11. NSGB WDTF Construction Schedule 03 Mar 22.pdf

PDF 732 KB Posted

Attached to
Veterinary Clinic IO Project - Guantanamo Bay
Solicitation number
W9127S22Q6004
Issued by

About this file

This special notice document announces an upcoming solicitation for an initial outfitting project for a Veterinary Clinic Military Working Dog Treatment Facility at Naval Station Guantanamo Bay, Cuba. The requirement will be set aside for small businesses only, with a NAICS code of 337127 and size standard of 500 employees. The estimated contract value is between $1-3 million. The simplified acquisition procedures of FAR Part 13 will be used along with commercial item procedures of FAR Part 12. The proposal due date is expected to be August 31, 2022. The OFB goal date is December 31, 2023. ProjNet will be open for questions from August 3-15, 2022 regarding this requirement.

View the file

Other files

File Type Posted
22. Facility Related Control Systems Overlay_FINAL (FOUO).pdf PDF
7. NSGB WDTF - FINAL DWGS SIGNED gov.pdf PDF
17. Example Generic ICS Med-COI Boundary Diagram v4-1.pdf PDF
13. GTMO WDTF Existing Inventory (G) 7 Apr 2022.xlsx XLSX spreadsheet
19. FRCS-VRA Ver 2.0.docx DOCX document
2. NSGB WDTF Haul Route_USNH to Landfill 15 Mar 22.pdf PDF
6. NSGB WDTF - BASIS OF DESIGN - FIO MAY 2021.pdf PDF
24. Refrigerator Monitoring Systems.pdf PDF
20. DHA MDE Categorization Memo.pdf PDF
14. DHA FRCS Baseline Categorization Memorandum-1 October 2020 (1).pdf PDF
9. NSGB WDTF - FINAL SUBMITTAL SID_VOL_II_BUNDLED - FIO.pdf PDF
16. DHA System-Level Continuous Monitoring Plan 23MAY2018.xlsx XLSX spreadsheet
3 Standard Notices (UEI PIEE NIST) For Industry.docx DOCX document
16. DHA System-Level Continuous Monitoring Plan 23MAY2018.pdf PDF
9. NSGB WDTF - FINAL SUBMITTAL SID_VOL_I_BUNDLED - FIO.pdf PDF
0. SOW-FY22 Guantanamo Bay Veterinary Clinic IOT-18 Jul 22.docx DOCX document
25. Audio Video Conferencing.pdf PDF
1. NSGB WDTF Haul Route_Port to USNH 15 Mar 22.pdf PDF
18. FRCS FAT SAT Checklist.pdf PDF
IO Eval Criteria GTMO WDTF.docx DOCX document
8. NSGB WDTF - Artwork Placement Plan - 01 JAN 19.pdf PDF
15. Draft DHA PM Standard Isolation Architecture for Cybersecurity of FRCS.DOCX DOCX document
00. FY22 NSGB WDTF_Div 00_CLIN Schedule_USACE.xlsx XLSX spreadsheet
23. Patient Monitoring and Telemetry System.pdf PDF
21. PIA Processes and Procedures.docx DOCX document
5. Guantanamo WDTF IO Project Status Report (PSR) 5 Apr 22.xlsx XLSX spreadsheet
10. NSGB WDTF - FINAL SUBMITTAL CID VOL1_AND_VOL2 - FIO 07 MAR 19.pdf PDF
12. NSGB WDTF - Medical Equipment - BASIS FOR BID - RPIE Removed 04 Apr 22.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Duration %

Complete

Original

Duration

Remaining

Duration

Total

Float

Start Finish Late Start Late Finish

GTMO Working Dog Treatment Facility - Construction Schedule Update - February 2022GTMO Working Dog Treatment Facility - Construction Schedule Update - February 202237.28% 636 399 -69 25-Aug-21 A 07-Sep-23 22-Nov-21 02-Jun-23

A1000 Contract Award 100% 0 0 25-Aug-21 A 10-Dec-21

A1010 Projected Completion 0% 0 0 -69 07-Sep-23 02-Jun-23

A1020 Contract Completion Date 0% 0 0 0 02-Jun-23* 02-Jun-23

PreconstructionPreconstruction 62.46% 213 80 250 25-Aug-21 A 17-Jun-22 10-Dec-21 02-Jun-23

PRECON1000 Project Preconstruction Meeting 100% 15 0 28-Sep-21 A 28-Sep-21 A 17-Jan-22 17-Jan-22

SubmittalsSubmittals 0% 60 60 270 25-Aug-21 A 20-May-22 10-Dec-21 02-Jun-23

SUB1000 Submit List of Contract Personnel 100% 30 0 25-Aug-21 A 07-Oct-21 A 02-Jun-23 02-Jun-23

SUB1010 Submit Earned Value Report 100% 30 0 25-Aug-21 A 27-Oct-21 A 02-Jun-23 02-Jun-23

SUB1020 Submit Bond 100% 10 0 25-Aug-21 A 07-Sep-21 A 02-Jun-23 02-Jun-23

SUB1030 Submit Project Schedule 100% 30 0 25-Aug-21 A 27-Oct-21 A 02-Jun-23 02-Jun-23

SUB1040 Submit Accident Prevention Plan 100% 40 0 25-Aug-21 A 30-Sep-21 A 02-Jun-23 02-Jun-23

SUB1050 Submit Quality Control Plan 100% 40 0 25-Aug-21 A 07-Oct-21 A 02-Jun-23 02-Jun-23

SUB1060 Submit Environmental Protection Plan 100% 40 0 25-Aug-21 A 05-Oct-21 A 02-Jun-23 02-Jun-23

SUB1080 Submit Concrete & Accessories Product Data 100% 10 0 25-Aug-21 A 22-Nov-21 A 16-Dec-21 16-Dec-21

SUB1090 Submit Masonry & Accessories Product Data 100% 5 0 25-Aug-21 A 18-Oct-21 A 20-Dec-21 20-Dec-21

SUB1100 Submit Metal Trusses Product Data 100% 20 0 25-Aug-21 A 22-Dec-21 A 25-Feb-22 25-Feb-22

SUB1110 Submit Structural Steel Product Data 100% 20 0 25-Aug-21 A 03-Nov-21 A 25-Feb-22 25-Feb-22

SUB1120 Submit Metal Roofing Product Data 100% 20 0 25-Aug-21 A 22-Feb-22 A 08-Apr-22 08-Apr-22

SUB1130 Submit Doors, Frames, & Hardware Product Data 0% 60 60 -10 25-Aug-21 A 20-May-22 11-Feb-22 06-May-22

SUB1140 Submit Glazing Product Data 0% 60 60 -30 25-Aug-21 A 20-May-22 14-Jan-22 08-Apr-22

