11. NSGB WDTF Construction Schedule 03 Mar 22.pdf
PDF 732 KB Posted
- Attached to
- Veterinary Clinic IO Project - Guantanamo Bay
- Solicitation number
- W9127S22Q6004
About this file
This special notice document announces an upcoming solicitation for an initial outfitting project for a Veterinary Clinic Military Working Dog Treatment Facility at Naval Station Guantanamo Bay, Cuba. The requirement will be set aside for small businesses only, with a NAICS code of 337127 and size standard of 500 employees. The estimated contract value is between $1-3 million. The simplified acquisition procedures of FAR Part 13 will be used along with commercial item procedures of FAR Part 12. The proposal due date is expected to be August 31, 2022. The OFB goal date is December 31, 2023. ProjNet will be open for questions from August 3-15, 2022 regarding this requirement.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Duration %
Complete
Original
Duration
Remaining
Duration
Total
Float
Start Finish Late Start Late Finish
GTMO Working Dog Treatment Facility - Construction Schedule Update - February 2022GTMO Working Dog Treatment Facility - Construction Schedule Update - February 202237.28% 636 399 -69 25-Aug-21 A 07-Sep-23 22-Nov-21 02-Jun-23
A1000 Contract Award 100% 0 0 25-Aug-21 A 10-Dec-21
A1010 Projected Completion 0% 0 0 -69 07-Sep-23 02-Jun-23
A1020 Contract Completion Date 0% 0 0 0 02-Jun-23* 02-Jun-23
PreconstructionPreconstruction 62.46% 213 80 250 25-Aug-21 A 17-Jun-22 10-Dec-21 02-Jun-23
PRECON1000 Project Preconstruction Meeting 100% 15 0 28-Sep-21 A 28-Sep-21 A 17-Jan-22 17-Jan-22
SubmittalsSubmittals 0% 60 60 270 25-Aug-21 A 20-May-22 10-Dec-21 02-Jun-23
SUB1000 Submit List of Contract Personnel 100% 30 0 25-Aug-21 A 07-Oct-21 A 02-Jun-23 02-Jun-23
SUB1010 Submit Earned Value Report 100% 30 0 25-Aug-21 A 27-Oct-21 A 02-Jun-23 02-Jun-23
SUB1020 Submit Bond 100% 10 0 25-Aug-21 A 07-Sep-21 A 02-Jun-23 02-Jun-23
SUB1030 Submit Project Schedule 100% 30 0 25-Aug-21 A 27-Oct-21 A 02-Jun-23 02-Jun-23
SUB1040 Submit Accident Prevention Plan 100% 40 0 25-Aug-21 A 30-Sep-21 A 02-Jun-23 02-Jun-23
SUB1050 Submit Quality Control Plan 100% 40 0 25-Aug-21 A 07-Oct-21 A 02-Jun-23 02-Jun-23
SUB1060 Submit Environmental Protection Plan 100% 40 0 25-Aug-21 A 05-Oct-21 A 02-Jun-23 02-Jun-23
SUB1080 Submit Concrete & Accessories Product Data 100% 10 0 25-Aug-21 A 22-Nov-21 A 16-Dec-21 16-Dec-21
SUB1090 Submit Masonry & Accessories Product Data 100% 5 0 25-Aug-21 A 18-Oct-21 A 20-Dec-21 20-Dec-21
SUB1100 Submit Metal Trusses Product Data 100% 20 0 25-Aug-21 A 22-Dec-21 A 25-Feb-22 25-Feb-22
SUB1110 Submit Structural Steel Product Data 100% 20 0 25-Aug-21 A 03-Nov-21 A 25-Feb-22 25-Feb-22
SUB1120 Submit Metal Roofing Product Data 100% 20 0 25-Aug-21 A 22-Feb-22 A 08-Apr-22 08-Apr-22
SUB1130 Submit Doors, Frames, & Hardware Product Data 0% 60 60 -10 25-Aug-21 A 20-May-22 11-Feb-22 06-May-22
SUB1140 Submit Glazing Product Data 0% 60 60 -30 25-Aug-21 A 20-May-22 14-Jan-22 08-Apr-22
SUB1150 Submit Framing & Drywall Product Data 0% 40 40 21 25-Aug-21 A 22-Apr-22 28-Mar-22 23-May-22
SUB1160 Submit Flooring Product Data 0% 40 40 114 25-Aug-21 A 22-Apr-22 04-Aug-22 29-Sep-22
SUB1170 Submit Paint Product Data 0% 40 40 106 25-Aug-21 A 22-Apr-22 25-Jul-22 19-Sep-22
SUB1180 Submit Specialties Product Data 0% 40 40 109 25-Aug-21 A 22-Apr-22 28-Jul-22 22-Sep-22
SUB1190 Submit Aluminum Canopy Product Data 0% 60 60 99 25-Aug-21 A 20-May-22 14-Jul-22 06-Oct-22
SUB1200 Submit Equipment Product Data 0% 60 60 94 25-Aug-21 A 20-May-22 07-Jul-22 29-Sep-22
SUB1210 Submit Fire Suppression Product Data 0% 60 60 54 25-Aug-21 A 20-May-22 12-May-22 04-Aug-22
SUB1220 Submit Plumbing & Utilities Product Data 0% 5 5 -45 25-Aug-21 A 04-Mar-22 24-Dec-21 31-Dec-21
SUB1230 Submit HVAC Product Data 0% 20 20 24 25-Aug-21 A 25-Mar-22 31-Mar-22 28-Apr-22
SUB1240 Submit Controls Product Data 0% 20 20 30 25-Aug-21 A 25-Mar-22 08-Apr-22 06-May-22
SUB1250 Submit Electrical Product Data 0% 10 10 -55 25-Aug-21 A 11-Mar-22 10-Dec-21 24-Dec-21
SUB1260 Submit Fencing, Gates, & Landscaping Product Data 0% 60 60 250 25-Aug-21 A 20-May-22 13-Feb-23 05-May-23
SUB1270 Submit Millwork Shop Drawings 100% 60 0 25-Aug-21 A 22-Feb-22 A 20-Oct-22 20-Oct-22
