0. SOW-FY22 Guantanamo Bay Veterinary Clinic IOT-18 Jul 22.docx

DOCX document 488 KB Posted

Attached to
Veterinary Clinic IO Project - Guantanamo Bay
Solicitation number
W9127S22Q6004
Issued by

About this file

This notice provides information about an upcoming initial outfitting project solicitation for a Veterinary Clinic at Naval Station Guantanamo Bay, Cuba. The United States Army Corps of Engineers Little Rock District intends to issue a request for quote using simplified acquisition procedures and commercial items procedures. The requirement is a total small business set-aside with a NAICS code of 337127 and size standard of 500 employees. The estimated contract value is between $1 million and $3 million. The outfitting project is for the Veterinary Clinic Military Working Dog Treatment Facility and involves furnishing, fixtures, equipment, and related transition services. The performance period goal date is December 31, 2023. Interested parties can submit questions to ProjNet between August 3rd and August 15th, while the estimated proposal due date is August 31st, 2022. The notice provides details about the requirement and forthcoming solicitation to inform potential contractors.

View the file

Other files

File Type Posted
22. Facility Related Control Systems Overlay_FINAL (FOUO).pdf PDF
7. NSGB WDTF - FINAL DWGS SIGNED gov.pdf PDF
17. Example Generic ICS Med-COI Boundary Diagram v4-1.pdf PDF
13. GTMO WDTF Existing Inventory (G) 7 Apr 2022.xlsx XLSX spreadsheet
19. FRCS-VRA Ver 2.0.docx DOCX document
2. NSGB WDTF Haul Route_USNH to Landfill 15 Mar 22.pdf PDF
6. NSGB WDTF - BASIS OF DESIGN - FIO MAY 2021.pdf PDF
24. Refrigerator Monitoring Systems.pdf PDF
20. DHA MDE Categorization Memo.pdf PDF
14. DHA FRCS Baseline Categorization Memorandum-1 October 2020 (1).pdf PDF
9. NSGB WDTF - FINAL SUBMITTAL SID_VOL_II_BUNDLED - FIO.pdf PDF
16. DHA System-Level Continuous Monitoring Plan 23MAY2018.xlsx XLSX spreadsheet
11. NSGB WDTF Construction Schedule 03 Mar 22.pdf PDF
3 Standard Notices (UEI PIEE NIST) For Industry.docx DOCX document
16. DHA System-Level Continuous Monitoring Plan 23MAY2018.pdf PDF
9. NSGB WDTF - FINAL SUBMITTAL SID_VOL_I_BUNDLED - FIO.pdf PDF
25. Audio Video Conferencing.pdf PDF
1. NSGB WDTF Haul Route_Port to USNH 15 Mar 22.pdf PDF
18. FRCS FAT SAT Checklist.pdf PDF
IO Eval Criteria GTMO WDTF.docx DOCX document
8. NSGB WDTF - Artwork Placement Plan - 01 JAN 19.pdf PDF
15. Draft DHA PM Standard Isolation Architecture for Cybersecurity of FRCS.DOCX DOCX document
00. FY22 NSGB WDTF_Div 00_CLIN Schedule_USACE.xlsx XLSX spreadsheet
23. Patient Monitoring and Telemetry System.pdf PDF
21. PIA Processes and Procedures.docx DOCX document
5. Guantanamo WDTF IO Project Status Report (PSR) 5 Apr 22.xlsx XLSX spreadsheet
10. NSGB WDTF - FINAL SUBMITTAL CID VOL1_AND_VOL2 - FIO 07 MAR 19.pdf PDF
12. NSGB WDTF - Medical Equipment - BASIS FOR BID - RPIE Removed 04 Apr 22.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY 22 GUANTANAMO BAY VETERINARY CLINIC REPL, CUBA, PROJECT NO. 89839 DATE: 2 MAY 22 (Version 5.0)

Table of Contents

Table of Contents2
Preface4
0Procurement & Contracting Requirements4
1General Requirements5
1.1Division 01 Requirements5
1.1.1Summary of Work5
1.1.2Work Restrictions5
1.1.3Administrative6
1.1.4Schedule8
1.1.5Submittals12
1.2Initial Outfitting & Furniture, Fixtures, Equipment & Low Voltage Systems (FFE-LVS)13
1.2.1General13
1.2.2Qualifications: FFE-LVS17
1.2.3Submittals: FFE-LVS18
1.3Transition20
1.3.1General Requirements: Transition Services20
1.3.2Qualifications: Transition Contractor26
1.3.3Submittals: Transition27
2Interior Design Requirements28
2.1General28
2.1.1Qualifications: Interior Design29
2.1.2Submittals: Interior Design29
2.2Division 09: Finishes (Interior)30
2.3Division 10: Specialties (Interior Signage, Fixtures, Wall Protection)30
2.3.1Signage-Interior (PP)30
2.3.2Storage & Lockers (PP)30
2.3.3Fire Protection Items (PP)30
2.4Division 12: Furnishings (Furniture, Accessories, Casework, Artwork, etc.)30
2.4.1FURNISHINGS (PP)31
3Equipment Requirements32
3.1General32
3.1.2Qualifications: Equipment34
3.1.3Submittals: Equipment34
3.2Division 11: Equipment (Medical, Institutional, Office, Etc.)35
3.3DIVISION 41: MATERIAL PROCESSING & HANDLING35
4Communication Requirements35
4.1General35
4.1.2Qualifications: Communications35
4.1.3Submittals: Communication/low voltage systems36
4.2Division 25: Integrated Automation (Cybersecurity)36
4.2.1Risk Management Framework (RMF)37
4.2.2Submittals: Cybersecurity38
4.2.3Schedule Constraints: Cybersecurity41
4.3Division 27: Communications (Infrastructure, Phone, Data, etc.)41
4.3.1General41
4.3.2Personal Property (PP)41
5REFERENCES43
6Attachments44

Preface The Defense Health Agency-Facilities Enterprise (DHA-FE) requires outfitting/transition services for the Veterinary Clinic Replacement Project located at NS Guantanamo Bay, Cuba.

