Attachment 12 - Addendum-01_Phase-2B_Drawings_Combined.pdf
PDF 2 MB Posted
- Attached to
- HVAC Repair Phase 2B, 3A, 3B Federal contract opportunity
- Solicitation number
- 1232SA26Q0056
About this file
This document is a set of contract specifications and construction drawings for USDA facility renovation work focusing on Phase 2B headhouse mechanical and piping systems. The work involves removal and replacement of hydronic heating equipment, including hot water reheat coils and VAV (variable air volume) boxes, along with associated piping, insulation, and controls. The contractor must provide insulation on all new and existing piping within the work areas on chilled water supply/return, heating water supply/return systems, and maintain the building heating water system in operation throughout construction.
The contractor is required to coordinate all activities with the USDA contracting officer, maintain building occupancy in non-work areas, erect protective barriers and signage, provide a detailed work plan before commencing, and field-verify all existing conditions. Construction must proceed in strict phasing sequence: Phase 2A, Phase 2B Sequence 1, Phase 2B Sequence 2, Phase 3A, and Phase 3B, with each phase requiring complete work acceptance before the next phase begins. The contractor must protect existing light fixtures, fire alarm devices, and sprinkler heads from damage, temporarily covering them daily and removing coverings at end of workday or when the facility is unattended for more than four hours. All damaged systems, equipment, or components must be repaired or replaced at no cost to the government. Test and balance requirements apply to all heating coils and VAV boxes, and mechanical cleaning of the HVAC system must meet NADCA standards.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PHASE 1A, 1B AND 1C (NOT IN CONTRACT):
PHASE 2A (NOT IN CONTRACT)
PHASE 2B SEQUENCE 2 (MAIN LAB BUILDING)
PHASE 3A (NOT IN CONTRACT)
PHASE 3B (NOT IN CONTRACT)
PHASE 2B SEQUENCE 1
(HEADHOUSE AND TWO GREENHOUSES)
PHASING LEGEND
A. ALL NON-WORK AREAS IN THE BUILDING WILL REMAIN OCCUPIED AND OPERATIONAL
DURING THE WORK. USDA WILL VACATE AREAS OF THE BUILDING WHERE WORK IS
BEING PERFORMED. THE CONTRACTOR MUST COORDINATE HIS/HER WORK
ACTIVITIES WITH THE CONTRACTING OFFICER TO AVOID CONFLICTS WITH FACILITY
OPERATIONS. THE CONTRACTOR MUST ERECT BARRIERS AND EMPLOY NECESSARY
MEASURES TO PROTECT PERSONNEL IN THE AREA FROM INJURY.
B. COVER AND PROTECT ALL FURNISHINGS AND EQUIPMENT REMAINING IN THE
SPACES.
C. THE CONTRACTOR MUST PROVIDE BARRIERS AND SIGNAGE TO SECURE THE WORK
AREAS, TO DIRECT PERSONNEL IN WAYFINDING, AND TO ENSURE THE SAFETY OF
BUILDING OCCUPANTS AND VISITORS. THE CONTRACTOR MUST PROVIDE A WORK
PLAN BEFORE BEGINNING THE WORK EXPLAINING AND ILLUSTRATING THE MEANS TO
BE IMPLEMENTED TO ALLOW THE BUILDING TO REMAIN OCCUPIED AND OPERATIONAL
DURING THE WORK. THE CONTRACTOR MUST FIELD VERIFY ALL DIMENSION AND
CONDITIONS BEFORE BEGINNING WORK.
D. CONTRACTOR MUST COORDINATE STAGING AREAS WITH USDA PERSONNEL.
E. THE HATCHED “AREA OF WORK” SHOWN ON THE PHASING PLAN INDICATES THE
PRIMARY RENOVATION LIMITS FOR EACH PHASE. WORK REQUIRED BY THE DRAWINGS
AND SPECIFICATIONS MAY EXTEND INTO ADJACENT AREAS OUTSIDE OF THE
HATCHED LIMITS (INCLUDING WORK ABOVE CEILINGS SUCH AS DUCTWORK, PIPING,
AND ASSOCIATED SYSTEMS). WHERE ACCESS IS REQUIRED IN THESE ADJACENT
AREAS, THE CONTRACTOR SHALL REMOVE AND REINSTALL CEILINGS AND FINISHES
AS NECESSARY TO PERFORM THE WORK AND SHALL RESTORE ALL AFFECTED AREAS
TO MATCH EXISTING CONDITIONS. ALL WORK INDICATED IN THE CONTRACT
DOCUMENTS SHALL BE INCLUDED IN THE SCOPE OF THE RESPECTIVE PHASE
REGARDLESS OF WHETHER IT OCCURS STRICTLY WITHIN THE HATCHED AREA.