Review & Approve SubmittalsReview & Approve Submittals 60.62% 203 80 250 08-Sep-21 A 17-Jun-22 16-Dec-21 02-Jun-23
APPSUB1000 Review & Approve List of Contract Personnel 100% 20 0 07-Oct-21 A 08-Oct-21 A 02-Jun-23 02-Jun-23
APPSUB1010 Review & Approve Earned Value Report 100% 20 0 27-Oct-21 A 08-Nov-21 A 02-Jun-23 02-Jun-23
APPSUB1020 Review & Approve Bond 100% 20 0 08-Sep-21 A 13-Sep-21 A 02-Jun-23 02-Jun-23
APPSUB1030 Review & Approve Project Schedule 100% 20 0 27-Oct-21 A 08-Nov-21 A 02-Jun-23 02-Jun-23
APPSUB1040 Review & Approve Accident Prevention Plan 100% 20 0 30-Sep-21 A 08-Nov-21 A 02-Jun-23 02-Jun-23
APPSUB1050 Review & Approve Quality Control Plan 100% 20 0 07-Oct-21 A 08-Nov-21 A 02-Jun-23 02-Jun-23
APPSUB1060 Review & Approve Environmental Protection Plan 100% 20 0 05-Oct-21 A 23-Nov-21 A 02-Jun-23 02-Jun-23
APPSUB1070 Review & Approve Concrete & Accessories Product Data 100% 20 0 15-Nov-21 A 08-Dec-21 A 16-Dec-21 16-Dec-21
APPSUB1080 Review & Approve Masonry & Accessories Product Data 100% 20 0 18-Oct-21 A 15-Nov-21 A 20-Dec-21 20-Dec-21
APPSUB1090 Review & Approve Metal Trusses Product Data 50% 20 10 0 22-Dec-21 A 11-Mar-22 25-Feb-22 11-Mar-22
APPSUB1100 Review & Approve Structura l Steel Product Data 100% 20 0 03-Nov-21 A 09-Nov-21 A 25-Feb-22 25-Feb-22
APPSUB1110 Review & Approve Metal Roofing Product Data 50% 20 10 30 22-Feb-22 A 11-Mar-22 08-Apr-22 22-Apr-22
APPSUB1120 Review & Approve Doors, Frames, & Hardware Product Data 0% 20 20 -10 23-May-22 17-Jun-22 06-May-22 03-Jun-22
APPSUB1130 Review & Approve Glazing Product Data 0% 20 20 -30 23-May-22 17-Jun-22 08-Apr-22 06-May-22
APPSUB1140 Review & Approve Framing & Drywall Product Data 0% 20 20 21 25-Apr-22 20-May-22 23-May-22 20-Jun-22
APPSUB1150 Review & Approve Flooring Product Data 0% 20 20 114 25-Apr-22 20-May-22 29-Sep-22 27-Oct-22
APPSUB1160 Review & Approve Paint Product Data 0% 20 20 106 25-Apr-22 20-May-22 19-Sep-22 17-Oct-22
APPSUB1170 Review & Approve Specialties Product Data 0% 20 20 109 25-Apr-22 20-May-22 22-Sep-22 20-Oct-22
APPSUB1180 Review & Approve Aluminum Canopy Product Data 0% 20 20 99 23-May-22 17-Jun-22 06-Oct-22 03-Nov-22
APPSUB1190 Review & Approve Equipment Product Data 0% 20 20 94 23-May-22 17-Jun-22 29-Sep-22 27-Oct-22
APPSUB1200 Review & Approve Fire Suppression Product Data 0% 20 20 54 23-May-22 17-Jun-22 04-Aug-22 01-Sep-22
APPSUB1210 Review & Approve Plumbing & Utilities Product Data 0% 20 20 -45 07-Mar-22 01-Apr-22 31-Dec-21 28-Jan-22
APPSUB1220 Review & Approve HVAC Product Data 0% 20 20 24 28-Mar-22 22-Apr-22 28-Apr-22 26-May-22
APPSUB1230 Review & Approve Controls Product Data 0% 20 20 30 28-Mar-22 22-Apr-22 06-May-22 03-Jun-22
APPSUB1240 Review & Approve Electrica l Product Data 0% 20 20 -55 14-Mar-22 08-Apr-22 24-Dec-21 21-Jan-22
APPSUB1250 Review & Approve Fencing, Gates, & Landscaping Product Data0% 20 20 250 23-May-22 17-Jun-22 08-May-23 02-Jun-23
APPSUB1260 Review & Approve Millwork Shop Drawings 100% 20 0 169 22-Feb-22 A 28-Feb-22 20-Oct-22 20-Oct-22
APPSUB2200 Submittals Complete 0% 0 0 250 17-Jun-22 02-Jun-23
ProcurementProcurement 25.97% 231 171 74 02-Nov-21 A 24-Oct-22 16-Dec-21 03-Feb-23
PRO1000 Procure Concrete Reinforcement & Accessories 0% 20 21 -51 02-Nov-21 A 28-Mar-22 16-Dec-21 14-Jan-22
PRO1001 Receive Concrete Reinforcement & Accessories 0% 1 1 -51 29-Mar-22 29-Mar-22 14-Jan-22 17-Jan-22
PRO1010 Procure Masonry & Accessories 50% 40 20 -49 15-Nov-21 A 25-Mar-22 20-Dec-21 17-Jan-22
PRO1011 Receive Masonry & Accessories 0% 1 0 -49 28-Mar-22 28-Mar-22 17-Jan-22 17-Jan-22
PRO1020 Procure Metal Trusses 0% 60 60 0 14-Mar-22 03-Jun-22 11-Mar-22 03-Jun-22
PRO1021 Receive Metal Trusses 0% 1 1 0 06-Jun-22 06-Jun-22 03-Jun-22 06-Jun-22
PRO1030 Procure Structural Steel 0% 60 60 5 28-Feb-22 20-May-22 04-Mar-22 27-May-22
PRO1031 Receive Structural Steel 0% 1 1 5 23-May-22 23-May-22 27-May-22 30-May-22
PRO1032 Procure Steel Embeds 0% 40 40 0 28-Feb-22 22-Apr-22 25-Feb-22 22-Apr-22
PRO1033 Receive Steel Embeds 0% 1 1 0 25-Apr-22 25-Apr-22 22-Apr-22 25-Apr-22
PRO1040 Procure Metal Roofing 0% 60 60 30 14-Mar-22 03-Jun-22 22-Apr-22 15-Jul-22
PRO1041 Receive Metal Roofing 0% 1 1 30 06-Jun-22 06-Jun-22 15-Jul-22 18-Jul-22
