Attachment 14 - Addendum-01_Phase-3B_Drawing_G002_Phasing-Plan.pdf
PDF 452 KB Posted
- Attached to
- HVAC Repair Phase 2B, 3A, 3B Federal contract opportunity
- Solicitation number
- 1232SA26Q0056
About this file
This is a General Notes page from a construction contract document for a USDA facility renovation project that includes a phasing plan with construction sequencing requirements. The document establishes critical operational requirements for work conducted within an occupied federal building where non-work areas remain operational throughout the renovation.
The contractor must maintain building occupancy and operations in all non-work areas and coordinate all activities with the Contracting Officer to prevent conflicts with facility operations. Key requirements include: erecting barriers and protective measures for personnel safety; covering and protecting furnishings and equipment; providing barriers and signage for wayfinding and building occupant safety; submitting a work plan before commencing work; field-verifying all dimensions and conditions; and coordinating staging areas with USDA personnel. The contractor must complete all dimension verification before work begins. Construction must follow a mandatory phasing sequence of Phase 2A → Phase 2B Sequence 1 → Phase 2B Sequence 2 → Phase 3A → Phase 3B, with no deviation permitted without prior written Contracting Officer approval. All work associated with a given phase must be completed, including testing, restoration, and acceptance, before any subsequent phase begins. The contractor is responsible for removing and reinstalling light fixtures to accommodate hydronic heating equipment and piping work, protecting fire alarm and sprinkler systems daily from dust and debris with temporary coverings that must be removed each workday and when the facility is unattended for more than four hours. Any damage to existing fire alarm, suppression systems, or other building components resulting from construction activities must be repaired or replaced by the contractor at no additional cost to the government, with all systems restored to full operational status prior to reoccupancy.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PHASE 3B
AREA OF
WORK
PHASE 1A, 1B AND 1C (NOT IN CONTRACT):
PHASE 2A (NOT IN CONTRACT)
PHASE 2B SEQUENCE 2 (NOT IN CONTRACT)
PHASE 3A (NOT IN CONTRACT)
PHASE 3B
PHASE 2B SEQUENCE 1
(NOT IN CONTRACT)
PHASING LEGEND
A. ALL NON-WORK AREAS IN THE BUILDING WILL REMAIN OCCUPIED AND OPERATIONAL
DURING THE WORK. USDA WILL VACATE AREAS OF THE BUILDING WHERE WORK IS
BEING PERFORMED. THE CONTRACTOR MUST COORDINATE HIS/HER WORK
ACTIVITIES WITH THE CONTRACTING OFFICER TO AVOID CONFLICTS WITH FACILITY
OPERATIONS. THE CONTRACTOR MUST ERECT BARRIERS AND EMPLOY NECESSARY
MEASURES TO PROTECT PERSONNEL IN THE AREA FROM INJURY.
B. COVER AND PROTECT ALL FURNISHINGS AND EQUIPMENT REMAINING IN THE
SPACES.
C. THE CONTRACTOR MUST PROVIDE BARRIERS AND SIGNAGE TO SECURE THE WORK
AREAS, TO DIRECT PERSONNEL IN WAYFINDING, AND TO ENSURE THE SAFETY OF
BUILDING OCCUPANTS AND VISITORS. THE CONTRACTOR MUST PROVIDE A WORK
PLAN BEFORE BEGINNING THE WORK EXPLAINING AND ILLUSTRATING THE MEANS TO
BE IMPLEMENTED TO ALLOW THE BUILDING TO REMAIN OCCUPIED AND OPERATIONAL
DURING THE WORK. THE CONTRACTOR MUST FIELD VERIFY ALL DIMENSION AND
CONDITIONS BEFORE BEGINNING WORK.
D. CONTRACTOR MUST COORDINATE STAGING AREAS WITH USDA PERSONNEL.
E. THE HATCHED “AREA OF WORK” SHOWN ON THE PHASING PLAN INDICATES THE
PRIMARY RENOVATION LIMITS FOR EACH PHASE. WORK REQUIRED BY THE DRAWINGS
AND SPECIFICATIONS MAY EXTEND INTO ADJACENT AREAS OUTSIDE OF THE
HATCHED LIMITS (INCLUDING WORK ABOVE CEILINGS SUCH AS DUCTWORK, PIPING,
AND ASSOCIATED SYSTEMS). WHERE ACCESS IS REQUIRED IN THESE ADJACENT
AREAS, THE CONTRACTOR SHALL REMOVE AND REINSTALL CEILINGS AND FINISHES
AS NECESSARY TO PERFORM THE WORK AND SHALL RESTORE ALL AFFECTED AREAS
TO MATCH EXISTING CONDITIONS. ALL WORK INDICATED IN THE CONTRACT
DOCUMENTS SHALL BE INCLUDED IN THE SCOPE OF THE RESPECTIVE PHASE
REGARDLESS OF WHETHER IT OCCURS STRICTLY WITHIN THE HATCHED AREA.