F. THE CONTRACTOR MUST COMPLETE ALL WORK ASSOCIATED WITH A GIVEN PHASE
PRIOR TO COMMENCEMENT OF WORK IN ANY SUBSEQUENT PHASE. WORK FOR A
NEW PHASE MUST NOT BEGIN UNTIL ALL WORK, TESTING, RESTORATION, AND
ACCEPTANCE REQUIREMENTS OF THE PREVIOUS PHASE ARE COMPLETE (NOTE:
PHASE 2B SEQUENCE 1 MAY BE CONSTRUCTED CONCURRENTLY WITH PHASE 2A.
PHASE 2B SEQUENCE 2 MAY BE CONSTRUCTED CONCURRENTLY WITH PHASE 2B
SEQUENCE 1. PHASE 2B SEQUENCE 2 MUST NOT COMMENCE UNTIL PHASE 2A IS
COMPLETED). THE REQUIRED ORDER OF CONSTRUCTION PHASING MUST BE AS
FOLLOWS:
PHASE 2A → PHASE 2B SEQUENCE 1→ PHASE 2B SEQUENCE 2→ PHASE 3A → PHASE 3B
G. DEVIATION FROM THE ESTABLISHED PHASING SEQUENCE MUST NOT OCCUR
WITHOUT PRIOR WRITTEN APPROVAL FROM THE CONTRACTING OFFICER.
H. CONTRACTOR MUST REMOVE AND RETAIN LIGHT FIXTURES (NOT SHOWN DRAWING)
AS REQUIRED TO ACCOMMODATE THE REMOVAL AND REPLACEMENT OF HYDRONIC
HEATING EQUIPMENT AND PIPING INSULATION AS SHOWN ON THE MECHANICAL
DRAWINGS. CONTRACTOR MUST DISCONNECT AND SAFELY TERMINATE ALL CONDUIT
AND WIRING WITH APPROVED WIRE NUTS AND ELECTRICAL TAPE. FIXTURES MUST BE
PROTECTED FROM DAMAGE AND STORED FOR REINSTALLATION. UPON COMPLETION
OF PIPING AND INSULATION WORK, CONTRACTOR MUST REINSTALL ALL FIXTURES IN
ORIGINAL LOCATIONS AND VERIFY PROPER OPERATION. ANY FIXTURES OR
ASSOCIATED COMPONENTS DAMAGED DURING THIS WORK MUST BE REPAIRED OR
REPLACED IN KIND AT NO COST TO THE GOVERNMENT.
I. PRIOR TO THE START OF WORK EACH DAY IN ACTIVE CONSTRUCTION AREAS, THE
CONTRACTOR MUST TEMPORARILY PROTECT FIRE ALARM INITIATING AND
NOTIFICATION DEVICES AS WELL AS SPRINKLER HEADS (NOT SHOWN ON DRAWING)
FROM DUST, DEBRIS, AND DAMAGE USING APPROVED METHODS. ALL TEMPORARY
COVERINGS MUST BE REMOVED AT THE END OF EACH WORKDAY AND AT ANY TIME
THE FACILITY WILL BE LEFT UNATTENDED FOR MORE THAN FOUR (4) HOURS. FIRE
ALARM DEVICES AND SPRINKLERS IN OCCUPIED AREAS MUST NOT BE COVERED,
DISABLED, OR OBSTRUCTED. ANY DAMAGE TO EXISTING FIRE ALARM OR
SUPPRESSION SYSTEM COMPONENTS RESULTING FROM CONSTRUCTION ACTIVITIES
MUST BE REPAIRED OR REPLACED IN KIND BY THE CONTRACTOR AT NO ADDITIONAL
COST TO THE OWNER, AND THE SYSTEM MUST BE RESTORED TO FULL OPERATIONAL
STATUS PRIOR TO REOCCUPANCY OF AFFECTED SPACES.
GENERAL NOTES
PHASE 2B SEQUENCE 2
AREA OF WORK
PHASE 2B SEQUENCE 1
AREA OF WORK
Dylan Mitchell sam
HL-1
HL-3
HL-5
HL-6
HL-4
0 4' 8' 16'
SCALE: 3/16"= 1'-0"
2'
SCALE:
PHASE 2B HEADHOUSE
REFLECTED CEILING PLAN
3/16" = 1'-0"
A-103
KEY PLAN
N.T.S.