PRO1050 Procure Door Frames 0% 40 40 -10 20-Jun-22 12-Aug-22 03-Jun-22 29-Jul-22
PRO1051 Receive Door Frames 0% 1 1 -10 15-Aug-22 15-Aug-22 29-Jul-22 01-Aug-22
PRO1060 Procure Doors & Hardware 0% 40 40 -5 20-Jun-22 12-Aug-22 10-Jun-22 05-Aug-22
PRO1061 Receive Doors & Hardware 0% 1 1 -5 15-Aug-22 15-Aug-22 05-Aug-22 08-Aug-22
PRO1070 Procure Glazing 0% 60 60 -30 20-Jun-22 09-Sep-22 06-May-22 29-Jul-22
PRO1071 Receive Glazing 0% 1 1 -30 12-Sep-22 12-Sep-22 29-Jul-22 01-Aug-22
PRO1080 Procure Framing & Drywall 0% 20 20 21 23-May-22 17-Jun-22 20-Jun-22 18-Jul-22
PRO1081 Receive Framing & Drywall 0% 1 1 21 20-Jun-22 20-Jun-22 18-Jul-22 19-Jul-22
PRO1090 Procure Flooring 0% 40 40 114 23-May-22 15-Jul-22 27-Oct-22 22-Dec-22
PRO1091 Receive Flooring 0% 1 1 114 18-Jul-22 18-Jul-22 22-Dec-22 23-Dec-22
PRO1100 Procure Paint 0% 20 20 106 23-May-22 17-Jun-22 17-Oct-22 14-Nov-22
PRO1101 Receive Paint 0% 1 1 106 20-Jun-22 20-Jun-22 14-Nov-22 15-Nov-22
PRO1110 Procure Specialties 0% 60 60 109 23-May-22 12-Aug-22 20-Oct-22 12-Jan-23
PRO1111 Receive Specialties 0% 1 1 109 15-Aug-22 15-Aug-22 12-Jan-23 13-Jan-23
PRO1120 Procure Aluminum Canopies 0% 60 60 99 20-Jun-22 09-Sep-22 03-Nov-22 26-Jan-23
PRO1121 Receive Aluminum Canopies 0% 1 1 99 12-Sep-22 12-Sep-22 26-Jan-23 27-Jan-23
PRO1130 Procure Equipment 0% 60 60 94 20-Jun-22 09-Sep-22 27-Oct-22 19-Jan-23
PRO1131 Receive Equipment 0% 1 1 94 12-Sep-22 12-Sep-22 19-Jan-23 20-Jan-23
PRO1140 Procure Fire Suppression Material 0% 60 60 54 20-Jun-22 09-Sep-22 01-Sep-22 24-Nov-22
PRO1141 Receive Fire Suppression Material 0% 1 1 54 12-Sep-22 12-Sep-22 24-Nov-22 25-Nov-22
PRO1150 Procure Utilities Material 0% 50 50 -45 20-Jan-22 A 10-Jun-22 28-Jan-22 08-Apr-22
PRO1151 Receive Utilities Material 0% 1 1 -45 13-Jun-22 13-Jun-22 08-Apr-22 11-Apr-22
PRO1160 Procure Plumbing Material 0% 60 60 40 04-Apr-22 24-Jun-22 27-May-22 19-Aug-22
PRO1161 Receive Plumbing Material 0% 1 1 40 27-Jun-22 27-Jun-22 19-Aug-22 22-Aug-22
PRO1171 Procure AHU-1 0% 130 130 24 25-Jan-22 A 21-Oct-22 26-May-22 24-Nov-22
PRO1181 Receive AHU-1 0% 1 1 24 24-Oct-22 24-Oct-22 24-Nov-22 25-Nov-22
PRO1191 Procure AHU-2 0% 130 130 24 25-Jan-22 A 21-Oct-22 26-May-22 24-Nov-22
PRO1201 Receive AHU-2 0% 1 1 24 24-Oct-22 24-Oct-22 24-Nov-22 25-Nov-22
PRO1202 Procure Chiller 0% 105 105 84 25-Apr-22 16-Sep-22 18-Aug-22 12-Jan-23
PRO1203 Receive Chiller 0% 1 1 84 19-Sep-22 19-Sep-22 12-Jan-23 13-Jan-23
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2022 2023
07-Sep-23, GTMO Working Dog Treatment Facility - Construction Schedule Update - February 2022
Projected Completion
Contract Completion Date
17-Jun-22, Preconstruction
20-May-22, Submittals
Submit List of Contract Personnel
Submit Earned Value Report
Submit Project Schedule
Submit Environmental Protection Plan
Submit Concrete & Accessories Product Data
Submit Masonry & Accessories Product Data
Submit Metal Trusses Product Data
Submit Structural Steel Product Data
Submit Metal Roofing Product Data
Submit Doors, Frames, & Hardware Product Data
Submit Glazing Product Data
Submit Framing & Drywall Product Data
Submit Flooring Product Data
Submit Paint Product Data
Submit Specialties Product Data
Submit Aluminum Canopy Product Data
Submit Equipment Product Data
Submit Fire Suppression Product Data
Submit Plumbing & Utilities Product Data
Submit HVAC Product Data
Submit Controls Product Data
Submit Electrical Product Data
Submit Fencing, Gates, & Landscaping Product Data
Submit Millwork Shop Drawings
17-Jun-22, Review & Approve Submittals
Review & Approve List of Contract Personnel
Review & Approve Earned Value Report
Review & Approve Project Schedule
Review & Approve Accident Prevention Plan
Review & Approve Quality Control Plan
Review & Approve Environmental Protection Plan
Review & Approve Concrete & Accessories Product Data
Review & Approve Masonry & Accessories Product Data
Review & Approve Metal Trusses Product Data
Review & Approve Structural Steel Product Data
Review & Approve Metal Roofing Product Data
Review & Approve Doors, Frames, & Hardware Product Data
Review & Approve Glazing Product Data
Review & Approve Framing & Drywall Product Data
Review & Approve Flooring Product Data
Review & Approve Paint Product Data
