This is a General Notes and Phasing Plan sheet for a USDA building renovation project. The document establishes construction requirements and sequencing for work to be performed while the facility remains occupied and operational. The project is organized into multiple phases: Phase 2A, Phase 2B Sequence 1, Phase 2B Sequence 2, Phase 3A, and Phase 3B, which must be completed in the specified order with no deviation without written approval from the Contracting Officer. The contractor must complete all work, testing, restoration, and acceptance requirements of each phase before commencing the next phase.

The contractor is responsible for providing a work plan detailing means to maintain building operations, coordinating with USDA personnel on staging areas and work activities, and erecting barriers and signage for safety and wayfinding. The contractor must protect existing furnishings, equipment, fire alarm devices, and sprinkler systems during construction, with all temporary coverings removed daily and whenever the facility is unattended for more than four hours. Work may extend beyond hatched area limits for systems above ceilings; the contractor must remove and reinstall ceilings and finishes as necessary and restore affected areas to match existing conditions. The contractor must remove and reinstall light fixtures as needed to accommodate hydronic heating equipment and piping insulation work, protecting fixtures from damage and verifying proper operation upon reinstallation. Any damage to existing systems resulting from construction activities must be repaired or replaced by the contractor at no additional cost to the government.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PHASE 3A

AREA OF

WORK

PHASE 1A, 1B AND 1C (NOT IN CONTRACT):

PHASE 2A (NOT IN CONTRACT)

PHASE 2B SEQUENCE 2 (NOT IN CONTRACT)

PHASE 3A

PHASE 3B (NOT IN CONTRACT)

PHASE 2B SEQUENCE 1

(NOT IN CONTRACT)

PHASING LEGEND

A. ALL NON-WORK AREAS IN THE BUILDING WILL REMAIN OCCUPIED AND OPERATIONAL

DURING THE WORK. USDA WILL VACATE AREAS OF THE BUILDING WHERE WORK IS

BEING PERFORMED. THE CONTRACTOR MUST COORDINATE HIS/HER WORK

ACTIVITIES WITH THE CONTRACTING OFFICER TO AVOID CONFLICTS WITH FACILITY

OPERATIONS. THE CONTRACTOR MUST ERECT BARRIERS AND EMPLOY NECESSARY

MEASURES TO PROTECT PERSONNEL IN THE AREA FROM INJURY.

B. COVER AND PROTECT ALL FURNISHINGS AND EQUIPMENT REMAINING IN THE

SPACES.

C. THE CONTRACTOR MUST PROVIDE BARRIERS AND SIGNAGE TO SECURE THE WORK

AREAS, TO DIRECT PERSONNEL IN WAYFINDING, AND TO ENSURE THE SAFETY OF

BUILDING OCCUPANTS AND VISITORS. THE CONTRACTOR MUST PROVIDE A WORK

PLAN BEFORE BEGINNING THE WORK EXPLAINING AND ILLUSTRATING THE MEANS TO

BE IMPLEMENTED TO ALLOW THE BUILDING TO REMAIN OCCUPIED AND OPERATIONAL

DURING THE WORK. THE CONTRACTOR MUST FIELD VERIFY ALL DIMENSION AND

CONDITIONS BEFORE BEGINNING WORK.

D. CONTRACTOR MUST COORDINATE STAGING AREAS WITH USDA PERSONNEL.

E. THE HATCHED “AREA OF WORK” SHOWN ON THE PHASING PLAN INDICATES THE

PRIMARY RENOVATION LIMITS FOR EACH PHASE. WORK REQUIRED BY THE DRAWINGS

AND SPECIFICATIONS MAY EXTEND INTO ADJACENT AREAS OUTSIDE OF THE

HATCHED LIMITS (INCLUDING WORK ABOVE CEILINGS SUCH AS DUCTWORK, PIPING,

AND ASSOCIATED SYSTEMS). WHERE ACCESS IS REQUIRED IN THESE ADJACENT

AREAS, THE CONTRACTOR SHALL REMOVE AND REINSTALL CEILINGS AND FINISHES

AS NECESSARY TO PERFORM THE WORK AND SHALL RESTORE ALL AFFECTED AREAS

TO MATCH EXISTING CONDITIONS. ALL WORK INDICATED IN THE CONTRACT

DOCUMENTS SHALL BE INCLUDED IN THE SCOPE OF THE RESPECTIVE PHASE

REGARDLESS OF WHETHER IT OCCURS STRICTLY WITHIN THE HATCHED AREA.