SUB1150 Submit Framing & Drywall Product Data 0% 40 40 21 25-Aug-21 A 22-Apr-22 28-Mar-22 23-May-22

SUB1160 Submit Flooring Product Data 0% 40 40 114 25-Aug-21 A 22-Apr-22 04-Aug-22 29-Sep-22

SUB1170 Submit Paint Product Data 0% 40 40 106 25-Aug-21 A 22-Apr-22 25-Jul-22 19-Sep-22

SUB1180 Submit Specialties Product Data 0% 40 40 109 25-Aug-21 A 22-Apr-22 28-Jul-22 22-Sep-22

SUB1190 Submit Aluminum Canopy Product Data 0% 60 60 99 25-Aug-21 A 20-May-22 14-Jul-22 06-Oct-22

SUB1200 Submit Equipment Product Data 0% 60 60 94 25-Aug-21 A 20-May-22 07-Jul-22 29-Sep-22

SUB1210 Submit Fire Suppression Product Data 0% 60 60 54 25-Aug-21 A 20-May-22 12-May-22 04-Aug-22

SUB1220 Submit Plumbing & Utilities Product Data 0% 5 5 -45 25-Aug-21 A 04-Mar-22 24-Dec-21 31-Dec-21

SUB1230 Submit HVAC Product Data 0% 20 20 24 25-Aug-21 A 25-Mar-22 31-Mar-22 28-Apr-22

SUB1240 Submit Controls Product Data 0% 20 20 30 25-Aug-21 A 25-Mar-22 08-Apr-22 06-May-22

SUB1250 Submit Electrical Product Data 0% 10 10 -55 25-Aug-21 A 11-Mar-22 10-Dec-21 24-Dec-21

SUB1260 Submit Fencing, Gates, & Landscaping Product Data 0% 60 60 250 25-Aug-21 A 20-May-22 13-Feb-23 05-May-23

SUB1270 Submit Millwork Shop Drawings 100% 60 0 25-Aug-21 A 22-Feb-22 A 20-Oct-22 20-Oct-22

Review & Approve SubmittalsReview & Approve Submittals 60.62% 203 80 250 08-Sep-21 A 17-Jun-22 16-Dec-21 02-Jun-23

APPSUB1000 Review & Approve List of Contract Personnel 100% 20 0 07-Oct-21 A 08-Oct-21 A 02-Jun-23 02-Jun-23

APPSUB1010 Review & Approve Earned Value Report 100% 20 0 27-Oct-21 A 08-Nov-21 A 02-Jun-23 02-Jun-23

APPSUB1020 Review & Approve Bond 100% 20 0 08-Sep-21 A 13-Sep-21 A 02-Jun-23 02-Jun-23

APPSUB1030 Review & Approve Project Schedule 100% 20 0 27-Oct-21 A 08-Nov-21 A 02-Jun-23 02-Jun-23

APPSUB1040 Review & Approve Accident Prevention Plan 100% 20 0 30-Sep-21 A 08-Nov-21 A 02-Jun-23 02-Jun-23

APPSUB1050 Review & Approve Quality Control Plan 100% 20 0 07-Oct-21 A 08-Nov-21 A 02-Jun-23 02-Jun-23

APPSUB1060 Review & Approve Environmental Protection Plan 100% 20 0 05-Oct-21 A 23-Nov-21 A 02-Jun-23 02-Jun-23

APPSUB1070 Review & Approve Concrete & Accessories Product Data 100% 20 0 15-Nov-21 A 08-Dec-21 A 16-Dec-21 16-Dec-21

APPSUB1080 Review & Approve Masonry & Accessories Product Data 100% 20 0 18-Oct-21 A 15-Nov-21 A 20-Dec-21 20-Dec-21

APPSUB1090 Review & Approve Metal Trusses Product Data 50% 20 10 0 22-Dec-21 A 11-Mar-22 25-Feb-22 11-Mar-22

APPSUB1100 Review & Approve Structura l Steel Product Data 100% 20 0 03-Nov-21 A 09-Nov-21 A 25-Feb-22 25-Feb-22

APPSUB1110 Review & Approve Metal Roofing Product Data 50% 20 10 30 22-Feb-22 A 11-Mar-22 08-Apr-22 22-Apr-22

APPSUB1120 Review & Approve Doors, Frames, & Hardware Product Data 0% 20 20 -10 23-May-22 17-Jun-22 06-May-22 03-Jun-22

APPSUB1130 Review & Approve Glazing Product Data 0% 20 20 -30 23-May-22 17-Jun-22 08-Apr-22 06-May-22

APPSUB1140 Review & Approve Framing & Drywall Product Data 0% 20 20 21 25-Apr-22 20-May-22 23-May-22 20-Jun-22

APPSUB1150 Review & Approve Flooring Product Data 0% 20 20 114 25-Apr-22 20-May-22 29-Sep-22 27-Oct-22

APPSUB1160 Review & Approve Paint Product Data 0% 20 20 106 25-Apr-22 20-May-22 19-Sep-22 17-Oct-22

APPSUB1170 Review & Approve Specialties Product Data 0% 20 20 109 25-Apr-22 20-May-22 22-Sep-22 20-Oct-22

APPSUB1180 Review & Approve Aluminum Canopy Product Data 0% 20 20 99 23-May-22 17-Jun-22 06-Oct-22 03-Nov-22

APPSUB1190 Review & Approve Equipment Product Data 0% 20 20 94 23-May-22 17-Jun-22 29-Sep-22 27-Oct-22

APPSUB1200 Review & Approve Fire Suppression Product Data 0% 20 20 54 23-May-22 17-Jun-22 04-Aug-22 01-Sep-22

APPSUB1210 Review & Approve Plumbing & Utilities Product Data 0% 20 20 -45 07-Mar-22 01-Apr-22 31-Dec-21 28-Jan-22

APPSUB1220 Review & Approve HVAC Product Data 0% 20 20 24 28-Mar-22 22-Apr-22 28-Apr-22 26-May-22

APPSUB1230 Review & Approve Controls Product Data 0% 20 20 30 28-Mar-22 22-Apr-22 06-May-22 03-Jun-22

APPSUB1240 Review & Approve Electrica l Product Data 0% 20 20 -55 14-Mar-22 08-Apr-22 24-Dec-21 21-Jan-22

APPSUB1250 Review & Approve Fencing, Gates, & Landscaping Product Data0% 20 20 250 23-May-22 17-Jun-22 08-May-23 02-Jun-23

APPSUB1260 Review & Approve Millwork Shop Drawings 100% 20 0 169 22-Feb-22 A 28-Feb-22 20-Oct-22 20-Oct-22

APPSUB2200 Submittals Complete 0% 0 0 250 17-Jun-22 02-Jun-23

ProcurementProcurement 25.97% 231 171 74 02-Nov-21 A 24-Oct-22 16-Dec-21 03-Feb-23