Review & Approve Specialties Product Data
Review & Approve Aluminum Canopy Product Data
Review & Approve Equipment Product Data
Review & Approve Fire Suppression Product Data
Review & Approve Plumbing & Utilities Product Data
Review & Approve HVAC Product Data
Review & Approve Controls Product Data
Review & Approve Electrica l Product Data
Review & Approve Fencing, Gates, & Landscaping Product Data
Review & Approve Millwork Shop Drawings
Submittals Complete
24-Oct-22, Procurement
Procure Concrete Reinforcement & Accessories
Receive Concrete Reinforcement & Accessories
Procure Masonry & Accessories
Receive Masonry & Accessories
Procure Metal Trusses
Receive Metal Trusses
Procure Structural Steel
Receive Structural Steel
Procure Steel Embeds
Receive Steel Embeds
Procure Metal Roofing
Receive Metal Roofing
Procure Door Frames
Receive Door Frames
Procure Doors & Hardware
Receive Doors & Hardware
Procure Glazing
Receive Glazing
Procure Framing & Drywall
Receive Framing & Drywall
Procure Flooring
Receive Flooring
Procure Paint
Receive Paint
Procure Specialties
Receive Specialties
Procure Aluminum Canopies
Receive Aluminum Canopies
Procure Equipment
Receive Equipment
Procure Fire Suppression Material
Receive Fire Suppression Material
Procure Utilities Material
Receive Utilities Material
Procure Plumbing Material
Receive Plumbing Material
Procure AHU-1
Receive AHU-1
Procure AHU-2
Receive AHU-2
Procure Chiller
Receive Chiller
GTMO Working Dog Treatment Facility - Construction Classic Schedule Layout 03-Mar-22 09:14
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Original
Duration
Remaining
Duration
Total
Float
Start Finish Late Start Late Finish
PRO1211 Procure VAVs 0% 60 60 25 25-Apr-22 15-Jul-22 27-May-22 19-Aug-22
PRO1221 Receive VAVs 0% 1 1 25 18-Jul-22 18-Jul-22 19-Aug-22 22-Aug-22
PRO1231 Procure FCUs 0% 50 50 149 25-Apr-22 01-Jul-22 17-Nov-22 26-Jan-23
PRO1241 Receive FCUs 0% 1 1 149 04-Jul-22 04-Jul-22 26-Jan-23 27-Jan-23
PRO1251 Procure Ductwork & Accessories 0% 60 60 25 25-Apr-22 15-Jul-22 27-May-22 19-Aug-22
PRO1261 Receive Ductwork & Accessories 0% 1 1 25 18-Jul-22 18-Jul-22 19-Aug-22 22-Aug-22
PRO1271 Procure Controls Materials 0% 60 60 30 25-Apr-22 15-Jul-22 03-Jun-22 26-Aug-22
PRO1281 Receive Controls Materials 0% 1 1 30 18-Jul-22 18-Jul-22 26-Aug-22 29-Aug-22
PRO1291 Procure Electrical Rough Material 0% 40 40 -55 11-Apr-22 03-Jun-22 21-Jan-22 18-Mar-22
PRO1301 Receive Electrical Rough Material 0% 1 1 -55 06-Jun-22 06-Jun-22 18-Mar-22 21-Mar-22
PRO1311 Procure Electrical Gear 0% 80 80 72 11-Apr-22 29-Jul-22 19-Jul-22 08-Nov-22
PRO1312 Receive Electrical Gear 0% 1 1 72 01-Aug-22 01-Aug-22 08-Nov-22 09-Nov-22
PRO1322 Procure Switch & Transformer 0% 140 140 74 11-Apr-22 21-Oct-22 21-Jul-22 02-Feb-23
PRO1323 Receive Switch & Transformer 0% 1 1 74 24-Oct-22 24-Oct-22 02-Feb-23 03-Feb-23
PRO1331 Procure Generator 0% 100 100 106 11-Apr-22 26-Aug-22 05-Sep-22 23-Jan-23
PRO1341 Receive Generator 0% 1 1 106 29-Aug-22 29-Aug-22 23-Jan-23 24-Jan-23
PRO1351 Procure Lighting & Trim 0% 60 60 115 11-Apr-22 01-Jul-22 16-Sep-22 09-Dec-22
PRO1361 Receive Lighting & Trim 0% 1 1 115 04-Jul-22 04-Jul-22 09-Dec-22 12-Dec-22
PRO1371 Procure Millwork 0% 60 60 169 28-Feb-22 20-May-22 20-Oct-22 12-Jan-23
PRO1381 Receive Millwork 0% 1 1 169 23-May-22 23-May-22 12-Jan-23 13-Jan-23
PRO1391 Procure Fire Alarm Material 0% 70 70 132 11-Apr-22 15-Jul-22 11-Oct-22 17-Jan-23
PRO1401 Receive Fire Alarm Materia l 0% 1 1 132 18-Jul-22 18-Jul-22 17-Jan-23 18-Jan-23
PRO1411 Procure Fences & Gates 0% 60 60 114 23-May-22 12-Aug-22 27-Oct-22 19-Jan-23
PRO1421 Receive Fences & Gates 0% 1 1 114 15-Aug-22 15-Aug-22 19-Jan-23 20-Jan-23
ImpactsImpacts 33.33% 60 40 -69 31-Jan-22 A 22-Apr-22 22-Nov-21 17-Jan-22
COVID QuarantineCOVID Quarantine 33.33% 60 40 -69 31-Jan-22 A 22-Apr-22 22-Nov-21 17-Jan-22
IN0010 COVID Quarantine Impact 33.33% 60 40 -69 31-Jan-22 A 22-Apr-22 22-Nov-21 17-Jan-22
ConstructionConstruction 0% 350 350 -60 25-Apr-22 25-Aug-23 17-Jan-22 02-Jun-23
CON0100 Mobilize 0% 1 0 -69 25-Apr-22 25-Apr-22 17-Jan-22 17-Jan-22
CON0110 Building Dry-In 0% 0 0 -69 25-Nov-22 22-Aug-22
CON0120 Beneficial Occupancy Date 0% 0 0 10 19-May-23 02-Jun-23
Site Demolition/EarthworkSite Demolition/Earthwork 0% 45 45 -69 25-Apr-22 24-Jun-22 17-Jan-22 21-Mar-22