Procurement & Contracting Requirements

#
ACQUISITION INFORMATION
1 C
Project Delivery Method
Design-Bid-Build plus Initial Outfitting & Transition (IOT)
2 D
Acquisition Type
Best Value Trade Off
3 E
Contract Type
Firm-Fixed Price
4 F
Contractor Selection
Open Competition
5
Contract Holder
United States Army Corps of Engineers – Little Rock (USACE-SWL)
6
Contract Title
SWL IDBIO MATOC 5.0
7
Business Size
Small Business 8(a)

Procurement Information General Requirements Division 01 Requirements Summary of Work Project Information

PROJECT INFORMATION

A
Real Property Jurisdiction
Department of the Navy
B
Location
NS Guantanamo Bay, Cuba
C
Project Delivery Method
IOT stand-alone
#
FACILITY INFORMATION
FACILITY 1
1
Project Number
89839
2
Project Title
Working Dog Treatment Facility Replacement
3
Current Facility Number
GC87
4
New Facility Number
450
5
Facility Name
Veterinary Clinic

Military Working Dog Treatment Facility

6
Square Footage
5277
7
Real Property Categorization
53045
8
Medical Treatment Facility (MTF) Type
Veterinary Clinic
9
Facility Function
Vet Clinic
10
Scope Description
Initial Outfitting and Transition
11
Fund Sources
O&M
12
Level of Construction
Permanent
13
Department Name(s)
Reception, Animal Holding, Animal Procedure, Animal Support, Food Defense Laboratory, Staff and Administration, Support, Building Service
14
Current Use (Occupancy)
Business
15
New Use (Occupancy)
Business
16
Historical Status
No
17
Archeological Site
No
18
Defense Medical Information System Identifier (DMIS ID)
8570

Project Information Requirement Description The existing Veterinary Clinic on NS Guantanamo Bay, Building GC87, is in extremely poor condition and is lacking appropriate surgical accommodations and will be replaced. The Government requires the services of an IOT Contractor that can outfit the new Veterinary Clinic with new Personal Property (PP), transition of occupants and reuse property, dispose of non-reuse furniture, fixtures, equipment, and low voltage systems, and support the clinic with public relations and orienting staff to their new space.

Real Property Installed Equipment (RPIE) & Personal Property (PP) Furnishings, Fixtures, Equipment and Low Voltage Systems (FFE-LVS) are classified as either Real Property Installed Equipment (RPIE/LOG CAT A) or Personal Property (PP/LOG CAT C).

RPIE FFE-LVS includes control systems, heating, cooling, electrical, emergency lighting, fixed non-movable medical equipment, communication systems, etc., are provided by the Construction Contractor (aka Builder) and funded with Project Funds (MILCON).

PP FFE-LVS includes non-fixed and moveable property and are funded with Operations & Maintenance-Initial Outfitting & Transition Funds (OM-IOT).

Work Restrictions Continued Occupancy All departments within the existing facility will remain in operation during the entire Period of Performance (POP) unless specifically stated herein. Permission to interrupt operations must be submitted in writing within the timelines outlined. Transition (remove and relocate government property) in all areas scheduled to receive work. Refer to section entitled Schedule Constraints.

Base Access & Working Hours When arranging access to Naval Station Guantanamo Bay, Cuba, refer to the CNIC Website which contains detailed steps on how to obtain area clearance for individuals visiting on official visits.

Working hours within the existing facility, and around the site, are outlined in the following table and exclude all Federal and Host Nation holidays. Work outside these hours requires MTF Facility Management (FM) approval and must be requested within the time outlined in the section entitled Schedule Constraints.

DAYS
WORK PERIOD
MORNING
AFTERNOON
Monday-Wednesday & Friday
6 hours
0900-1200
1300-1600

24/7 on-call for emergencies

Contractor Access and Use of Premises Contractor installation access instructions are defined in the Installation Contractor Requirements.

Security Requirements Installation and/or MTF security requirements are detailed in the Installation Contractor Requirements.

Administrative Progress and Completion Photos Provide professional pre-work, progress, and/or completion photos for the spaces outlined in the table below.

#
SPACE
PRE-WORK
IN-PROGRESS
COMPLETION
1
Lobby/Waiting
Yes
Yes
Yes
2
Exam/Treatment
Yes
Yes
Yes
3
Office
Yes
Yes
Yes
4
Kennels Lg Animals
Yes
Yes
Yes
5
Holding Sm Animals
Yes
Yes
Yes
6
Laboratory
Yes
Yes
Yes
7
Imaging
Yes
Yes
Yes
8
Operating Room
Yes
Yes
Yes

Post Award Meetings Meeting Logistics Coordinate Agendas and meeting arrangements with the government prior to proposed meeting dates. Notify the government of workspace requirements necessary to conduct the meeting (e.g., required number of meeting rooms, tables, chairs, presentation boards, teleconferencing ability, wi-fi connectivity, etc.). Provide equipment, accessories, and documents necessary to conduct the meeting. Include the meeting address, building and room number on all agendas.

Documentation of Potential Changes At the close of each meeting identify Potential Changes that may impact the project cost, scope, schedule, or safety. Document it as a potential risk on the Project Status Report (PSR), circumstance or individual driving the change, and, if approved, government individual approving the change. Refer to section entitled Project Status Report.

Post Award/Kickoff Meeting Attendees Coordinate activities and deliverables with the government representatives listed in the table below.

#
AGENCY
REPRESENTATIVE
ROLE
1
DHA-FE
Project Officer/Project Lead (PO/PL)
Leads DHA-FE project team; project’s primary point of contact (POC)
Facility/Clinical Planner
DHA-FE project team members (referred to as the “Integrated Project Team” (IPT); supports PO/PL for project’s life cycle; develops project requirements on behalf of the project sponsor (DHA-FE); reviews submittals for compliance/conformance; serves as healthcare subject experts for their respective discipline.