PRO1000 Procure Concrete Reinforcement & Accessories 0% 20 21 -51 02-Nov-21 A 28-Mar-22 16-Dec-21 14-Jan-22

PRO1001 Receive Concrete Reinforcement & Accessories 0% 1 1 -51 29-Mar-22 29-Mar-22 14-Jan-22 17-Jan-22

PRO1010 Procure Masonry & Accessories 50% 40 20 -49 15-Nov-21 A 25-Mar-22 20-Dec-21 17-Jan-22

PRO1011 Receive Masonry & Accessories 0% 1 0 -49 28-Mar-22 28-Mar-22 17-Jan-22 17-Jan-22

PRO1020 Procure Metal Trusses 0% 60 60 0 14-Mar-22 03-Jun-22 11-Mar-22 03-Jun-22

PRO1021 Receive Metal Trusses 0% 1 1 0 06-Jun-22 06-Jun-22 03-Jun-22 06-Jun-22

PRO1030 Procure Structural Steel 0% 60 60 5 28-Feb-22 20-May-22 04-Mar-22 27-May-22

PRO1031 Receive Structural Steel 0% 1 1 5 23-May-22 23-May-22 27-May-22 30-May-22

PRO1032 Procure Steel Embeds 0% 40 40 0 28-Feb-22 22-Apr-22 25-Feb-22 22-Apr-22

PRO1033 Receive Steel Embeds 0% 1 1 0 25-Apr-22 25-Apr-22 22-Apr-22 25-Apr-22

PRO1040 Procure Metal Roofing 0% 60 60 30 14-Mar-22 03-Jun-22 22-Apr-22 15-Jul-22

PRO1041 Receive Metal Roofing 0% 1 1 30 06-Jun-22 06-Jun-22 15-Jul-22 18-Jul-22

PRO1050 Procure Door Frames 0% 40 40 -10 20-Jun-22 12-Aug-22 03-Jun-22 29-Jul-22

PRO1051 Receive Door Frames 0% 1 1 -10 15-Aug-22 15-Aug-22 29-Jul-22 01-Aug-22

PRO1060 Procure Doors & Hardware 0% 40 40 -5 20-Jun-22 12-Aug-22 10-Jun-22 05-Aug-22

PRO1061 Receive Doors & Hardware 0% 1 1 -5 15-Aug-22 15-Aug-22 05-Aug-22 08-Aug-22

PRO1070 Procure Glazing 0% 60 60 -30 20-Jun-22 09-Sep-22 06-May-22 29-Jul-22

PRO1071 Receive Glazing 0% 1 1 -30 12-Sep-22 12-Sep-22 29-Jul-22 01-Aug-22

PRO1080 Procure Framing & Drywall 0% 20 20 21 23-May-22 17-Jun-22 20-Jun-22 18-Jul-22

PRO1081 Receive Framing & Drywall 0% 1 1 21 20-Jun-22 20-Jun-22 18-Jul-22 19-Jul-22

PRO1090 Procure Flooring 0% 40 40 114 23-May-22 15-Jul-22 27-Oct-22 22-Dec-22

PRO1091 Receive Flooring 0% 1 1 114 18-Jul-22 18-Jul-22 22-Dec-22 23-Dec-22

PRO1100 Procure Paint 0% 20 20 106 23-May-22 17-Jun-22 17-Oct-22 14-Nov-22

PRO1101 Receive Paint 0% 1 1 106 20-Jun-22 20-Jun-22 14-Nov-22 15-Nov-22

PRO1110 Procure Specialties 0% 60 60 109 23-May-22 12-Aug-22 20-Oct-22 12-Jan-23

PRO1111 Receive Specialties 0% 1 1 109 15-Aug-22 15-Aug-22 12-Jan-23 13-Jan-23

PRO1120 Procure Aluminum Canopies 0% 60 60 99 20-Jun-22 09-Sep-22 03-Nov-22 26-Jan-23

PRO1121 Receive Aluminum Canopies 0% 1 1 99 12-Sep-22 12-Sep-22 26-Jan-23 27-Jan-23

PRO1130 Procure Equipment 0% 60 60 94 20-Jun-22 09-Sep-22 27-Oct-22 19-Jan-23

PRO1131 Receive Equipment 0% 1 1 94 12-Sep-22 12-Sep-22 19-Jan-23 20-Jan-23

PRO1140 Procure Fire Suppression Material 0% 60 60 54 20-Jun-22 09-Sep-22 01-Sep-22 24-Nov-22

PRO1141 Receive Fire Suppression Material 0% 1 1 54 12-Sep-22 12-Sep-22 24-Nov-22 25-Nov-22

PRO1150 Procure Utilities Material 0% 50 50 -45 20-Jan-22 A 10-Jun-22 28-Jan-22 08-Apr-22

PRO1151 Receive Utilities Material 0% 1 1 -45 13-Jun-22 13-Jun-22 08-Apr-22 11-Apr-22

PRO1160 Procure Plumbing Material 0% 60 60 40 04-Apr-22 24-Jun-22 27-May-22 19-Aug-22

PRO1161 Receive Plumbing Material 0% 1 1 40 27-Jun-22 27-Jun-22 19-Aug-22 22-Aug-22

PRO1171 Procure AHU-1 0% 130 130 24 25-Jan-22 A 21-Oct-22 26-May-22 24-Nov-22

PRO1181 Receive AHU-1 0% 1 1 24 24-Oct-22 24-Oct-22 24-Nov-22 25-Nov-22

PRO1191 Procure AHU-2 0% 130 130 24 25-Jan-22 A 21-Oct-22 26-May-22 24-Nov-22

PRO1201 Receive AHU-2 0% 1 1 24 24-Oct-22 24-Oct-22 24-Nov-22 25-Nov-22

PRO1202 Procure Chiller 0% 105 105 84 25-Apr-22 16-Sep-22 18-Aug-22 12-Jan-23

PRO1203 Receive Chiller 0% 1 1 84 19-Sep-22 19-Sep-22 12-Jan-23 13-Jan-23

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

2022 2023

07-Sep-23, GTMO Working Dog Treatment Facility - Construction Schedule Update - February 2022