CON0200 Site Demolition 0% 10 10 -69 25-Apr-22 06-May-22 17-Jan-22 31-Jan-22
CON0210 Rough Grading 0% 10 10 -69 09-May-22 20-May-22 31-Jan-22 14-Feb-22
CON0220 Excavate Footings 0% 5 5 -69 23-May-22 27-May-22 14-Feb-22 21-Feb-22
CON0230 Backfill 0% 5 5 -69 20-Jun-22 24-Jun-22 14-Mar-22 21-Mar-22
Foundation/ConcreteFoundation/Concrete 0% 140 140 32 30-May-22 09-Dec-22 21-Feb-22 24-Jan-23
CON0300 Form/Place Footings 0% 5 5 -69 30-May-22 03-Jun-22 21-Feb-22 28-Feb-22
CON0310 Cure Footings 0% 5 5 -69 06-Jun-22 10-Jun-22 28-Feb-22 07-Mar-22
CON0320 Form/Place Slab 0% 5 5 -69 18-Jul-22 22-Jul-22 11-Apr-22 18-Apr-22
CON0330 Cure Slab 0% 5 5 -69 25-Jul-22 29-Jul-22 18-Apr-22 25-Apr-22
CON0340 Form/Place Site Concrete 0% 5 5 30 28-Nov-22 02-Dec-22 06-Jan-23 13-Jan-23
CON0350 Cure Site Concrete 0% 5 5 30 05-Dec-22 09-Dec-22 13-Jan-23 20-Jan-23
CON0360 Form/Place Exterior Utility Pads 0% 5 5 117 01-Aug-22 05-Aug-22 10-Jan-23 17-Jan-23
CON0370 Cure Exterior Utility Pads 0% 5 5 117 08-Aug-22 12-Aug-22 17-Jan-23 24-Jan-23
Site UtilitiesSite Utilities 0% 80 80 99 07-Jun-22 26-Sep-22 02-Nov-22 10-Feb-23
CON0400 Underground Plumbing 0% 20 20 144 28-Jun-22 25-Jul-22 13-Jan-23 10-Feb-23
CON0410 Underground Sanitary Sewer 0% 20 20 154 14-Jun-22 11-Jul-22 13-Jan-23 10-Feb-23
CON0420 Underground Storm Drainage 0% 20 20 154 14-Jun-22 11-Jul-22 13-Jan-23 10-Feb-23
CON0430 Underground Electrical Raceway 0% 20 20 99 02-Aug-22 29-Aug-22 16-Dec-22 13-Jan-23
CON0431 Underground Electrical Conductors 0% 20 20 99 30-Aug-22 26-Sep-22 13-Jan-23 10-Feb-23
CON0440 Underground Telecom W iring 0% 20 20 139 05-Jul-22 01-Aug-22 13-Jan-23 10-Feb-23
CON0450 Underground CCTV Cable to Hospital 0% 20 20 107 05-Jul-22 01-Aug-22 30-Nov-22 28-Dec-22
CON0460 Underground Comm Raceway 0% 20 20 107 07-Jun-22 04-Jul-22 02-Nov-22 30-Nov-22
MasonryMasonry 0% 65 65 47 13-Jun-22 09-Sep-22 07-Mar-22 15-Nov-22
CON0500 Install Foundation Walls 0% 5 5 -69 13-Jun-22 17-Jun-22 07-Mar-22 14-Mar-22
CON0510 Install Exterior CMU Walls 0% 30 30 -69 01-Aug-22 09-Sep-22 25-Apr-22 06-Jun-22
CON0520 Install Interior CMU Walls 0% 5 5 72 01-Aug-22 05-Aug-22 08-Nov-22 15-Nov-22
Structural SteelStructural Steel 0% 86 86 24 08-Aug-22 05-Dec-22 30-May-22 06-Jan-23
CON0600 Set Structural Steel Posts 0% 5 5 -49 08-Aug-22 12-Aug-22 30-May-22 06-Jun-22
CON0610 Install Steel Trusses Area 1A 0% 15 15 -69 12-Sep-22 30-Sep-22 06-Jun-22 27-Jun-22
CON0620 Install Metal Deck Area 1A 0% 15 15 -69 03-Oct-22 21-Oct-22 27-Jun-22 18-Jul-22
CON0630 Install Steel Trusses Area 1B 0% 10 10 24 08-Nov-22 21-Nov-22 09-Dec-22 23-Dec-22
CON0640 Install Metal Deck Area 1B 0% 10 10 24 22-Nov-22 05-Dec-22 23-Dec-22 06-Jan-23
Roofing & InsulationRoofing & Insulation 0% 46 46 34 24-Oct-22 26-Dec-22 18-Jul-22 10-Feb-23
CON0700 Install Insulation - 1A 0% 10 10 -69 24-Oct-22 04-Nov-22 18-Jul-22 01-Aug-22
CON0701 Install Insulation - 1B 0% 5 5 24 06-Dec-22 12-Dec-22 06-Jan-23 13-Jan-23
CON0710 Install Standing Seam Roof - 1A 0% 15 15 -69 07-Nov-22 25-Nov-22 01-Aug-22 22-Aug-22
CON0720 Install Standing Seam Roof - 1B 0% 5 5 24 13-Dec-22 19-Dec-22 13-Jan-23 20-Jan-23
CON0730 Install Gutter 0% 5 5 34 20-Dec-22 26-Dec-22 03-Feb-23 10-Feb-23
Windows & StorefrontWindows & Storefront 0% 15 15 -30 13-Sep-22 03-Oct-22 01-Aug-22 22-Aug-22
CON0800 Install Unit Window Framing 0% 10 10 -30 13-Sep-22 26-Sep-22 01-Aug-22 15-Aug-22
CON0810 Install Unit Window Glazing 0% 5 5 -30 27-Sep-22 03-Oct-22 15-Aug-22 22-Aug-22
CON0820 Install Storefront Framing 0% 10 10 -30 13-Sep-22 26-Sep-22 01-Aug-22 15-Aug-22
CON0830 Install Storefront Glazing 0% 5 5 -30 27-Sep-22 03-Oct-22 15-Aug-22 22-Aug-22
Interior Framing & InsulationInterior Framing & Insulation 0% 50 50 -69 24-Oct-22 30-Dec-22 19-Jul-22 26-Sep-22
CON0900 Frame Interior Walls 0% 29 29 -68 24-Oct-22 01-Dec-22 19-Jul-22 29-Aug-22
CON0910 Spray Foam Insulation (exterior walls) 0% 10 10 -59 28-Nov-22 09-Dec-22 05-Sep-22 19-Sep-22
CON0920 Interior Wall Insulation 0% 5 5 -63 16-Dec-22 22-Dec-22 19-Sep-22 26-Sep-22
CON0930 Ceiling Insulation 0% 10 10 -69 19-Dec-22 30-Dec-22 12-Sep-22 26-Sep-22
FinishesFinishes 0% 84 84 -54 02-Jan-23 27-Apr-23 26-Sep-22 10-Feb-23