Interior Design Planner

Equipment Planner

Communications Rep (aka IM-IT Planner)

Architectural Planner/Representative

Mechanical Representative

Electrical Representative

Fire Protection Representative

Civil-Structural Representative

IOT Planner

Transition Coordinator
Coordinate property management & transition service activities
13
Medical Treatment Facility (MTF)
Facility Manager (FM)
Manages MTF’s environment of care, safety, ops, maintenance
Logistics
Oversees property management and procurement activities
Information Systems (IM-IT)
Maintains information management/technology Systems
Medical Equipment Maintenance
Maintains Medical Devices and Equipment on behalf of the MTF
Safety & Security
Provides safety and security oversight on behalf of MTF
Equipment Custodian
Responsible for all property located within assigned department
Infection Control
Responsible for MTF infection control compliance
Department Representatives
Serves as department’s representative to support the transition
21
Installation
Installation Rep
Represents installation’s security, site, and comm requirements
22
Installation
Authority Having Jurisdiction (AHJ)
Refer to UFCs

Weekly Progress/Team Meetings Conduct weekly progress meetings with the government project team. Provide agendas, meeting minutes, action items, and attendance records. At a minimum, include agenda items outlined in the table below.

#
AGENDA ITEM
TOPIC
DISCUSSION
1
Project Status Report (PSR)
Project Status Report (PSR)
Overarching risks and changes
Overview
Changes
Cost
Changes and potential exposure
Schedule
Changes to milestones and Impact on project schedule and critical path
Scope
Changes in scope for all disciplines
Risk
Review risks, strive for resolution, assign a point of contact to work issues
Requests for Information (RFI)
RFIs’ that require resolution and/or action
Distribution
Determine if distribution requirements changed
9
Meeting Minutes
Previous meeting documentation and corrections
10
Submittals
Upcoming and outstanding submittals

Project Status Report (PSR) Use the Attachment: Project Status Report (PSR) to document project status, information, and issues. The PSR also outlines submittal distribution requirements. The purpose of the PSR is to keep senior leadership and the project team informed of risks related to cost, schedule, scope, and safety. The PSR serves as a repository of relevant and historical information and is used extensively for studies, analysis, and senior-level reporting. It enables team members to proactively manage issues and minimize risks real time.

Update the PSR weekly until receipt of the final set of DD Form 250 is the Material Inspection and Receiving Report (MIRR) (Personal Property).

Review the PSR during weekly progress meetings. Highlight changes, updates, and edits. It is critical the PSR reflect accurate and current information and all fields are complete. Failure to maintain this document could adversely impact the project, programming decisions, prompt resolution, change management, and affect contractor performance rating(s).

Tracking Potential Changes (Process) Refer to Contract Clauses. Use the Project Status Report (PSR) to clearly identify any adjustments which may have a potential cost, schedule, scope, safety, or quality change. Should one be identified, notify the Contracting Officer in accordance with the Contract Clauses. The PSR is the mechanism used to inform the project team of potential risks.

Meeting Minutes and Written Records Prepare detailed and accurate written records of each site visit and meeting. Refer to the Project Status Report (PSR) Distribution List for distribution requirements. Include agenda, subject, names of participants, document relevant details, action items, the party responsible, and resolution date. Illustrate and/or include drawings reflecting scope additions and deletions. Summarize work the contractor believes is outside the contract scope. Number written records in consecutive order. Provide electronic copies of all written records, agendas, presentations, and meeting minutes in each submittal.

File Naming Conventions, Electronic Submittals, and Distribution Provide standardized electronic naming conventions to ensure timely government responses. Include numerical date (year, month, day), fiscal year (FY), installation name, submittal/RFI/ASI number, and project number. Do not exceed thirty (35) characters or include special characters (e.g., 20210109_FY23 FtBragg _DS4_PNxxxxx). Distribute electronic submittals to the government team via a publicly accessible site (such as Microsoft® SharePoint® or equivalent). Provide electronic submittals in accordance with the Project Status Report (PSR). Provide electronic submittals with a single file structure with proper bookmarks. Each file size may not exceed 50 megabytes (MB).

Review & Resolution Conferences Review and resolution conferences are to be held following each submittal. Review open issues or actions from the last meeting, what occurred, and what is planned to occur before next meeting. Reviews should focus on critical path items and activities that may impact the project’s schedule/scope. The objective of the review or resolution conference is to resolve any outstanding compliance or conformance deficiencies identified by the government. No comment should be left unresolved before moving forward to the next submittal.

Schedule Project Schedule (Detailed Requirements) & Period of Performance (POP) The Period of Performance (POP) includes the activities and deliverables outlined in the tables below.

A
INITIAL OUTFITTING/FFE-LVS INSTALLATION
INCLUDED POP/SCHEDULE
1
Notice to Proceed
Yes (IOT Stand Alone Projects: NTE 24-mos prior to install date)
2
FFE-LVS Submittals 1-2
3
Procurement
4
Delivery/Storage
5
Installation of Personal Property
Yes-Prior to Transition Start
6
Testing
7
Certifications
8
Cleaning
9
Inspections
10
Acceptance
11
Train Staff
12
Property Transfers
B
TRANSITION
INCLUDED POP/SCHEDULE
1.
Transition Submittals
Yes
1
Orient Staff Members
Yes-Upon completion of FFE-LVS install, prior to each phased move
2
Property Moves

Yes-2 workdays by phase

3
De and Re-Installations
4
Testing
5
Certifications
6
Inspections
7
Acceptance
8
Temporary Signage
9
Move Occupants
10
Clean (Aseptic)
11
Dispose
Yes-Shall not impede critical path

Schedule Constraints Due to DHA-FE and MTF operational and/or patient care constraints, schedules must account for the constraints outlined in the table below. Exclude Federal or Host Nation holidays from the number of required calendar days. These schedule constraints take precedence over those listed in the specifications.