Projected Completion

Contract Completion Date

17-Jun-22, Preconstruction

20-May-22, Submittals

Submit List of Contract Personnel

Submit Earned Value Report

Submit Project Schedule

Submit Environmental Protection Plan

Submit Concrete & Accessories Product Data

Submit Masonry & Accessories Product Data

Submit Metal Trusses Product Data

Submit Structural Steel Product Data

Submit Metal Roofing Product Data

Submit Doors, Frames, & Hardware Product Data

Submit Glazing Product Data

Submit Framing & Drywall Product Data

Submit Flooring Product Data

Submit Paint Product Data

Submit Specialties Product Data

Submit Aluminum Canopy Product Data

Submit Equipment Product Data

Submit Fire Suppression Product Data

Submit Plumbing & Utilities Product Data

Submit HVAC Product Data

Submit Controls Product Data

Submit Electrical Product Data

Submit Fencing, Gates, & Landscaping Product Data

Submit Millwork Shop Drawings

17-Jun-22, Review & Approve Submittals

Review & Approve List of Contract Personnel

Review & Approve Earned Value Report

Review & Approve Project Schedule

Review & Approve Accident Prevention Plan

Review & Approve Quality Control Plan

Review & Approve Environmental Protection Plan

Review & Approve Concrete & Accessories Product Data

Review & Approve Masonry & Accessories Product Data

Review & Approve Metal Trusses Product Data

Review & Approve Structural Steel Product Data

Review & Approve Metal Roofing Product Data

Review & Approve Doors, Frames, & Hardware Product Data

Review & Approve Glazing Product Data

Review & Approve Framing & Drywall Product Data

Review & Approve Flooring Product Data

Review & Approve Paint Product Data

Review & Approve Specialties Product Data

Review & Approve Aluminum Canopy Product Data

Review & Approve Equipment Product Data

Review & Approve Fire Suppression Product Data

Review & Approve Plumbing & Utilities Product Data

Review & Approve HVAC Product Data

Review & Approve Controls Product Data

Review & Approve Electrica l Product Data

Review & Approve Fencing, Gates, & Landscaping Product Data

Review & Approve Millwork Shop Drawings

Submittals Complete

24-Oct-22, Procurement

Procure Concrete Reinforcement & Accessories

Receive Concrete Reinforcement & Accessories

Procure Masonry & Accessories

Receive Masonry & Accessories

Procure Metal Trusses

Receive Metal Trusses

Procure Structural Steel

Receive Structural Steel

Procure Steel Embeds

Receive Steel Embeds

Procure Metal Roofing

Receive Metal Roofing

Procure Door Frames

Receive Door Frames

Procure Doors & Hardware

Receive Doors & Hardware

Procure Glazing

Receive Glazing

Procure Framing & Drywall

Receive Framing & Drywall

Procure Flooring

Receive Flooring

Procure Paint

Receive Paint

Procure Specialties

Receive Specialties

Procure Aluminum Canopies

Receive Aluminum Canopies

Procure Equipment

Receive Equipment

Procure Fire Suppression Material

Receive Fire Suppression Material

Procure Utilities Material

Receive Utilities Material

Procure Plumbing Material

Receive Plumbing Material

Procure AHU-1

Receive AHU-1

Procure AHU-2

Receive AHU-2

Procure Chiller

Receive Chiller

GTMO Working Dog Treatment Facility - Construction Classic Schedule Layout 03-Mar-22 09:14

Actual Work

Remaining Work

Critical Remaining W...

Milestone

Page 1 of 3 TASK filter: All Activities

© Oracle Corporation

Original

Duration

Remaining

Duration

Total

Float

Start Finish Late Start Late Finish

PRO1211 Procure VAVs 0% 60 60 25 25-Apr-22 15-Jul-22 27-May-22 19-Aug-22

PRO1221 Receive VAVs 0% 1 1 25 18-Jul-22 18-Jul-22 19-Aug-22 22-Aug-22

PRO1231 Procure FCUs 0% 50 50 149 25-Apr-22 01-Jul-22 17-Nov-22 26-Jan-23

PRO1241 Receive FCUs 0% 1 1 149 04-Jul-22 04-Jul-22 26-Jan-23 27-Jan-23

PRO1251 Procure Ductwork & Accessories 0% 60 60 25 25-Apr-22 15-Jul-22 27-May-22 19-Aug-22

PRO1261 Receive Ductwork & Accessories 0% 1 1 25 18-Jul-22 18-Jul-22 19-Aug-22 22-Aug-22

PRO1271 Procure Controls Materials 0% 60 60 30 25-Apr-22 15-Jul-22 03-Jun-22 26-Aug-22

PRO1281 Receive Controls Materials 0% 1 1 30 18-Jul-22 18-Jul-22 26-Aug-22 29-Aug-22

PRO1291 Procure Electrical Rough Material 0% 40 40 -55 11-Apr-22 03-Jun-22 21-Jan-22 18-Mar-22

PRO1301 Receive Electrical Rough Material 0% 1 1 -55 06-Jun-22 06-Jun-22 18-Mar-22 21-Mar-22

PRO1311 Procure Electrical Gear 0% 80 80 72 11-Apr-22 29-Jul-22 19-Jul-22 08-Nov-22

PRO1312 Receive Electrical Gear 0% 1 1 72 01-Aug-22 01-Aug-22 08-Nov-22 09-Nov-22

PRO1322 Procure Switch & Transformer 0% 140 140 74 11-Apr-22 21-Oct-22 21-Jul-22 02-Feb-23

PRO1323 Receive Switch & Transformer 0% 1 1 74 24-Oct-22 24-Oct-22 02-Feb-23 03-Feb-23

PRO1331 Procure Generator 0% 100 100 106 11-Apr-22 26-Aug-22 05-Sep-22 23-Jan-23

PRO1341 Receive Generator 0% 1 1 106 29-Aug-22 29-Aug-22 23-Jan-23 24-Jan-23

PRO1351 Procure Lighting & Trim 0% 60 60 115 11-Apr-22 01-Jul-22 16-Sep-22 09-Dec-22

PRO1361 Receive Lighting & Trim 0% 1 1 115 04-Jul-22 04-Jul-22 09-Dec-22 12-Dec-22

PRO1371 Procure Millwork 0% 60 60 169 28-Feb-22 20-May-22 20-Oct-22 12-Jan-23

PRO1381 Receive Millwork 0% 1 1 169 23-May-22 23-May-22 12-Jan-23 13-Jan-23

PRO1391 Procure Fire Alarm Material 0% 70 70 132 11-Apr-22 15-Jul-22 11-Oct-22 17-Jan-23

PRO1401 Receive Fire Alarm Materia l 0% 1 1 132 18-Jul-22 18-Jul-22 17-Jan-23 18-Jan-23

PRO1411 Procure Fences & Gates 0% 60 60 114 23-May-22 12-Aug-22 27-Oct-22 19-Jan-23

PRO1421 Receive Fences & Gates 0% 1 1 114 15-Aug-22 15-Aug-22 19-Jan-23 20-Jan-23

ImpactsImpacts 33.33% 60 40 -69 31-Jan-22 A 22-Apr-22 22-Nov-21 17-Jan-22

COVID QuarantineCOVID Quarantine 33.33% 60 40 -69 31-Jan-22 A 22-Apr-22 22-Nov-21 17-Jan-22

