UNATTENDED FOR MORE THAN FOUR (4) HOURS. FIRE

ALARM DEVICES AND SPRINKLERS IN OCCUPIED AREAS MUST NOT BE COVERED,

DISABLED, OR OBSTRUCTED. ANY DAMAGE TO EXISTING FIRE ALARM OR

SUPPRESSION SYSTEM COMPONENTS RESULTING FROM CONSTRUCTION ACTIVITIES

MUST BE REPAIRED OR REPLACED IN KIND BY THE CONTRACTOR AT NO ADDITIONAL

COST TO THE OWNER, AND THE SYSTEM MUST BE RESTORED TO FULL OPERATIONAL

STATUS PRIOR TO REOCCUPANCY OF AFFECTED SPACES.

GENERAL NOTES

Dylan Mitchell sam

Sheets and Views
G002-2B-G-002-2B
G002-3A-G-002-3A
G002-3B-G-002-3B
A-103-E-111-2A
MD104-MD104
MP102-MP102
M-603-M-603

File details come from the government source that posted it. Updated .