NORTH
AREA OF WORK PHASE 2B
SEQUENCE 1
LEGEND
CONTRACTOR MUST REMOVE EXISTING 24" x 24" SUSPENDED CEILING TILE AND GRID COMPLETE. RETAIN EXISTING HANGER WIRES FOR REUSE. INSTALL NEW 24" x 24" IN SAME PATTERN AND LOCATION AS EXISTING.
CONTRACTOR MUST REMOVE EXISTING GYPSUM BOARD CEILING SYSTEM AS REQUIRED TO COMPLETE
MECHANICAL WORK. COORDINATE WORK WITH MECHANICAL WORK.
CONTRACTOR MUST REMOVE EXISTING 24" x 48" SUSPENDED CEILING TILE AND GRID COMPLETE. RETAIN EXISTING HANGER WIRES FOR REUSE. INSTALL NEW 24" x 48" IN SAME PATTERN AND LOCATION AS EXISTING.
GENERAL NOTES
1. CONTRACTOR MUST REMOVE AND RETAIN LIGHT FIXTURES
(NOT SHOWN DRAWING) AS REQUIRED TO ACCOMMODATE THE
REMOVAL AND REPLACEMENT OF HYDRONIC HEATING
EQUIPMENT AND PIPING INSULATION AS SHOWN ON THE
MECHANICAL DRAWINGS. CONTRACTOR MUST DISCONNECT
AND SAFELY TERMINATE ALL CONDUIT AND WIRING WITH
APPROVED WIRE NUTS AND ELECTRICAL TAPE. FIXTURES
MUST BE PROTECTED FROM DAMAGE AND STORED FOR
REINSTALLATION. UPON COMPLETION OF PIPING AND
INSULATION WORK, CONTRACTOR MUST REINSTALL ALL
FIXTURES IN ORIGINAL LOCATIONS AND VERIFY PROPER
OPERATION. ANY FIXTURES OR ASSOCIATED COMPONENTS
DAMAGED DURING THIS WORK MUST BE REPAIRED OR
REPLACED IN KIND AT NO COST TO THE GOVERNMENT.
2. PRIOR TO THE START OF WORK EACH DAY IN ACTIVE
CONSTRUCTION AREAS, THE CONTRACTOR MUST
TEMPORARILY PROTECT FIRE ALARM INITIATING AND
NOTIFICATION DEVICES AS WELL AS SPRINKLER HEADS (NOT
SHOWN ON DRAWING) FROM DUST, DEBRIS, AND DAMAGE
USING APPROVED METHODS. ALL TEMPORARY COVERINGS
MUST BE REMOVED AT THE END OF EACH WORKDAY AND AT
ANY TIME THE FACILITY WILL BE LEFT UNATTENDED FOR MORE
THAN FOUR (4) HOURS. FIRE ALARM DEVICES AND SPRINKLERS
IN OCCUPIED AREAS MUST NOT BE COVERED, DISABLED, OR
OBSTRUCTED. ANY DAMAGE TO EXISTING FIRE ALARM OR
SUPPRESSION SYSTEM COMPONENTS RESULTING FROM
CONSTRUCTION ACTIVITIES MUST BE REPAIRED OR REPLACED
IN KIND BY THE CONTRACTOR AT NO ADDITIONAL COST TO
THE OWNER, AND THE SYSTEM MUST BE RESTORED TO FULL
OPERATIONAL STATUS PRIOR TO REOCCUPANCY OF
AFFECTED SPACES.
robin
SCALE:
HEADHOUSE MECHANICAL
PIPING DEMOLITION PLAN
3/16" = 1'-0"
MD104
0 4' 8' 16'
SCALE: 3/16"= 1'-0"
2'
1. DEMOLISH EXISTING HOT WATER REHEAT COIL,
CONTROL VALVES, CONTROLS, AND ALL
APPURTENANCES. DEMOLISH EXISTING PIPING
AND INSULATION BACK TO EXISTING ISOLATION
VALVES AND PLUG.
2. DEMOLISH EXISTING HOT WATER VAV BOX,
CONTROL VALVES, CONTROLS, AND ALL
APPURTENANCES. DEMOLISH EXISTING PIPING
AND INSULATION BACK TO EXISTING ISOLATION
VALVES AND PLUG.