IN0010 COVID Quarantine Impact 33.33% 60 40 -69 31-Jan-22 A 22-Apr-22 22-Nov-21 17-Jan-22

ConstructionConstruction 0% 350 350 -60 25-Apr-22 25-Aug-23 17-Jan-22 02-Jun-23

CON0100 Mobilize 0% 1 0 -69 25-Apr-22 25-Apr-22 17-Jan-22 17-Jan-22

CON0110 Building Dry-In 0% 0 0 -69 25-Nov-22 22-Aug-22

CON0120 Beneficial Occupancy Date 0% 0 0 10 19-May-23 02-Jun-23

Site Demolition/EarthworkSite Demolition/Earthwork 0% 45 45 -69 25-Apr-22 24-Jun-22 17-Jan-22 21-Mar-22

CON0200 Site Demolition 0% 10 10 -69 25-Apr-22 06-May-22 17-Jan-22 31-Jan-22

CON0210 Rough Grading 0% 10 10 -69 09-May-22 20-May-22 31-Jan-22 14-Feb-22

CON0220 Excavate Footings 0% 5 5 -69 23-May-22 27-May-22 14-Feb-22 21-Feb-22

CON0230 Backfill 0% 5 5 -69 20-Jun-22 24-Jun-22 14-Mar-22 21-Mar-22

Foundation/ConcreteFoundation/Concrete 0% 140 140 32 30-May-22 09-Dec-22 21-Feb-22 24-Jan-23

CON0300 Form/Place Footings 0% 5 5 -69 30-May-22 03-Jun-22 21-Feb-22 28-Feb-22

CON0310 Cure Footings 0% 5 5 -69 06-Jun-22 10-Jun-22 28-Feb-22 07-Mar-22

CON0320 Form/Place Slab 0% 5 5 -69 18-Jul-22 22-Jul-22 11-Apr-22 18-Apr-22

CON0330 Cure Slab 0% 5 5 -69 25-Jul-22 29-Jul-22 18-Apr-22 25-Apr-22

CON0340 Form/Place Site Concrete 0% 5 5 30 28-Nov-22 02-Dec-22 06-Jan-23 13-Jan-23

CON0350 Cure Site Concrete 0% 5 5 30 05-Dec-22 09-Dec-22 13-Jan-23 20-Jan-23

CON0360 Form/Place Exterior Utility Pads 0% 5 5 117 01-Aug-22 05-Aug-22 10-Jan-23 17-Jan-23

CON0370 Cure Exterior Utility Pads 0% 5 5 117 08-Aug-22 12-Aug-22 17-Jan-23 24-Jan-23

Site UtilitiesSite Utilities 0% 80 80 99 07-Jun-22 26-Sep-22 02-Nov-22 10-Feb-23

CON0400 Underground Plumbing 0% 20 20 144 28-Jun-22 25-Jul-22 13-Jan-23 10-Feb-23

CON0410 Underground Sanitary Sewer 0% 20 20 154 14-Jun-22 11-Jul-22 13-Jan-23 10-Feb-23

CON0420 Underground Storm Drainage 0% 20 20 154 14-Jun-22 11-Jul-22 13-Jan-23 10-Feb-23

CON0430 Underground Electrical Raceway 0% 20 20 99 02-Aug-22 29-Aug-22 16-Dec-22 13-Jan-23

CON0431 Underground Electrical Conductors 0% 20 20 99 30-Aug-22 26-Sep-22 13-Jan-23 10-Feb-23

CON0440 Underground Telecom W iring 0% 20 20 139 05-Jul-22 01-Aug-22 13-Jan-23 10-Feb-23

CON0450 Underground CCTV Cable to Hospital 0% 20 20 107 05-Jul-22 01-Aug-22 30-Nov-22 28-Dec-22

CON0460 Underground Comm Raceway 0% 20 20 107 07-Jun-22 04-Jul-22 02-Nov-22 30-Nov-22

MasonryMasonry 0% 65 65 47 13-Jun-22 09-Sep-22 07-Mar-22 15-Nov-22

CON0500 Install Foundation Walls 0% 5 5 -69 13-Jun-22 17-Jun-22 07-Mar-22 14-Mar-22

CON0510 Install Exterior CMU Walls 0% 30 30 -69 01-Aug-22 09-Sep-22 25-Apr-22 06-Jun-22

CON0520 Install Interior CMU Walls 0% 5 5 72 01-Aug-22 05-Aug-22 08-Nov-22 15-Nov-22

Structural SteelStructural Steel 0% 86 86 24 08-Aug-22 05-Dec-22 30-May-22 06-Jan-23

CON0600 Set Structural Steel Posts 0% 5 5 -49 08-Aug-22 12-Aug-22 30-May-22 06-Jun-22

CON0610 Install Steel Trusses Area 1A 0% 15 15 -69 12-Sep-22 30-Sep-22 06-Jun-22 27-Jun-22

CON0620 Install Metal Deck Area 1A 0% 15 15 -69 03-Oct-22 21-Oct-22 27-Jun-22 18-Jul-22

CON0630 Install Steel Trusses Area 1B 0% 10 10 24 08-Nov-22 21-Nov-22 09-Dec-22 23-Dec-22

CON0640 Install Metal Deck Area 1B 0% 10 10 24 22-Nov-22 05-Dec-22 23-Dec-22 06-Jan-23

Roofing & InsulationRoofing & Insulation 0% 46 46 34 24-Oct-22 26-Dec-22 18-Jul-22 10-Feb-23

CON0700 Install Insulation - 1A 0% 10 10 -69 24-Oct-22 04-Nov-22 18-Jul-22 01-Aug-22

CON0701 Install Insulation - 1B 0% 5 5 24 06-Dec-22 12-Dec-22 06-Jan-23 13-Jan-23

CON0710 Install Standing Seam Roof - 1A 0% 15 15 -69 07-Nov-22 25-Nov-22 01-Aug-22 22-Aug-22

CON0720 Install Standing Seam Roof - 1B 0% 5 5 24 13-Dec-22 19-Dec-22 13-Jan-23 20-Jan-23

CON0730 Install Gutter 0% 5 5 34 20-Dec-22 26-Dec-22 03-Feb-23 10-Feb-23

Windows & StorefrontWindows & Storefront 0% 15 15 -30 13-Sep-22 03-Oct-22 01-Aug-22 22-Aug-22

CON0800 Install Unit Window Framing 0% 10 10 -30 13-Sep-22 26-Sep-22 01-Aug-22 15-Aug-22

CON0810 Install Unit Window Glazing 0% 5 5 -30 27-Sep-22 03-Oct-22 15-Aug-22 22-Aug-22

CON0820 Install Storefront Framing 0% 10 10 -30 13-Sep-22 26-Sep-22 01-Aug-22 15-Aug-22