NO
ACTIVITY/DELIVERABLE
SCHEDULE CONSTRAINTS (CALENDAR DAYS)
1
Acceptance Docs: Reuse FFE-LVS (Interim)
45 days prior to Conditional Acceptance
2
Acceptance Docs: Reuse FFE-LVS (Revised)
21 days prior to Conditional Acceptance
3
Acceptance Docs: Reuse FFE-LVS (Final)
21 days to Final Acceptance
4
Acceptance Forms: New FFE-LVS (Interim)
45 days prior to Conditional Acceptance
5
Acceptance Forms: New FFE-LVS (Revised)
21 days prior to Pre-Final Acceptance
6
Acceptance Forms: New FFE-LVS (Final)
21 days prior to Final Acceptance
7
Acceptance Inspections (Notice)
45 days prior
8
Acceptance Submittals (O&M Manuals)
At time of installations
9
Disposition Plan (& Notice Date to Begin) DD Form 1348-1A Disposal Turn-In Form
Coordinate deliveries w/ Logistics & DLA-DS NLT 90 days prior to disposition
10
Documentation (Warranty & Maintenance)
15 days post acceptance; 21-day Govt review
11
Inspection (Punch Lists & Inspection Findings)
7 days following government inspection
12
Inspection Docs: Corrected Final Documents
14 days prior to Final Inspection
13
Inspection Docs: Notification: Inspection
21 days prior to inspection
14
Inspection Docs: Systems & Equipment Testing List
90 days prior to testing
15
Lessons Learned Survey (Distribute Reports)
NLT 45 days following survey distribution
16
Lessons Learned Survey (Transition & PR) (Distribute Surveys)
NLT 14 days following moves by phase
17
Meeting (Kick-Off)
7 days following Notice to Proceed (NTP)
18
Meeting Agendas (Draft)
45 days prior to meeting date
19
Meeting Agendas (Final) & Attendee Confirmation
10 days prior to meeting
20
Meeting Minutes & Written Records
5 days following meeting/conference
21
Meeting: Comm/LVS Coordination Meeting
Bi-Weekly; commence NLT 120 prior to moves
22
Meeting: FFE-LVS Third-Party Vendor Coordination
Coordination with MTF NLT 6 mos. prior to start
23
Meeting: Project Status Report (Risk Identification)
Within 14 days of identification
24
Meeting: Project Status Report (Risk Resolution)
30 days of identification
25
Meeting: Transition Planning
Minimum Bi-Weekly; commence NLT 90 days prior to moves
26
Notice: Disruption of Utility Services
14 days prior to shutdown
27
Notice: Facility Cleaning
120 days prior to moves
28
Notice: FFE-LVS Installation
21 days prior to installation
29
Notice: Installation Security Notification
60 days prior to mobilization
30
Notice: Preliminary Moves- Notification
60 days prior to target move date by phase
31
Notice: Street Closings
30 days prior to closure
32
Notice: Traffic Disruptions/Traffic Control Plan
14 days prior to work commencement
33
Notice: Work holidays, weekends, after hours
14 days prior to commencing work
34
Notice: Final Moves Notification
21 days prior to Conditional Acceptance by phase
35
Notice: Request for Time Extensions
Refer to Contract Clauses
36
Performance Forms: Contractor Address/Resolve Rating
Contractor 7 days to respond to rating; Govt 7 days to confirm
37
Provide Attic Stock
Within 30 days of Govt acceptance of each phase
38
Public Relations (Coordinate Ceremony Materials/Postings)
Review w/MTF a min of 45 days prior to release
39
Public Relations (Distribute materials /postings & handouts)
Min of 90 days prior to move or ceremony
40
Record Documents (Draft/Final)
21 days for review
41
Request for Information (RFI)
Govt 14 days to respond
42
Resumes (Key Personnel-Revisions)
Project kick-off meeting
43
Resumes (Updated Key/FFE-LVS Personnel)
Provide to Govt at time of project kick-off meeting
44
Schedule (Updates on PSR)
7 days of meeting date or major shift in schedule
45
Submittal (Initialed PRC room drawings)
7 days following conditional inspections
46
Submittal (O&M Data Changes)
14 days of Govt notification
47
Submittal 1: Comm/LVS Binder (Draft)
NLT 12 months prior to Conditional Acceptance Date (PH1 if project is phased)
48
Submittal 1: Department Transition Plan (Draft)
49
Submittal 1: FFE Binder (Draft)
50
Submittal 1: FFE-LVS Execution Plan Binder (Draft)
51
Submittal 1: MTF Transition Plan (Draft)
52
Submittal 2: Comm/LVS Binder (Final)
NLT 9 months prior Conditional Acceptance Date (PH1 if project is phased)
53
Submittal 2: Department Transition Plan (Final)
54
Submittal 2: FFE Binder (Final)
55
Submittal 2: FFE-LVS Execution Plan Binder (Final)
56
Submittal 2: MTF Transition Plan (Final)
57
Submittal 3: FFE-LVS Training Schedule, Testing & Certification Schedule (new & reuse)
Distribute revisions 60 days prior to move commencement by phase
58
Submittal 4: Transition Plan: Final Activity Schedules, Move Guides, Move Spreadsheets & “Day in the Life”
Distribute handouts 14 days prior to move commencement by phase
59
Submittals: Final Corrected
21 days of correction; govt review = 15 workdays
60
Submittals: Government Review Period
21-day review period
61
Submittal: O&M Manuals (to include Facility Data)
At time of RP, RPIE, PP Conditional Acceptance

Operational Time Constraints The tables below outline functional, operational, and phasing time constraints. Consider these constraints during development of proposals, phasing/transition plans, and project schedules.

#
CONSTRAINT
1
Contractor work must not negatively impact patient care or healthcare delivery and operations
2
Contractor must work within the time constraints outlined in the section entitled Schedule Constraints
3
Departments may not be closed for more than 2-work days during the transition period.
4
All existing security systems to remain fully operational (i.e., Duress, IDS, Card Access, etc.)