3. POINT SHOWN IS APPROXIMATE EXTENT OF
WORK ACCORDING TO PHASE. CONTRACTOR
MUST FIELD VERIFY EXTENT OF WORK
COMPLETED IN PREVIOUS PHASE PRIOR TO
BEGINNING OF ANY WORK. THE CONTRACTOR
MUST COMPLETE ALL WORK SHOWN
THROUGHOUT THE DRAWINGS AND
SPECIFICATIONS UP THE EXTENT OF WORK
COMPLETED IN THE PREVIOUS PHASE.
KEYED NOTES
DEMO PIPING
EXISTING PIPING
LEGEND:
CHWR CHILLED WATER RETURN
CHWS CHILLED WATER SUPPLY
COND. CONDENSATE
HWR HEATING WATER RETURN
HWS HEATING WATER SUPPLY
VTR VENT THROUGH ROOF
POINT OF CONNECTION
EXIST. 4" HWR, 4" STM, 1-1/4"
COND, 8" CHWR, 4" CHWS,
AND 4" HWS TO REMAIN
EXISTING
UNIT HEATER
EXISTING
UNIT HEATER
EXISTING
UNIT HEATER
EXISTING
UNIT HEATER
EXISTING
UNIT HEATER
GENERAL NOTES
1. ALL PIPING UP TO THE ISOLATION VALVE MUST
REMAIN IN PLACE. REMOVE INSULATION FROM
ALL PIPES AND FITTINGS WITHIN THE AREA OF
WORK ON THE FOLLOWING SYSTEMS: CHILLED
WATER SUPPLY, CHILLED WATER RETURN,
HEATING WATER RETURN, AND HEATING
WATER SUPPLY.
2. THE DEMOLITION PLAN AND EXISTING
CONDITIONS ARE APPROXIMATE. CONTRACTOR
MUST FIELD VERIFY EXISTING CONDITIONS.
CONTRACTOR MUST PROTECT ALL EXISTING
HVAC EQUIPMENT, DUCTWORK, DIFFUSERS,
PIPING, VALVES, CONTROLS, INSULATION, ETC.
FROM ANY DAMAGE OR CONTAMINATION
UNLESS NOTED OTHERWISE. OPEN ENDS OF
ALL DUCTWORK AND PIPING MUST BE
COVERED DURING CONSTRUCTION.
EXISTING
CONDENSATE
PUMP1
EXISTING 6" STM, 6"
CHWS, AND 6" CHWR UP
2-1/2"
2"
2-1/2"
3"
3" 3"
2-1/2"
2"
1-1/4"
3"
2"
2"
3"
3"
4"
1"
4"3"
1-1/2"1-1/2"2"
1"
1-1/2"1/2"
1/2"
3/4"
1/2"
1/2"
1-1/4"
1-1/4" 1-1/4" 1-1/4"
3/4"
3/4"
3/4"
3/4"
4"
4"
6" 4"
1/2"
1/2"
2"
6"
1-1/2"
SCALE:
HEADHOUSE MECHANICAL
PIPING NEW WORK PLAN
3/16" = 1'-0"
MP102
0 4' 8' 16'
SCALE: 3/16"= 1'-0"
2'
KEYED NOTES
1. PROVIDE HOT WATER HEATING COIL, 3-WAY
CONTROL VALVE, CONTROLS, AND ALL
APPURTENANCES IN PLACE OF EXISTING.
2. PROVIDE HOT WATER VAV BOX, 3-WAY CONTROL
VALVE, CONTROLS, AND ALL APPURTENANCES IN
PLACE OF EXISTING.
GENERAL NOTES
1. PROVIDE INSULATION ON ALL NEW AND
EXISTING PIPING AND FITTINGS WITHIN THE
AREA OF WORK ON THE FOLLOWING SYSTEMS:
CHILLED WATER RETURN, CHILLED WATER
SUPPLY, HEATING WATER RETURN, HEATER
WATER SUPPLY. BUILDING HEATING WATER
SYSTEM MUST REMAIN IN OPERATION
THROUGHOUT CONSTRUCTION. ANY
DISRUPTION TO THE EXISTING HEATING WATER
SYSTEM MUST BE COORDINATED WITH THE
CONTRACTING OFFICER.
2. CONTRACTOR MUST PROTECT ALL EXISTING
HVAC EQUIPMENT, DUCTWORK, DIFFUSERS,
PIPING, VALVES, CONTROLS, INSULATION, ETC.