CON0830 Install Storefront Glazing 0% 5 5 -30 27-Sep-22 03-Oct-22 15-Aug-22 22-Aug-22

Interior Framing & InsulationInterior Framing & Insulation 0% 50 50 -69 24-Oct-22 30-Dec-22 19-Jul-22 26-Sep-22

CON0900 Frame Interior Walls 0% 29 29 -68 24-Oct-22 01-Dec-22 19-Jul-22 29-Aug-22

CON0910 Spray Foam Insulation (exterior walls) 0% 10 10 -59 28-Nov-22 09-Dec-22 05-Sep-22 19-Sep-22

CON0920 Interior Wall Insulation 0% 5 5 -63 16-Dec-22 22-Dec-22 19-Sep-22 26-Sep-22

CON0930 Ceiling Insulation 0% 10 10 -69 19-Dec-22 30-Dec-22 12-Sep-22 26-Sep-22

FinishesFinishes 0% 84 84 -54 02-Jan-23 27-Apr-23 26-Sep-22 10-Feb-23

CON1000 Install Drywall 0% 49 49 -69 02-Jan-23 09-Mar-23 26-Sep-22 02-Dec-22

CON1010 Interior Painting 0% 19 19 -69 21-Feb-23 17-Mar-23 15-Nov-22 12-Dec-22

CON1020 Epoxy Flooring 0% 15 15 -60 20-Mar-23 07-Apr-23 23-Dec-22 13-Jan-23

CON1030 Resilient Tile Flooring 0% 10 10 -55 20-Mar-23 31-Mar-23 30-Dec-22 13-Jan-23

CON1040 Ceramic Tile Flooring 0% 10 10 -55 20-Mar-23 31-Mar-23 30-Dec-22 13-Jan-23

CON1050 Wall Tile 0% 10 10 -55 20-Mar-23 31-Mar-23 30-Dec-22 13-Jan-23

CON1060 Acoustic Ceiling 0% 15 15 -69 07-Apr-23 27-Apr-23 30-Dec-22 20-Jan-23

CON1070 Acoustic Panels 0% 5 5 -30 20-Mar-23 24-Mar-23 03-Feb-23 10-Feb-23

Doors, Frames, & HardwareDoors, Frames, & Hardware 0% 158 158 -29 16-Aug-22 23-Mar-23 01-Aug-22 10-Feb-23

CON1100 Install Exterior Hollow Metal Frames 0% 5 5 -10 16-Aug-22 22-Aug-22 01-Aug-22 08-Aug-22

CON1110 Install Exterior Hollow Metal Doors 0% 5 5 -10 23-Aug-22 29-Aug-22 08-Aug-22 15-Aug-22

CON1120 Install Interior Frames 0% 5 5 -48 25-Nov-22 01-Dec-22 19-Sep-22 26-Sep-22

CON1130 Install Interior Doors 0% 5 5 -29 03-Mar-23 09-Mar-23 20-Jan-23 27-Jan-23

CON1140 Install Exterior Hardware 0% 5 5 114 30-Aug-22 05-Sep-22 03-Feb-23 10-Feb-23

CON1150 Install Interior Hardware 0% 10 10 -29 10-Mar-23 23-Mar-23 27-Jan-23 10-Feb-23

CON1160 Install Exterior Hollow Metal Glazing 0% 5 5 -20 13-Sep-22 19-Sep-22 15-Aug-22 22-Aug-22

CON1161 Install Interior Hollow Metal Glazing 0% 5 5 -24 10-Mar-23 16-Mar-23 03-Feb-23 10-Feb-23

CON1170 Install X-Ray Door & Hardware 0% 5 5 -24 10-Mar-23 16-Mar-23 03-Feb-23 10-Feb-23

MillworkMillwork 0% 20 20 -69 21-Apr-23 18-May-23 13-Jan-23 10-Feb-23

CON1200 Install Millwork 0% 20 20 -69 21-Apr-23 18-May-23 13-Jan-23 10-Feb-23

CON1210 Install Gov't Furnished Materials 0% 20 20 -69 21-Apr-23 18-May-23 13-Jan-23 10-Feb-23

Specialties & EquipmentSpecialties & Equipment 0% 110 110 -65 12-Dec-22 12-May-23 13-Jan-23 10-Feb-23

CON1300 Install Equipment 0% 15 15 -64 21-Apr-23 11-May-23 20-Jan-23 10-Feb-23

CON1310 Install Bathroom Specialties 0% 20 20 -65 17-Apr-23 12-May-23 13-Jan-23 10-Feb-23

CON1320 Install Miscellaneous Specialties 0% 15 15 -50 03-Apr-23 21-Apr-23 20-Jan-23 10-Feb-23

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

2022 2023

Procure VAVs

Receive VAVs

Procure FCUs

Receive FCUs

Procure Ductwork & Accessories

Receive Ductwork & Accessories

Procure Controls Materials

Receive Controls Materials

Procure Electrical Rough Material

Receive Electrical Rough Material

Procure Electrical Gear

Receive Electrical Gear

Procure Switch & Transformer

Receive Switch & Transformer

Procure Generator

Receive Generator

Procure Lighting & Trim

Receive Lighting & Trim

Procure Millwork

Receive Millwork

Procure Fire Alarm Material

Receive Fire Alarm Materia l

Procure Fences & Gates

Receive Fences & Gates

22-Apr-22, Impacts

22-Apr-22, COVID Quarantine

COVID Quarantine Impact

25-Aug-23, Construction

Mobilize

Building Dry-In

Beneficial Occupancy Date

24-Jun-22, Site Demolition/Earthwork

Site Demolition

Rough Grading

Excavate Footings

Backfill

09-Dec-22, Foundation/Concrete

Form/Place Footings

Cure Footings

Form/Place Slab

Cure Slab

Form/Place Site Concrete

Cure Site Concrete

Form/Place Exterior Utility Pads

Cure Exterior Utility Pads

26-Sep-22, Site Utilities

Underground Plumbing

Underground Sanitary Sewer

Underground Storm Drainage

Underground Electrical Raceway

Underground Electrical Conductors

Underground Telecom W iring

Underground CCTV Cable to Hospital

Underground Comm Raceway

09-Sep-22, Masonry

Install Foundation Walls

Install Exterior CMU Walls

Install Interior CMU Walls

05-Dec-22, Structural Steel

Set Structural Steel Posts

Install Steel Trusses Area 1A

Install Metal Deck Area 1A

Install Steel Trusses Area 1B

Install Metal Deck Area 1B

26-Dec-22, Roofing & Insulation

Install Insulation - 1A

Install Insulation - 1B

Install Standing Seam Roof - 1A

Install Standing Seam Roof - 1B

Install Gutter

03-Oct-22, Windows & Storefront

Install Unit Window Framing

Install Unit Window Glazing

Install Storefront Framing

Install Storefront Glazing

30-Dec-22, Interior Framing & Insulation

Frame Interior Walls

Spray Foam Insulation (exterior walls)