F. THE CONTRACTOR MUST COMPLETE ALL WORK ASSOCIATED WITH A GIVEN PHASE

PRIOR TO COMMENCEMENT OF WORK IN ANY SUBSEQUENT PHASE. WORK FOR A

NEW PHASE MUST NOT BEGIN UNTIL ALL WORK, TESTING, RESTORATION, AND

ACCEPTANCE REQUIREMENTS OF THE PREVIOUS PHASE ARE COMPLETE. THE

REQUIRED ORDER OF CONSTRUCTION PHASING MUST BE AS FOLLOWS:

PHASE 2A → PHASE 2B SEQUENCE 1→ PHASE 2B SEQUENCE 2→ PHASE 3A → PHASE 3B

G. DEVIATION FROM THE ESTABLISHED PHASING SEQUENCE MUST NOT OCCUR

WITHOUT PRIOR WRITTEN APPROVAL FROM THE CONTRACTING OFFICER.

H. CONTRACTOR MUST REMOVE AND RETAIN LIGHT FIXTURES (NOT SHOWN DRAWING)

AS REQUIRED TO ACCOMMODATE THE REMOVAL AND REPLACEMENT OF HYDRONIC

HEATING EQUIPMENT AND PIPING INSULATION AS SHOWN ON THE MECHANICAL

DRAWINGS. CONTRACTOR MUST DISCONNECT AND SAFELY TERMINATE ALL CONDUIT

AND WIRING WITH APPROVED WIRE NUTS AND ELECTRICAL TAPE. FIXTURES MUST BE

PROTECTED FROM DAMAGE AND STORED FOR REINSTALLATION. UPON COMPLETION

OF PIPING AND INSULATION WORK, CONTRACTOR MUST REINSTALL ALL FIXTURES IN

ORIGINAL LOCATIONS AND VERIFY PROPER OPERATION. ANY FIXTURES OR

ASSOCIATED COMPONENTS DAMAGED DURING THIS WORK MUST BE REPAIRED OR

REPLACED IN KIND AT NO COST TO THE GOVERNMENT.

I. PRIOR TO THE START OF WORK EACH DAY IN ACTIVE CONSTRUCTION AREAS, THE

CONTRACTOR MUST TEMPORARILY PROTECT FIRE ALARM INITIATING AND

NOTIFICATION DEVICES AS WELL AS SPRINKLER HEADS (NOT SHOWN ON DRAWING)

FROM DUST, DEBRIS, AND DAMAGE USING APPROVED METHODS. ALL TEMPORARY

COVERINGS MUST BE REMOVED AT THE END OF EACH WORKDAY AND AT ANY TIME

THE FACILITY WILL BE LEFT UNATTENDED FOR MORE THAN FOUR (4) HOURS. FIRE

ALARM DEVICES AND SPRINKLERS IN OCCUPIED AREAS MUST NOT BE COVERED,

DISABLED, OR OBSTRUCTED. ANY DAMAGE TO EXISTING FIRE ALARM OR

SUPPRESSION SYSTEM COMPONENTS RESULTING FROM CONSTRUCTION ACTIVITIES

MUST BE REPAIRED OR REPLACED IN KIND BY THE CONTRACTOR AT NO ADDITIONAL

COST TO THE OWNER, AND THE SYSTEM MUST BE RESTORED TO FULL OPERATIONAL

STATUS PRIOR TO REOCCUPANCY OF AFFECTED SPACES.

GENERAL NOTES

Dylan Mitchell sam

Sheets and Views
G002-2B-G-002-2B
G002-3A-G-002-3A
G002-3B-G-002-3B
A-103-E-111-2A
MD104-MD104
MP102-MP102
M-603-M-603

File details come from the government source that posted it. Updated .