Acceptance Milestones & Terminology The following figure illustrates acceptance milestones, terminology, and associated documentation. Include acceptance milestones in project schedules and the Project Status Report.

Acceptance and Transfer Documentation Submit property transfer documentation (e.g., DD Form 1354: Transfer and Acceptance of Real Property (RP/RPIE) and/or final set of DD Form 250 is the Material Inspection and Receiving Report (MIRR) (Personal Property). The following table outlines the project phase and deliverables related to work acceptance[footnoteRef:2] and property type transfers. [2:

#
PHASE DUE
RESPONSIBILITY
PROPERTY
MILESTONE
ACCEPTANCE DOCUMENTATION
1
Initial Outfit (PH7)
PP Sub/Contractor
New PP
Conditional Acceptance
Interim DD Form 250s & ATO Documentation (Refer to Submittals: Cybersecurity)
2
Transition
Transition Sub/Contractor
Reuse FFE-LVS
Conditional Acceptance
Reuse Property Transfer Documentation: (1) Existing Inventory List of Reuse Items; (2) Room-By-Room Drawings, (3) PRC List, and (4) Punch lists

Final Acceptance

4
Activation
PP Sub/Contractor
New PP
Final Acceptance
Revised DD Form 250s & ATO Documentation (Refer to Submittals: Cybersecurity)

The following table outlines who are authorized to take acceptance.

No
Document
Section
Authorized Government Rep
1
DD Form 1354 (Real Property & Real Property Installed Equipment (RPIE))
27 Transferred By
Contracting Officer Representative
28 Accepted By
Installation Engineer/MTF Facility Manager
3
DD Form 250 (Personal Property)
21a. Origin
Prime/IOT Contractor
21 c. Destination
DHA-FE IO/T Coordinator (if assigned). PO/PL if no IO/T Coordinator
22 Receiver’s Use
MTF Logistics Representative
6
Existing Inventory/PRC (Reuse FFE-LVS)
All
MTF Logistics Representative
7
Punchlist (RP/RPIE/PP)
All
Project Officer/Project Lead
8
AHJ Documentation (RP)
All
AHJ-MST Fire Protection Engineer
9
ATO Documentation (Communications)
All
Chief Information Officer/ISSM

Acceptance Classifications All inspection and acceptance items specified for correction (via the “punch list”) will be assigned an acceptance classification to include (1) Counterfeit, (2) Critical, (3) Critical Non-Conformance, (4) Major Non-Conformance, or (5) Warranty.

a. Counterfeit item means an unlawful or unauthorized reproduction, substitution, or alteration that has been knowingly mismarked, misidentified, or otherwise misrepresented to be an authentic, unmodified item from the original manufacturer, or a source with the express written authority of the original manufacturer or current design activity, including an authorized aftermarket manufacturer (e.g., used items represented as new, or the false identification of grade, serial number, lot number, date code, or performance characteristics).

b. Critical item means an item, the failure of which is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the item; or is likely to prevent performance of a vital agency mission.

c. Critical Nonconformance means a nonconformance that is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the supplies or services; or is likely to prevent performance of a vital agency mission.

d. Major Nonconformance means a nonconformance, other than critical, that is likely to result in failure of the supplies or services, or to materially reduce the usability of the supplies or services for their intended purpose Conditional Acceptance Conditional Acceptance, as defined in Federal Acquisition Regulation (FAR) 46.101, means acceptance of supplies or services that do not conform to contract quality requirements, or are otherwise incomplete, that the contractor is required to correct or otherwise complete by a specified date. In Accordance with (IAW) FAR 46.407 Nonconforming supplies or services, the contracting officer may determine acceptance or conditional acceptance of supplies or services when it is in the best interest of the Government. The contracting officer will work with the project sponsor (i.e., DHA-FE) to provide the specified date in which the contractor is to correct or otherwise complete the portion of the requirement[footnoteRef:3] that does not meet the quality requirements. Conditional Acceptance occurs once the Contracting Officer notifies the project sponsor (i.e., DHA-FE) that the work has reached Substantial Completion. Construction Conditional Acceptance is synonymous with Placed in Service (PIS) date and Beneficial Occupancy Date (BOD). [3: FAR 46.5 Acceptance, UFC 1-300-08 Criteria and Transfer and Acceptance of Real Property, FAR 46.101 Quality Assurance

Final Acceptance Final Acceptance means an authorized government representative assumes ownership of the property, determines services rendered are complete, in accordance with the contract. Final acceptance includes Authority to Operate (ATO) documentation. Final Acceptance is synonymous with Construction Complete and Open for Business (OFB).

Contract Complete Contract Completion means if, and only if, all work is complete to include contract obligations, deficiencies and punch list items are corrected, and complied with all conditions for final payment.

Weekly Progress Meetings Refer to section entitled Administrative.

Submittals Quantity of Submittals Provide the number of submittals outlined on the Attachment: Project Status Report (PSR) (Distribution List). The distribution list identifies electronic vs. hard copy submittal requirements.

Project Submittal Register and Database Within 30-days of contract award, provide a Submittal Register for all project phases to include what’s listed in the table below.

NO
SUBMITTAL REQUIREMENTS
SUBMITTAL REGISTER REQUIRED
1
FFE-LVS Submittals
Yes
2
Transition Submittals
Yes
3
Activation Submittals
Yes
4
*DHA-FE Unique Cybersecurity Submittals (By Phase)
Yes

Submittal Variations: Real Property Installed Equipment (RPIE) and/or Personal Property (PP) FFE-LVS Real Property Install Equipment (RPIE) and/or Personal Property (PP) Furniture, Fixtures, Equipment and Low Voltage System (FFE-LVS) documents submitted with the solicitation, and accepted by the government, are considered the contract documents and are used to track cost, scope, and schedule adjustments for the project duration.