FROM ANY DAMAGE OR CONTAMINATION. OPEN
ENDS OF ALL DUCTWORK MUST BE COVERED
DURING CONSTRUCTION. CONTRACTOR MUST
MECHANICALLY CLEAN ENTIRE HVAC SYSTEM IN
WORK AREA TO REMOVE ALL VISIBLE
CONTAMINANTS, SUCH THAT SYSTEMS ARE
CAPABLE OF PASSING NADCA CLEANING
VERIFICATION TESTING STANDARDS ONCE
CONSTRUCTION IS COMPLETE.
3. TEST AND BALANCE HOT WATER COILS, VAV
BOXES AND ALL AFFECTED EXISTING
EQUIPMENT TO MEET SCHEDULES VALUES.
HC-32
HC-33
HC-34
HC-36
HC-37
HC-35
HC-38
HC-39
HC-40
HC-41
HC-42
HC-43
HC-44
VAV 4-1
VAV 4-2
EXISTING
UNIT HEATER
EXISTING
UNIT HEATER
EXISTING
UNIT HEATER
EXISTING
UNIT HEATER
EXISTING
UNIT HEATER
EXISTING
CONDENSATE
PUMP
EXIST. 4" HWR, 4" STM, 1-1/4"
COND, 8" CHWR, 4" CHWS,
AND 4" HWS TO REMAIN
POINT SHOWN IS APPROXIMATE EXTENT OF WORK ACCORDING TO PHASE.
CONTRACTOR MUST FIELD VERIFY EXTENT OF WORK COMPLETED IN PREVIOUS
PHASE PRIOR TO BEGINNING OF ANY WORK. THE CONTRACTOR MUST COMPLETE
ALL WORK SHOWN THROUGHOUT THE DRAWINGS AND SPECIFICATIONS UP THE
EXTENT OF WORK COMPLETED IN THE PREVIOUS PHASE.
EXISTING 6" STM, 6"
CHWS, AND 6" CHWR UP
HEAD HOUSE DUCT MOUNTED HEATING COIL SCHEDULE
BASIS
OF DESIGNMARK SERVES FUNCTION CAPACITY
MBH
AIRFLOW
CFM
COIL DATA
HC-32 MODINE LAB SUPPLY
AIR REHEAT 91.101200
0.270.38
12.82
EAT
°F
HC-33
HC-34
HC-35
HC-36
HC-37
HC-38
HC-39
HC-40
HC-41
HC-42
MODINE
MODINE
MODINE
MODINE
MODINE
MODINE
MODINE
MODINE
MODINE
MODINE
EXISTING
AHU-3
EXISTING
SUP 4-2
EXISTING
SUP 4-20
EXISTING
SUP 4-7
EXISTING
SUP 4-17
EXISTING
SUP 4-8
EXISTING
SUP 4-3
EXISTING
SUP 4-5
EXISTING
SUP 4-19
EXISTING
SUP 4-14
EXISTING
SUP 4-12
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
LAB SUPPLY
AIR REHEAT
MAX APD
IN.WC.
MAX WPD
FT.HD.
0.05 0.47
LAT
°F
100.0
FLOW
GPM
9.1
1.3
EWT
°F
LWT
°F
SIZE
IN
24X12
55 108.7 180 12X9
220 12.82 0.05 0.471.3105.8 180 10X6
285 15.27 0.07 0.621.5104.4 180
295 15.62 0.08 0.651.6103.8 180
330 16.76 0.10 0.731.7101.8 180
380 20.94 0.21 1.052.1105.8 180
350 17.38 0.11 0.771.7100.8 180
505 26.67 0.25 1.592.7103.7 180
720 37.22 0.11 4.103.7102.7 180 18X12
295 103.815.62 0.08 0.681.6
SINGLE DUCT VAV TERMINAL SCHEDULE
BOX TYPEBASIS OF
DESIGN
MFG.
BOX
MIN.
CFM
MFG.
BOX
MAX.
CFM
CFM DATA
INLET
SIZE
REHEAT/HEATING COIL DATA
MBH EWT/LWT °F EAT °F GPM
MAX.
WPD
FT.HD.
MAX
APD
IN.WC
REMARKS
SINGLE DUCT
REHEAT 5"Ø 180/137 55 5.00.17 SEE NOTES
DUCT CONN.