Interior Wall Insulation

Ceiling Insulation

27-Apr-23, Finishes

Install Drywall

Interior Painting

Epoxy Flooring

Resilient Ti le Flooring

Ceramic Tile Flooring

Wall Tile

Acoustic Ceiling

Acoustic Panels

23-Mar-23, Doors, Frames, & Hardware

Install Exterior Hollow Metal Frames

Install Exterior Hollow Metal Doors

Install Interior Frames

Install Interior Doors

Install Exterior Hardware

Install Interior Hardware

Install Exterior Hollow Metal Glazing

Install Interior Hollow Metal Glazing

Install X-Ray Door & Hardware

18-May-23, Millwork

Install Millwork

Install Gov't Furnished Materials

12-May-23, Specialties & Equipment

Install Equipment

Install Bathroom Specialties

Install Miscellaneous Specialties

GTMO Working Dog Treatment Facility - Construction Classic Schedule Layout 03-Mar-22 09:14

Actual Work

Remaining Work

Critical Remaining W...

Milestone

Page 2 of 3 TASK filter: All Activities

Original

Duration

Remaining

Duration

Total

Float

Start Finish Late Start Late Finish

CON1330 Install Signage 0% 10 10 -35 20-Mar-23 31-Mar-23 27-Jan-23 10-Feb-23

CON1340 Exterior Fencing & Fixtures 0% 15 15 30 12-Dec-22 30-Dec-22 20-Jan-23 10-Feb-23

ElectricalElectrical 0% 219 219 -54 27-Jun-22 27-Apr-23 21-Mar-22 10-Feb-23

CON1400 Under Slab Electrical Rough-in 0% 15 15 -69 27-Jun-22 15-Jul-22 21-Mar-22 11-Apr-22

CON1410 Exterior Wall Rough-in 0% 20 20 6 15-Aug-22 09-Sep-22 22-Aug-22 19-Sep-22

CON1420 Interior Wall Rough-in 0% 30 30 -68 04-Nov-22 15-Dec-22 01-Aug-22 12-Sep-22

CON1421 Interior Branch Wiring 0% 15 15 -4 16-Dec-22 05-Jan-23 09-Dec-22 30-Dec-22

CON1430 Exterior Electrical Trim-Out 0% 10 10 -35 20-Mar-23 31-Mar-23 27-Jan-23 10-Feb-23

CON1440 Exterior Lighting 0% 10 10 100 12-Sep-22 23-Sep-22 27-Jan-23 10-Feb-23

CON1450 Interior Electrical Trim-Out 0% 15 15 -55 20-Mar-23 07-Apr-23 30-Dec-22 20-Jan-23

CON1460 Interior Lighting 0% 29 29 -69 20-Mar-23 27-Apr-23 12-Dec-22 20-Jan-23

CON1461 Install Switch 0% 5 5 74 25-Oct-22 31-Oct-22 03-Feb-23 10-Feb-23

CON1462 Install Transformer 0% 5 5 74 25-Oct-22 31-Oct-22 03-Feb-23 10-Feb-23

CON1470 Generator Placement 0% 3 3 106 30-Aug-22 01-Sep-22 24-Jan-23 27-Jan-23

CON1480 Generator Connections 0% 5 5 31 16-Dec-22 22-Dec-22 27-Jan-23 03-Feb-23

CON1490 Generator Startup 0% 5 5 31 23-Dec-22 29-Dec-22 03-Feb-23 10-Feb-23

CON1500 Lightning Protection 0% 15 15 24 20-Dec-22 09-Jan-23 20-Jan-23 10-Feb-23

CON1510 Communications Raceway 0% 20 20 -58 04-Nov-22 01-Dec-22 15-Aug-22 12-Sep-22

CON1520 Set Communications Racks 0% 15 15 -16 02-Dec-22 22-Dec-22 09-Nov-22 30-Nov-22

CON1530 Install Communications Cable 0% 20 20 -16 23-Dec-22 19-Jan-23 30-Nov-22 28-Dec-22

CON1540 Terminate & Test Communications 0% 20 20 -57 20-Mar-23 14-Apr-23 28-Dec-22 25-Jan-23

MechanicalMechanical 0% 74 74 30 20-Sep-22 30-Dec-22 22-Aug-22 10-Feb-23

CON1600 Mechanical Ductwork Install 0% 15 15 -69 28-Nov-22 16-Dec-22 22-Aug-22 12-Sep-22

CON1610 Install VAVs 0% 15 15 -69 28-Nov-22 16-Dec-22 22-Aug-22 12-Sep-22

CON1620 Install FCUs 0% 10 10 45 28-Nov-22 09-Dec-22 27-Jan-23 10-Feb-23

CON1630 Install AHU-1 0% 10 10 24 25-Oct-22 07-Nov-22 25-Nov-22 09-Dec-22

CON1640 Install AHU-2 0% 10 10 24 25-Oct-22 07-Nov-22 25-Nov-22 09-Dec-22

CON1641 Install Chiller 0% 10 10 84 20-Sep-22 03-Oct-22 13-Jan-23 27-Jan-23

CON1650 Controls Rough-In 0% 10 10 -48 04-Nov-22 17-Nov-22 29-Aug-22 12-Sep-22

CON1660 Controls Cabling 0% 10 10 21 18-Nov-22 01-Dec-22 16-Dec-22 30-Dec-22

CON1670 Controls Termination 0% 5 5 41 02-Dec-22 08-Dec-22 27-Jan-23 03-Feb-23

CON1680 Controls Testing 0% 5 5 41 09-Dec-22 15-Dec-22 03-Feb-23 10-Feb-23

CON1690 Install GRDs 0% 10 10 15 19-Dec-22 30-Dec-22 06-Jan-23 20-Jan-23

PlumbingPlumbing 0% 210 210 -45 27-Jun-22 14-Apr-23 21-Mar-22 10-Feb-23

A1030 Under Slab Plumbing Rough-In 0% 15 15 -69 27-Jun-22 15-Jul-22 21-Mar-22 11-Apr-22

A1040 In-Wall Plumbing Rough-In 0% 15 15 -63 18-Nov-22 08-Dec-22 22-Aug-22 12-Sep-22

A1050 Set Plumbing Fixtures 0% 10 10 -65 20-Mar-23 31-Mar-23 16-Dec-22 30-Dec-22

A1060 Install Water Heaters & Equipment 0% 20 20 26 09-Dec-22 05-Jan-23 13-Jan-23 10-Feb-23