During the course of the project, document all deviations to the contract documents to include but not limited to (1) quantity, (2) additional accessories and options to a particular JSN or system, (3) deletion or addition of a JSN or system, and/or (4) changes from a JSN or system from “reuse” to “new” or vice versa. The contractor is not authorized to execute changes, or exceed the contract price, without a contract modification. Summarize justification for the change and highlight all deviations on the awarded or modified contract documents and include in each submittal. Use a different color to highlight submittal revisions.

Initial Outfitting & Furniture, Fixtures, Equipment & Low Voltage Systems (FFE-LVS) General The following FFE-LVS Requirements clarify or augments the provisions outlined in Unified Facilities Criteria. Provide the Furniture & Fixtures outlined in the section entitled Interior Design Requirements. Provide the Equipment outlined in the section entitled Equipment Requirements. Provide the Low Volage Systems (LVS) outlined in the section entitled Communication Requirements.

There are two types of Furniture, Fixtures, Equipment and Low Voltage Systems (FFE-LVS) (1) Real Property Installed Equipment (RPIE) which is procured and installed by the Builder, and (2) Personal Property (PP) which is procured and installed by the IOT Contractor. The table below outlines (1) the property types, (2) nomenclature, (3) appropriation or fund source, (4) definitions, and (5) which set of criteria typically applies. Attachment: Project Room Contents (PRC) outlines what FFE is considered RPIE versus PP. MIL-STD-1691 Military Medical and Dental Facilities Policy Document (FFE-LVS) outlines what LVS is considered RPIE versus PP.

Comply with referenced criteria and standards outlined in the table below unless otherwise explicitly stated. Exceptions: Some equipment or systems such as Electronic Security Systems (ESS) must comply with both and . Other exceptions are noted throughout this document.

#
PROPERTY TYPE
ALSO KNOWN AS
APPROPRIATION/

FUND SOURCE

DEFINITION[footnoteRef:4] [4: Reference: UFC 1-300-008 Criteria for Transfer and Acceptance of DoD Real Property]

APPLICABLE CRITERIA & STANDARDS*

1
Real Property Installed Equipment
RPIE or Installed Building Equipment (IBE)
MILCON or Operations & Maintenance (O&M)

Also known as “Project Funds”

Property affixed and built into the facility as an integral part of the facility; necessary to make facility complete, and if removed, would destroy, or severely reduce the usefulness of the facility
and
2
Personal Property
Expense Equipment

(1-year money)

Initial Outfitting & Transition (OM-IOT)
Property (systems and equipment, materials, and supplies) except real property
and

Investment/Expense Equipment (2-year money)

Research, Development, Evaluation & Training (RDT&E)
Property (except real property/ Property that consists of capital and other nonexpendable equipment

Equipment in Place (EIP) or Investment Equipment (3-year money)

Procurement (P)
Property that consists of capital and other nonexpendable equipment of a movable nature that has been fixed in place or attached to the real property but is not an integral part of the facility

Government Representatives Coordinate FFE-LVS activities and deliverables with the government representatives listed in the table below.

#
REPRESENTATIVE
ROLE
1
Contracting Officer Representative
Responsible for administering the contract on behalf of the Contracting Officer
2
Project Manager
Manages the project scope on behalf of the Contracting Activity/Agent
3
Project Officer/Lead
Leads the DHA-FE project team and serves as the project’s primary point of contact (POC)
4
IOT Planner/Transition Coordinator
Lifecycle representatives focused on contractual obligations & Project Officer/Lead support, Coordinate’s property management & transition service activities on behalf of DHA-FE/MTF.
5
Facility Manager
Manages the facilities environment of care, safety, operations, and maintenance programs
6
Logistics
Oversees property management and procurement activities on behalf of the MTF
7
Information Systems
Maintains information management/technology Systems on behalf of the MTF
8
Medical Equipment Maintenance
Maintains Medical Devices and Equipment on behalf of the MTF
9
Safety & Security
Provides safety and security oversight on behalf of the MTF and/or Installation
10
Equipment Custodian
Responsible for all property located within their assigned department
11
Department Representative
Serves as the department’s representative to support the transition
12
Information Systems Security Manager (ISSM)
Responsible for the development, implementation, assessment, and monitoring of common controls.
13
GOV Site Information System Owner (ISO)
Responsible for the overall procurement, development, integration, modification, operation, maintenance, and disposal of an information system
14
GOV Information System Security Officer (ISSO)
Responsible for developing and enforcing security policies for the information system, managing/controlling changes to the information system and assessing the security impacts of those changes.

Space Planning & Document Updates Prior to Submittal 1 conduct a detailed Survey and Inventory of existing FFE-LVS for all departments and spaces impacted by construction or moves. Based on these findings, markup[footnoteRef:5] the DOR or government-provided (“G”) documents to reflect field-verified conditions; prior to FFE-LVS procurement date and 6-months prior to expected installation. The scope of this effort includes: [5: Markup = colored highlights, clouds, etc. ]

a. Field Verification: Field verify room configuration, infrastructure, and structural conditions and impact on FFE-LVS

b. Project Room Contents (PRC) (Confirm new versus reuse and logistical responsibility)

c. MEP/Architectural Drawings (New and Reuse FFE-LVS)

d. FFE/Equipment Drawings (New and Reuse FFE)

e. Communication Drawings (New and Reuse LVS)

f. Specifications/Cutsheets (New Equipment and LVS)

g. Room Data/Illustration Sheets (New Furniture and Fixtures)

h. Change Summary (Document summarizing required changes to infrastructure/structural)

i. Existing Inventory List (C): All existing property must be documented on an updated and contractor-maintained Existing Inventory List (C) derived from the Attachment: Existing Inventory List(s)(G) (also referred to as the Defense Medical Logistics Standard Support (DMLSS) Accountable Medical Device Equipment (MDE) List and DMLSS RPIE List). In addition to what is listed as reuse on the contractual PRC, incorporate findings from the Existing Inventory List (C) on a sortable Microsoft® Excel® spreadsheet. Include information found in the table below.

j. Space Planning. Prior to the placement of the FFE-LVS, field verify existing site conditions to include architectural, mechanical, electrical, communications, fire protection, and civil-structural conditions. Contractor updated FFE space plans (drawings) must show all electrical, communications, mechanical (i.e., fume/exhaust hoods), and plumbing interface (i.e., sinks, water connections, medical gas) on the same drawing.

k. Reuse FFE. Reuse is defined as property with 24-months of useful life remaining at the time of re-installation. As part of the submittal review process, the MTF Biomedical Equipment Technician (BMET) will verify if equipment meets this definition and is scheduled for reuse or disposition.