F. THE CONTRACTOR MUST COMPLETE ALL WORK ASSOCIATED WITH A GIVEN PHASE
PRIOR TO COMMENCEMENT OF WORK IN ANY SUBSEQUENT PHASE. WORK FOR A
NEW PHASE MUST NOT BEGIN UNTIL ALL WORK, TESTING, RESTORATION, AND
ACCEPTANCE REQUIREMENTS OF THE PREVIOUS PHASE ARE COMPLETE. THE
REQUIRED ORDER OF CONSTRUCTION PHASING MUST BE AS FOLLOWS:
PHASE 2A → PHASE 2B SEQUENCE 1→ PHASE 2B SEQUENCE 2→ PHASE 3A → PHASE 3B
G. DEVIATION FROM THE ESTABLISHED PHASING SEQUENCE MUST NOT OCCUR
WITHOUT PRIOR WRITTEN APPROVAL FROM THE CONTRACTING OFFICER.
H. CONTRACTOR MUST REMOVE AND RETAIN LIGHT FIXTURES (NOT SHOWN DRAWING)
AS REQUIRED TO ACCOMMODATE THE REMOVAL AND REPLACEMENT OF HYDRONIC
HEATING EQUIPMENT AND PIPING INSULATION AS SHOWN ON THE MECHANICAL
DRAWINGS. CONTRACTOR MUST DISCONNECT AND SAFELY TERMINATE ALL CONDUIT
AND WIRING WITH APPROVED WIRE NUTS AND ELECTRICAL TAPE. FIXTURES MUST BE
PROTECTED FROM DAMAGE AND STORED FOR REINSTALLATION. UPON COMPLETION
OF PIPING AND INSULATION WORK, CONTRACTOR MUST REINSTALL ALL FIXTURES IN
ORIGINAL LOCATIONS AND VERIFY PROPER OPERATION. ANY FIXTURES OR
ASSOCIATED COMPONENTS DAMAGED DURING THIS WORK MUST BE REPAIRED OR
REPLACED IN KIND AT NO COST TO THE GOVERNMENT.
I. PRIOR TO THE START OF WORK EACH DAY IN ACTIVE CONSTRUCTION AREAS, THE
CONTRACTOR MUST TEMPORARILY PROTECT FIRE ALARM INITIATING AND
NOTIFICATION DEVICES AS WELL AS SPRINKLER HEADS (NOT SHOWN ON DRAWING)
FROM DUST, DEBRIS, AND DAMAGE USING APPROVED METHODS. ALL TEMPORARY
COVERINGS MUST BE REMOVED AT THE END OF EACH WORKDAY AND AT ANY TIME
THE FACILITY WILL BE LEFT UNATTENDED FOR MORE THAN FOUR (4) HOURS. FIRE
ALARM DEVICES AND SPRINKLERS IN OCCUPIED AREAS MUST NOT BE COVERED,
DISABLED, OR OBSTRUCTED. ANY DAMAGE TO EXISTING FIRE ALARM OR
SUPPRESSION SYSTEM COMPONENTS RESULTING FROM CONSTRUCTION ACTIVITIES
MUST BE REPAIRED OR REPLACED IN KIND BY THE CONTRACTOR AT NO ADDITIONAL
COST TO THE OWNER, AND THE SYSTEM MUST BE RESTORED TO FULL OPERATIONAL
STATUS PRIOR TO REOCCUPANCY OF AFFECTED SPACES.
GENERAL NOTES
Dylan Mitchell sam
| Sheets and Views |
| G002-2B-G-002-2B |
| G002-3A-G-002-3A |
| G002-3B-G-002-3B |
| A-103-E-111-2A |
| MD104-MD104 |
| MP102-MP102 |
| M-603-M-603 |
File details come from the government source that posted it. Updated .