CON1000 Install Drywall 0% 49 49 -69 02-Jan-23 09-Mar-23 26-Sep-22 02-Dec-22
CON1010 Interior Painting 0% 19 19 -69 21-Feb-23 17-Mar-23 15-Nov-22 12-Dec-22
CON1020 Epoxy Flooring 0% 15 15 -60 20-Mar-23 07-Apr-23 23-Dec-22 13-Jan-23
CON1030 Resilient Tile Flooring 0% 10 10 -55 20-Mar-23 31-Mar-23 30-Dec-22 13-Jan-23
CON1040 Ceramic Tile Flooring 0% 10 10 -55 20-Mar-23 31-Mar-23 30-Dec-22 13-Jan-23
CON1050 Wall Tile 0% 10 10 -55 20-Mar-23 31-Mar-23 30-Dec-22 13-Jan-23
CON1060 Acoustic Ceiling 0% 15 15 -69 07-Apr-23 27-Apr-23 30-Dec-22 20-Jan-23
CON1070 Acoustic Panels 0% 5 5 -30 20-Mar-23 24-Mar-23 03-Feb-23 10-Feb-23
Doors, Frames, & HardwareDoors, Frames, & Hardware 0% 158 158 -29 16-Aug-22 23-Mar-23 01-Aug-22 10-Feb-23
CON1100 Install Exterior Hollow Metal Frames 0% 5 5 -10 16-Aug-22 22-Aug-22 01-Aug-22 08-Aug-22
CON1110 Install Exterior Hollow Metal Doors 0% 5 5 -10 23-Aug-22 29-Aug-22 08-Aug-22 15-Aug-22
CON1120 Install Interior Frames 0% 5 5 -48 25-Nov-22 01-Dec-22 19-Sep-22 26-Sep-22
CON1130 Install Interior Doors 0% 5 5 -29 03-Mar-23 09-Mar-23 20-Jan-23 27-Jan-23
CON1140 Install Exterior Hardware 0% 5 5 114 30-Aug-22 05-Sep-22 03-Feb-23 10-Feb-23
CON1150 Install Interior Hardware 0% 10 10 -29 10-Mar-23 23-Mar-23 27-Jan-23 10-Feb-23
CON1160 Install Exterior Hollow Metal Glazing 0% 5 5 -20 13-Sep-22 19-Sep-22 15-Aug-22 22-Aug-22
CON1161 Install Interior Hollow Metal Glazing 0% 5 5 -24 10-Mar-23 16-Mar-23 03-Feb-23 10-Feb-23
CON1170 Install X-Ray Door & Hardware 0% 5 5 -24 10-Mar-23 16-Mar-23 03-Feb-23 10-Feb-23
MillworkMillwork 0% 20 20 -69 21-Apr-23 18-May-23 13-Jan-23 10-Feb-23
CON1200 Install Millwork 0% 20 20 -69 21-Apr-23 18-May-23 13-Jan-23 10-Feb-23
CON1210 Install Gov't Furnished Materials 0% 20 20 -69 21-Apr-23 18-May-23 13-Jan-23 10-Feb-23
Specialties & EquipmentSpecialties & Equipment 0% 110 110 -65 12-Dec-22 12-May-23 13-Jan-23 10-Feb-23
CON1300 Install Equipment 0% 15 15 -64 21-Apr-23 11-May-23 20-Jan-23 10-Feb-23
CON1310 Install Bathroom Specialties 0% 20 20 -65 17-Apr-23 12-May-23 13-Jan-23 10-Feb-23
CON1320 Install Miscellaneous Specialties 0% 15 15 -50 03-Apr-23 21-Apr-23 20-Jan-23 10-Feb-23
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2022 2023
Procure VAVs
Receive VAVs
Procure FCUs
Receive FCUs
Procure Ductwork & Accessories
Receive Ductwork & Accessories
Procure Controls Materials
Receive Controls Materials
Procure Electrical Rough Material
Receive Electrical Rough Material
Procure Electrical Gear
Receive Electrical Gear
Procure Switch & Transformer
Receive Switch & Transformer
Procure Generator
Receive Generator
Procure Lighting & Trim
Receive Lighting & Trim
Procure Millwork
Receive Millwork
Procure Fire Alarm Material
Receive Fire Alarm Materia l
Procure Fences & Gates
Receive Fences & Gates
22-Apr-22, Impacts
22-Apr-22, COVID Quarantine
COVID Quarantine Impact
25-Aug-23, Construction
Mobilize
Building Dry-In
Beneficial Occupancy Date
24-Jun-22, Site Demolition/Earthwork
Site Demolition
Rough Grading
Excavate Footings
Backfill
09-Dec-22, Foundation/Concrete
Form/Place Footings
Cure Footings
Form/Place Slab
Cure Slab
Form/Place Site Concrete
Cure Site Concrete
Form/Place Exterior Utility Pads
Cure Exterior Utility Pads
26-Sep-22, Site Utilities
Underground Plumbing
Underground Sanitary Sewer
Underground Storm Drainage
Underground Electrical Raceway
Underground Electrical Conductors
Underground Telecom W iring
Underground CCTV Cable to Hospital
Underground Comm Raceway
09-Sep-22, Masonry
Install Foundation Walls
Install Exterior CMU Walls
Install Interior CMU Walls
05-Dec-22, Structural Steel
Set Structural Steel Posts
Install Steel Trusses Area 1A
Install Metal Deck Area 1A
Install Steel Trusses Area 1B
Install Metal Deck Area 1B
26-Dec-22, Roofing & Insulation
Install Insulation - 1A
Install Insulation - 1B
Install Standing Seam Roof - 1A
Install Standing Seam Roof - 1B
Install Gutter
03-Oct-22, Windows & Storefront
Install Unit Window Framing
Install Unit Window Glazing
Install Storefront Framing
Install Storefront Glazing
30-Dec-22, Interior Framing & Insulation
Frame Interior Walls
Spray Foam Insulation (exterior walls)
Interior Wall Insulation
Ceiling Insulation
27-Apr-23, Finishes
Install Drywall
Interior Painting
Epoxy Flooring
Resilient Ti le Flooring