A1070 Plumbing Trim Out 0% 15 15 -65 27-Mar-23 14-Apr-23 23-Dec-22 13-Jan-23

Fire AlarmFire Alarm 0% 128 128 -57 04-Nov-22 02-May-23 25-Nov-22 10-Feb-23

CON1700 Fire Alarm Rough-in 0% 10 10 16 04-Nov-22 17-Nov-22 25-Nov-22 09-Dec-22

CON1710 Fire Alarm Cabling 0% 15 15 16 18-Nov-22 08-Dec-22 09-Dec-22 30-Dec-22

CON1720 Fire Alarm Device Trim-out 0% 10 10 19 09-Dec-22 22-Dec-22 04-Jan-23 18-Jan-23

CON1730 Fire Alarm Panel Connections 0% 5 5 19 23-Dec-22 29-Dec-22 18-Jan-23 25-Jan-23

CON1740 Fire Alarm Testing 0% 12 12 -57 17-Apr-23 02-May-23 25-Jan-23 10-Feb-23

Fire SuppressionFire Suppression 0% 40 40 0 28-Nov-22 20-Jan-23 25-Nov-22 20-Jan-23

CON1800 Fire Sprinkler Main Runs 0% 20 20 0 28-Nov-22 23-Dec-22 25-Nov-22 23-Dec-22

CON1810 Install Fire Sprinkler Heads 0% 20 20 0 26-Dec-22 20-Jan-23 23-Dec-22 20-Jan-23

InspectionsInspections 0% 5 5 -59 12-Dec-22 16-Dec-22 19-Sep-22 26-Sep-22

CON1900 Air Barrier Pressure Tests 0% 5 5 -59 12-Dec-22 16-Dec-22 19-Sep-22 26-Sep-22

Demolition - GC87Demolition - GC87 0% 30 30 -69 17-Jul-23 25-Aug-23 10-Apr-23 22-May-23

DEMO1000 Abatement GC87 0% 10 10 -69 17-Jul-23 28-Jul-23 10-Apr-23 24-Apr-23

DEMO1200 Demolish GC87 0% 20 20 -69 31-Jul-23 25-Aug-23 24-Apr-23 22-May-23

Demolition - Brig SiteDemolition - Brig Site 0% 15 15 -66 31-Jul-23 18-Aug-23 27-Apr-23 18-May-23

DEMO1300 Abatement N403E 0% 5 5 -66 31-Jul-23 04-Aug-23 27-Apr-23 04-May-23

DEMO1400 Demolish N403E 0% 10 10 -66 07-Aug-23 18-Aug-23 04-May-23 18-May-23

DEMO1500 Demolish Building 283 0% 10 10 -66 07-Aug-23 18-Aug-23 04-May-23 18-May-23

OptionsOptions 0% 10 10 99 13-Sep-22 26-Sep-22 27-Jan-23 10-Feb-23

Option 1 - Aluminum SunshadesOption 1 - Aluminum Sunshades 0% 10 10 99 13-Sep-22 26-Sep-22 27-Jan-23 10-Feb-23

OPT1000 Install Aluminum Sunshades 0% 10 10 99 13-Sep-22 26-Sep-22 27-Jan-23 10-Feb-23

Project CloseoutProject Closeout 0% 80 80 -69 19-May-23 07-Sep-23 10-Feb-23 02-Jun-23

CLOSE0100 Final Building Inspection 0% 1 1 -69 19-May-23 19-May-23 10-Feb-23 13-Feb-23

CLOSE0120 Punchlist Corrections 0% 10 10 0 22-May-23 02-Jun-23 19-May-23 02-Jun-23

CLOSE0121 End User Move-In 0% 40 40 -69 22-May-23 14-Jul-23 13-Feb-23 10-Apr-23

CLOSE0130 Demolition Inspection - GC-87 0% 1 1 -69 28-Aug-23 28-Aug-23 22-May-23 23-May-23

CLOSE0131 Punchlist Corrections 0% 8 8 -69 29-Aug-23 07-Sep-23 23-May-23 02-Jun-23

CLOSE0140 Demolition Inspection - Brig Site 0% 1 1 -66 21-Aug-23 21-Aug-23 18-May-23 19-May-23

CLOSE0141 Punchlist Corrections 0% 10 10 -66 22-Aug-23 04-Sep-23 19-May-23 02-Jun-23

CLOSE0150 Demobilization 0% 1 1 -62 29-Aug-23 29-Aug-23 01-Jun-23 02-Jun-23

CLOSE0160 Closeout Documents 0% 40 40 -60 03-Jul-23 25-Aug-23 07-Apr-23 02-Jun-23

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

2022 2023

Install Signage

Exterior Fencing & Fixtures

27-Apr-23, Electrical

Under Slab Electrical Rough-in

Exterior Wall Rough-in

Interior Wall Rough-in

Interior Branch Wiring

Exterior Electrical Trim-Out

Exterior Lighting

Interior Electrical Trim-Out

Interior Lighting

Install Switch

Install Transformer

Generator Placement

Generator Connections

Generator Startup

Lightning Protection

Communications Raceway

Set Communications Racks

Install Communications Cable

Terminate & Test Communications

30-Dec-22, Mechanical

Mechanical Ductwork Install

Install VAVs

Install FCUs

Install AHU-1

Install AHU-2

Install Chiller

Controls Rough-In

Controls Cabling

Controls Termination

Controls Testing

Install GRDs

14-Apr-23, Plumbing

Under Slab Plumbing Rough-In

In-Wall Plumbing Rough-In

Set Plumbing Fixtures

Install Water Heaters & Equipment

Plumbing Trim Out

02-May-23, Fire Alarm

Fire Alarm Rough-in

Fire Alarm Cabling

Fire Alarm Device Trim-out

Fire Alarm Panel Connections

Fire Alarm Testing

20-Jan-23, Fire Suppression

Fire Sprinkler Main Runs

Install Fire Sprinkler Heads

16-Dec-22, Inspections

Air Barrier Pressure Tests

25-Aug-23, Demolition - GC87

Abatement GC87

Demolish GC87

18-Aug-23, Demolition - Brig Site

Abatement N403E

Demolish N403E

Demolish Building 283

26-Sep-22, Options

26-Sep-22, Option 1 - Aluminum Sunshades

Install Aluminum Sunshades

07-Sep-23, Project Closeout

Final Building Inspection

Punchlist Corrections

End User Move-In

Demolition Inspection - GC-87

Punchlist Corrections

Demolition Inspection - Brig Site

Punchlist Corrections

Demobilization

Closeout Documents

GTMO Working Dog Treatment Facility - Construction Classic Schedule Layout 03-Mar-22 09:14

Actual Work

Remaining Work

Critical Remaining W...

Milestone

Page 3 of 3 TASK filter: All Activities