#
EXISTING INVENTORY LIST (C)
1
Confirm what property is to be moved, relocated, and reinstalled (reuse)
2
Include room level information for current, interim, and final locations
3
Confirm reuse items planned for the project meet the operability, durability, and safety requirements
4
Determine reuse items will fit within allowable space in new facility; notify project leadership if they will not
5
Confirm items will have necessary utilities to function in accordance with manufacturer specifications
6
Determine if reuse items can be delivered into the new facility via corridors, doors, etc.
7
Determine which items should be denoted for excessing and disposition
8
Include utilities, dimensions, and photographs for all Medical Device Equipment (MDE)
9
Include JSN, Nomenclature, quantities, Equipment Control Numbers (ECNs)
10
Include existing artwork
11
Coordinate reuse vs. disposal with MTF FM, BMETs, Logistics, Property Custodians

Shipping & Receiving Provide an FFE-LVS Execution Plan: Shipping & Receiving Plan. Prior to each submittal coordinate plan details with project representatives from the MTF facility management and logistics. Containers shipping from the US to Guantanamo Bay ship from the Blount Island Marine Terminal located in Jacksonville, Florida. Refer to Blount Island Marine Terminal for port details. The table below outlines shipping and receiving details.

#
ACTIVITY/DELIVERABLE
RESPONSIBLE
KTR
MTF
1 1
Address containers shipping from the Blount Island Marine Terminal to the US Naval Hospital Guantanamo Bay as follows: Portus Warehouse, Attn: USNH Guantanamo Bay, 8693 Maritime Street, Jacksonville, Florida, 32226. No additional address is required on the receiving end in Guantanamo Bay.
X
2
Shipping time from Jacksonville to Guantanamo Bay is estimated to be 4-5 weeks.
X
3
Coordinate pending container deliveries with the Navy APO, Frank Kidd. He can be reached at (757) 458-2998 (office) or (217) 621-6813 (cell), franklin.r.kidd.civ@mail.mil.
X
4
Arrange transport of containers from the Guantanamo Bay port to the US Naval Hospital (USNH)
X
5
US Naval Hospital Property Management personnel will open the containers to inspect new PP and gain into the DMLSS system. The inspected property will be loaded back into the containers where they will stay until time to install new property. Acceptance of the new PP will take place once installed in the new facility. It is estimated to be 4-5 weeks from the time the containers are received at port, delivered to the USNH, equipment inspected and reloaded back into the containers.

X

Storage & Staging Provide an FFE-LVS Execution Plan: Storage & Staging Plan. Prior to each submittal coordinate plan details with project representatives from the MTF facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Staging requirements must be coordinated and approved by the MTF Facility Manager prior to need date. Replace in-kind all property damaged during moves or transport. Provide water line shock treatment in accordance with manufacturer recommendations.

#
RESOURCE
1 1
Once containers are inspected by the Property Management group at the USNH, they can remain on site until installation of the PP. However, due to local environmental conditions, it is advisable to limit container storage of new PP to a maximum of 4-6 weeks. Environmentally controlled containers are recommended for new PP.
X
2
Temporary power may be available at the job site for containers requiring environmental control. Contact Jason Adkins, NAVFAC Construction Manager, at Jason.e.adkins.civ@us.navy.mil or (757) 458-5650 for additional information.
X

Local Services Equipment rental and personnel services available on the installation are limited. The table below provides resource information for local businesses operating within the Naval installation.

#
RESOURCE
SERVICES
CONTACT INFORMATION
1 1
Vectrus Systems Corporation
BOSC Workorder System for USNH/Vet Clinic, Equipment, Personnel
(757) 458-3110
2
Schuyler Line Navigation Company
Equipment, Personnel
(757) 458-4711
3
Guardian
Moving Services, Equipment
(757) 458-4481
4
Public Works department
Unconditioned warehouse space – contact Jason Adkins, NAVFAC
(757) 458-5650

Delivery & Installation Provide an FFE-LVS Execution Plan: Delivery & Installation Plan. Prior to each submittal coordinate plan details with project representatives from MTF facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Deliver and install all new FFE-LVS. Protect areas and equipment from damage during moves and installation. Provide drop cloths and other coverings necessary to protect all surfaces. Mask and cover wall fixtures, plaques, pictures, bulletin boards, communication equipment, and cables. Move furniture, equipment, or other items necessary to install the property. Return areas to the original condition.

Prior to installation, confirm placement of commodities with Government Representatives outlined in the table above. Ensure installation and placement of FFE-LVS complies with the Architectural Barriers Act (ABA) and does not block access to sinks, doors, etc. All Government installed/provided FFE-LVS (e.g., paper towels, hand soap, hand sanitizer, etc.) must be installed and operational prior to inspections. Provide labels for users to distinguish apart hand soap and hand sanitizer dispensers if JSNs are the same.

Mock-Ups (Interior) Provide Building Information Modeling (BIM) Mock-Ups outlined in the table below. 3-D mock-ups do not need to display final finish materials but must accurately reflect the size of space represented and be of sufficient fidelity to allow for accurate evaluation of the space, equipment, and functionality. At a minimum, mock-ups must contain replication of walls, ceiling height indication, ceiling mounted lights/equipment, medical gases, medical functional equipment, identification of wall mounted and installed power, IT, and control items. Contractor to provide all equipment necessary for users to view 3-D models.