Ceramic Tile Flooring
Wall Tile
Acoustic Ceiling
Acoustic Panels
23-Mar-23, Doors, Frames, & Hardware
Install Exterior Hollow Metal Frames
Install Exterior Hollow Metal Doors
Install Interior Frames
Install Interior Doors
Install Exterior Hardware
Install Interior Hardware
Install Exterior Hollow Metal Glazing
Install Interior Hollow Metal Glazing
Install X-Ray Door & Hardware
18-May-23, Millwork
Install Millwork
Install Gov't Furnished Materials
12-May-23, Specialties & Equipment
Install Equipment
Install Bathroom Specialties
Install Miscellaneous Specialties
GTMO Working Dog Treatment Facility - Construction Classic Schedule Layout 03-Mar-22 09:14
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 2 of 3 TASK filter: All Activities
Original
Duration
Remaining
Duration
Total
Float
Start Finish Late Start Late Finish
CON1330 Install Signage 0% 10 10 -35 20-Mar-23 31-Mar-23 27-Jan-23 10-Feb-23
CON1340 Exterior Fencing & Fixtures 0% 15 15 30 12-Dec-22 30-Dec-22 20-Jan-23 10-Feb-23
ElectricalElectrical 0% 219 219 -54 27-Jun-22 27-Apr-23 21-Mar-22 10-Feb-23
CON1400 Under Slab Electrical Rough-in 0% 15 15 -69 27-Jun-22 15-Jul-22 21-Mar-22 11-Apr-22
CON1410 Exterior Wall Rough-in 0% 20 20 6 15-Aug-22 09-Sep-22 22-Aug-22 19-Sep-22
CON1420 Interior Wall Rough-in 0% 30 30 -68 04-Nov-22 15-Dec-22 01-Aug-22 12-Sep-22
CON1421 Interior Branch Wiring 0% 15 15 -4 16-Dec-22 05-Jan-23 09-Dec-22 30-Dec-22
CON1430 Exterior Electrical Trim-Out 0% 10 10 -35 20-Mar-23 31-Mar-23 27-Jan-23 10-Feb-23
CON1440 Exterior Lighting 0% 10 10 100 12-Sep-22 23-Sep-22 27-Jan-23 10-Feb-23
CON1450 Interior Electrical Trim-Out 0% 15 15 -55 20-Mar-23 07-Apr-23 30-Dec-22 20-Jan-23
CON1460 Interior Lighting 0% 29 29 -69 20-Mar-23 27-Apr-23 12-Dec-22 20-Jan-23
CON1461 Install Switch 0% 5 5 74 25-Oct-22 31-Oct-22 03-Feb-23 10-Feb-23
CON1462 Install Transformer 0% 5 5 74 25-Oct-22 31-Oct-22 03-Feb-23 10-Feb-23
CON1470 Generator Placement 0% 3 3 106 30-Aug-22 01-Sep-22 24-Jan-23 27-Jan-23
CON1480 Generator Connections 0% 5 5 31 16-Dec-22 22-Dec-22 27-Jan-23 03-Feb-23
CON1490 Generator Startup 0% 5 5 31 23-Dec-22 29-Dec-22 03-Feb-23 10-Feb-23
CON1500 Lightning Protection 0% 15 15 24 20-Dec-22 09-Jan-23 20-Jan-23 10-Feb-23
CON1510 Communications Raceway 0% 20 20 -58 04-Nov-22 01-Dec-22 15-Aug-22 12-Sep-22
CON1520 Set Communications Racks 0% 15 15 -16 02-Dec-22 22-Dec-22 09-Nov-22 30-Nov-22
CON1530 Install Communications Cable 0% 20 20 -16 23-Dec-22 19-Jan-23 30-Nov-22 28-Dec-22
CON1540 Terminate & Test Communications 0% 20 20 -57 20-Mar-23 14-Apr-23 28-Dec-22 25-Jan-23
MechanicalMechanical 0% 74 74 30 20-Sep-22 30-Dec-22 22-Aug-22 10-Feb-23
CON1600 Mechanical Ductwork Install 0% 15 15 -69 28-Nov-22 16-Dec-22 22-Aug-22 12-Sep-22
CON1610 Install VAVs 0% 15 15 -69 28-Nov-22 16-Dec-22 22-Aug-22 12-Sep-22
CON1620 Install FCUs 0% 10 10 45 28-Nov-22 09-Dec-22 27-Jan-23 10-Feb-23
CON1630 Install AHU-1 0% 10 10 24 25-Oct-22 07-Nov-22 25-Nov-22 09-Dec-22
CON1640 Install AHU-2 0% 10 10 24 25-Oct-22 07-Nov-22 25-Nov-22 09-Dec-22
CON1641 Install Chiller 0% 10 10 84 20-Sep-22 03-Oct-22 13-Jan-23 27-Jan-23
CON1650 Controls Rough-In 0% 10 10 -48 04-Nov-22 17-Nov-22 29-Aug-22 12-Sep-22
CON1660 Controls Cabling 0% 10 10 21 18-Nov-22 01-Dec-22 16-Dec-22 30-Dec-22
CON1670 Controls Termination 0% 5 5 41 02-Dec-22 08-Dec-22 27-Jan-23 03-Feb-23
CON1680 Controls Testing 0% 5 5 41 09-Dec-22 15-Dec-22 03-Feb-23 10-Feb-23
CON1690 Install GRDs 0% 10 10 15 19-Dec-22 30-Dec-22 06-Jan-23 20-Jan-23
PlumbingPlumbing 0% 210 210 -45 27-Jun-22 14-Apr-23 21-Mar-22 10-Feb-23
A1030 Under Slab Plumbing Rough-In 0% 15 15 -69 27-Jun-22 15-Jul-22 21-Mar-22 11-Apr-22
A1040 In-Wall Plumbing Rough-In 0% 15 15 -63 18-Nov-22 08-Dec-22 22-Aug-22 12-Sep-22
A1050 Set Plumbing Fixtures 0% 10 10 -65 20-Mar-23 31-Mar-23 16-Dec-22 30-Dec-22
A1060 Install Water Heaters & Equipment 0% 20 20 26 09-Dec-22 05-Jan-23 13-Jan-23 10-Feb-23
A1070 Plumbing Trim Out 0% 15 15 -65 27-Mar-23 14-Apr-23 23-Dec-22 13-Jan-23
Fire AlarmFire Alarm 0% 128 128 -57 04-Nov-22 02-May-23 25-Nov-22 10-Feb-23
CON1700 Fire Alarm Rough-in 0% 10 10 16 04-Nov-22 17-Nov-22 25-Nov-22 09-Dec-22
CON1710 Fire Alarm Cabling 0% 15 15 16 18-Nov-22 08-Dec-22 09-Dec-22 30-Dec-22