COIL
POSITION
DISCHARGE
COOLING/
HEATING
CFM
MARK
VAV-4-1
LAT °F
MIN.
COOLING/
HEATING
CFM
150 15050 350 0.5TRANE VCWF 10.56
1. ACTUATORS FOR VAV BOX AIR-CONTROL DAMPERS ARE TO BE FURNISHED AND INSTALLED BY THE AUTOMATIC TEMPERATURE CONTROLS SUPPLIER.
2. HEATING COIL CONTROL VALVES AND ACTUATORS ARE TO BE FURNISHED AND INSTALLED BY THE AUTOMATIC TEMPERATURE CONTROLS SUPPLIER.
3. MFR'S INLET SIZE MAY NOT REPRESENT PRIMARY AIR DUCT SIZE. FURNISH REDUCERS OR ENLARGERS FOR CONNECTING PRIMARY DUCT TO INLET.
4. PROVIDE BOXES WITH CONTROL ENCLOSURES, INTERNALLY LINED CASINGS, HEATING COILS LOCATED ON THE DISCHARGE POSITION.
5. FOR ALL BOXES, FIELD VERIFY RIGHT-HAND OR LEFT-HAND BOX AND COIL CONFIGURATIONS, DUCT CONNECTION CONFIGURATIONS, AND ELECTRICAL & CONTROL BOX
LOCATIONS PRIOR TO SUBMITTAL.
6. PROVIDE VAV BOXES WITH DOUBLE WALL CONSTRUCTION.
7. MINIMUM AND MAXIMUM AIRFLOWS LISTED ARE SHOWN FOR SIZING OF VAV BOXES. VAV BOXES MUST BE BALANCED TO COOLING AND HEATING DESIGN AIRFLOWS LISTED.
8. THE CONTRACTOR MUST FIELD VERIFY EXISTING CONDITIONS AND DIMENSIONS PRIOR TO EQUIPMENT SELECTION. CONTRACTOR MUST ENSURE THAT ALL EQUIPMENT
SELECTED IS SIZED ACCORDINGLY TO ALLOW FOR SEAMLESS CONNECTION TO EXISTING DUCTWORK, PIPING, AND ALL OTHER APPURTENANCES. VAV BOXES MUST BE PROVIDED WITH ALL CONTROLS REQUIRED TO SEAMLESSLY CONNECT INTO THE EXISTING BUILDING CONTROL SYSTEM.
NOTES:
HC-43 MODINE EXISTING
SUP 4-10
LAB SUPPLY
AIR REHEAT 2875 140.40 0.32 0.7614.0100.0 180 36X18
HC-44 MODINE EXISTING
SUP 4-22
LAB SUPPLY
AIR REHEAT 4355 212.50 0.27 1.3421.2100.0 180 48X18
SINGLE DUCT
REHEAT 5.0 SEE NOTESDISCHARGEVAV-4-2 TRANE VCWF
1. HOT WATER COILS MUST BE PROVIDED WITH ALL CONTROLS REQUIRED TO SEAMLESSLY CONNECT INTO THE EXISTING BUILDING CONTROL SYSTEM.
2. HEATING COIL CONTROL VALVES AND ACTUATORS ARE TO BE FURNISHED AND INSTALLED BY THE AUTOMATIC TEMPERATURE CONTROLS SUPPLIER.
3. MFR'S INLET SIZE MAY NOT REPRESENT PRIMARY AIR DUCT SIZE. FURNISH REDUCERS OR ENLARGERS FOR CONNECTING PRIMARY DUCT TO INLET.
4. THE CONTRACTOR MUST FIELD VERIFY EXISTING CONDITIONS AND DIMENSIONS PRIOR TO EQUIPMENT SELECTION. CONTRACTOR MUST ENSURE THAT ALL EQUIPMENT
SELECTED IS SIZED ACCORDINGLY TO ALLOW FOR SEAMLESS CONNECTION TO EXISTING DUCTWORK, PIPING, AND ALL OTHER APPURTENANCES.
NOTES:
12X9
12X9
12X9
12X9
12X9
12X9
12X9
REMARKS
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
SEE NOTES
5"Ø 180/137 550.17 119150 15050 350 0.510.56
| Sheets and Views |
| G002-2B-G-002-2B |
| G002-3A-G-002-3A |
| G002-3B-G-002-3B |
| A-103-E-111-2A |
| MD104-MD104 |
| MP102-MP102 |
| M-603-M-603 |
File details come from the government source that posted it. Updated .