CON1720 Fire Alarm Device Trim-out 0% 10 10 19 09-Dec-22 22-Dec-22 04-Jan-23 18-Jan-23
CON1730 Fire Alarm Panel Connections 0% 5 5 19 23-Dec-22 29-Dec-22 18-Jan-23 25-Jan-23
CON1740 Fire Alarm Testing 0% 12 12 -57 17-Apr-23 02-May-23 25-Jan-23 10-Feb-23
Fire SuppressionFire Suppression 0% 40 40 0 28-Nov-22 20-Jan-23 25-Nov-22 20-Jan-23
CON1800 Fire Sprinkler Main Runs 0% 20 20 0 28-Nov-22 23-Dec-22 25-Nov-22 23-Dec-22
CON1810 Install Fire Sprinkler Heads 0% 20 20 0 26-Dec-22 20-Jan-23 23-Dec-22 20-Jan-23
InspectionsInspections 0% 5 5 -59 12-Dec-22 16-Dec-22 19-Sep-22 26-Sep-22
CON1900 Air Barrier Pressure Tests 0% 5 5 -59 12-Dec-22 16-Dec-22 19-Sep-22 26-Sep-22
Demolition - GC87Demolition - GC87 0% 30 30 -69 17-Jul-23 25-Aug-23 10-Apr-23 22-May-23
DEMO1000 Abatement GC87 0% 10 10 -69 17-Jul-23 28-Jul-23 10-Apr-23 24-Apr-23
DEMO1200 Demolish GC87 0% 20 20 -69 31-Jul-23 25-Aug-23 24-Apr-23 22-May-23
Demolition - Brig SiteDemolition - Brig Site 0% 15 15 -66 31-Jul-23 18-Aug-23 27-Apr-23 18-May-23
DEMO1300 Abatement N403E 0% 5 5 -66 31-Jul-23 04-Aug-23 27-Apr-23 04-May-23
DEMO1400 Demolish N403E 0% 10 10 -66 07-Aug-23 18-Aug-23 04-May-23 18-May-23
DEMO1500 Demolish Building 283 0% 10 10 -66 07-Aug-23 18-Aug-23 04-May-23 18-May-23
OptionsOptions 0% 10 10 99 13-Sep-22 26-Sep-22 27-Jan-23 10-Feb-23
Option 1 - Aluminum SunshadesOption 1 - Aluminum Sunshades 0% 10 10 99 13-Sep-22 26-Sep-22 27-Jan-23 10-Feb-23
OPT1000 Install Aluminum Sunshades 0% 10 10 99 13-Sep-22 26-Sep-22 27-Jan-23 10-Feb-23
Project CloseoutProject Closeout 0% 80 80 -69 19-May-23 07-Sep-23 10-Feb-23 02-Jun-23
CLOSE0100 Final Building Inspection 0% 1 1 -69 19-May-23 19-May-23 10-Feb-23 13-Feb-23
CLOSE0120 Punchlist Corrections 0% 10 10 0 22-May-23 02-Jun-23 19-May-23 02-Jun-23
CLOSE0121 End User Move-In 0% 40 40 -69 22-May-23 14-Jul-23 13-Feb-23 10-Apr-23
CLOSE0130 Demolition Inspection - GC-87 0% 1 1 -69 28-Aug-23 28-Aug-23 22-May-23 23-May-23
CLOSE0131 Punchlist Corrections 0% 8 8 -69 29-Aug-23 07-Sep-23 23-May-23 02-Jun-23
CLOSE0140 Demolition Inspection - Brig Site 0% 1 1 -66 21-Aug-23 21-Aug-23 18-May-23 19-May-23
CLOSE0141 Punchlist Corrections 0% 10 10 -66 22-Aug-23 04-Sep-23 19-May-23 02-Jun-23
CLOSE0150 Demobilization 0% 1 1 -62 29-Aug-23 29-Aug-23 01-Jun-23 02-Jun-23
CLOSE0160 Closeout Documents 0% 40 40 -60 03-Jul-23 25-Aug-23 07-Apr-23 02-Jun-23
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2022 2023
Install Signage
Exterior Fencing & Fixtures
27-Apr-23, Electrical
Under Slab Electrical Rough-in
Exterior Wall Rough-in
Interior Wall Rough-in
Interior Branch Wiring
Exterior Electrical Trim-Out
Exterior Lighting
Interior Electrical Trim-Out
Interior Lighting
Install Switch
Install Transformer
Generator Placement
Generator Connections
Generator Startup
Lightning Protection
Communications Raceway
Set Communications Racks
Install Communications Cable
Terminate & Test Communications
30-Dec-22, Mechanical
Mechanical Ductwork Install
Install VAVs
Install FCUs
Install AHU-1
Install AHU-2
Install Chiller
Controls Rough-In
Controls Cabling
Controls Termination
Controls Testing
Install GRDs
14-Apr-23, Plumbing
Under Slab Plumbing Rough-In
In-Wall Plumbing Rough-In
Set Plumbing Fixtures
Install Water Heaters & Equipment
Plumbing Trim Out
02-May-23, Fire Alarm
Fire Alarm Rough-in
Fire Alarm Cabling
Fire Alarm Device Trim-out
Fire Alarm Panel Connections
Fire Alarm Testing
20-Jan-23, Fire Suppression
Fire Sprinkler Main Runs
Install Fire Sprinkler Heads
16-Dec-22, Inspections
Air Barrier Pressure Tests
25-Aug-23, Demolition - GC87
Abatement GC87
Demolish GC87
18-Aug-23, Demolition - Brig Site
Abatement N403E
Demolish N403E
Demolish Building 283
26-Sep-22, Options
26-Sep-22, Option 1 - Aluminum Sunshades
Install Aluminum Sunshades
07-Sep-23, Project Closeout
Final Building Inspection
Punchlist Corrections
End User Move-In
Demolition Inspection - GC-87
Punchlist Corrections
Demolition Inspection - Brig Site
Punchlist Corrections
Demobilization
Closeout Documents
GTMO Working Dog Treatment Facility - Construction Classic Schedule Layout 03-Mar-22 09:14
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 3 of 3 TASK filter: All Activities
File details come from the government source that posted it. Updated .