Document mock-up milestones on the project schedule. Mock-ups must be provided and accepted prior to the start of procurement. Refer to DHA-FE Example – PP Package-Interior Mockups for expected level of development.

MOCK-UP ROOM
PROVIDE
1
Operating Room
BIM

Testing & Certification Provide an FFE-LVS Execution Plan: Testing & Certification Plan. Prior to each submittal, coordinate plan details with project representatives from the MTF facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Test and certify new FFE-LVS. Test and certify all property in accordance with manufacturer instructions. Certify that testing, measurement, and diagnostic equipment complies with calibration certifications and National Institute of Standards and Technology (NIST) requirements. Provide operational and safety results to the government prior to acceptance and use. Provide qualified Biomedical Equipment Technicians (BMETs) to perform safety checks, inspections, and calibrations on relocated medical equipment.

Security Provide an FFE-LVS Execution Plan: Security Plan. Prior to each submittal coordinate plan details with MTF facility management and safety and security personnel. Secure new FFE-LVS and existing department property. Provide necessary security provisions to keep property safe, secure, and in its designated location. The government is not responsible for the property until formal acceptance. Provide security measures to guard against damage and theft. Employ procedures to track product movement until time of acceptance.

Cleaning Develop and coordinate details of the FFE-LVS Execution Plan: Cleaning Plan and cleaning protocols with project representatives from the MTF facility management, infection control point of contact(s), and the COR in advance of cleaning. Include measures to take to ensure a clean work area and compliance with site-specific trash disposal and recycling policies. Provide cleaning services for all areas impacted by installation of new property. Clean finishes and property in accordance with manufacturer instructions, UFGS 01 78 00 Closeout Submittals, and UFGS 01 74 13 Progress Cleaning.

Inspections & Acceptance Provide an FFE-LVS Execution Plan: Inspection & Acceptance Plan. Prior to each submittal, coordinate plan details, inspections, and acceptance activities with project representatives from the MTF facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Include copies of all required property transfer forms. Acceptance cannot occur until all property is installed, tested, and certified. Provide deliverables at time of the conditional and final acceptance to ensure the process is efficient and well organized.

Prior to inspections provide (1) a Punch List stating what activities are yet to be accomplished, (2) a Pending JSN & LVS List of FFE-LVS not yet installed to include nomenclature, ECNs, a brief explanation of the issue, and a date it will be resolved.

At time of inspection, provide a current PRC & LVS List and post at the entrance/door of all areas where FFE-LVS is required. The PRC must include all current RPIE and PP JSNs, nomenclature, and ECNs. Update each ECN with the ECN of the item it replaces. This is not required for items not replaced. The current PRC will serve as a checklist for inspections and acceptance.

Upon inspection completion submit (1) Inspected Commodities List in Microsoft® Excel® format, (2) a scanned copy of the PRCs with Government inspectors’ initials and signatures.

The MTF Logistics Officer, or an officially designated representative, must sign all DD Form 250s for PP FFE-LVS at time of acceptance, and DD Form 1354s for all RPIE/EIP FFE-LVS.

Operations & Maintenance Data Provide Operations & Maintenance Data for all new FFE-LVS in accordance with the and the .

Training Provide an FFE-LVS Plan: Training Plan and coordinate with project representatives from the MTF facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Train designated personnel to properly operate and maintain new FFE-LVS.

Warranty Provide Warranty Documents in accordance with the and the .

Government Furnished Equipment & Communication Systems Coordinate all schedules with MTF personnel on government-furnished procurement efforts and government managed third-party installations. For each project phase, provide and maintain a Microsoft® Excel® Government Furnished Equipment List (GFE) of all FFE-LVS the MTF is responsible to procure (i.e., soap dispensers, information technology gear and equipment, etc.). Indicate required delivery dates. Refer to the section entitled Schedule Constraints.

Cybersecurity Provisions Refer to section entitled Communication Requirements, Division 25: Integrated Automation (Cybersecurity).

Qualifications: FFE-LVS Contractor personnel involved with FFE-LVS services are to be present on-site during all moves, installation, testing, certifications, inspections, and acceptance. The Contractor is responsible for coordinating all FFE-LVS activities.

Project Manager Provide an IO&T Project Manager (PM) responsible for the overall life-cycle management and coordination of FFE-LVS and transition services. They serve as the central point of contact for government personnel for all FFE-LVS correspondence, activities, and deliverables. The FFE-LVS PM must have an intimate knowledge of the project requirements, be able to anticipate and control risks related to (1) trades and third-party contractor coordination, (2) space planning of interim and final locations, (3) utilizing reuse property, and (4) transition. They are responsible for adequate internal controls and to minimize operational risks, conflicts, and misunderstandings. The table below outlines the required qualifications.

#
QUALIFICATIONS
REQUIRED
#
QUALIFICATIONS
REQUIRED
(Experience in this role)
Y/N
# YRS
(Experience in this role)
Y/N
# YRS
1
Total Years of Transition Experience
Yes
5
11
Budget & Procurement Documentation
Yes
5
2
DoD Criteria & Standards
Yes
3
12
Proficient in reading design documents
Yes
5
3
On-site construction management
Yes
3
13
Proficient in reading construction docs
Yes
5
4
Well-Versed in Healthcare Operations
Yes
2
14
Risk Management: Quality & Safety
Yes
5
5
Initial Outfit/Supply FFE-LVS
Yes
3
15
Proficient of & understanding of DoD healthcare PP IM-IT systems
Yes
5
6
Transition Services
Yes
3
16
Procurement, delivery, installation
Yes
5
7
New Construction Work
Yes
3
17
Testing, certification, commissioning
Yes
5
8
Multi-Phased Alterations (occupied)
Yes
3
18
Training related to property
Yes
3
9
Demolition & Disposition Work
Yes
3
19
Proficient in reading project schedules
Yes
5
10
Risk Management: Quality & Safety
Yes
3

IOT Personnel Contractor personnel involved with FFE-LVS services are to be present on-site during all moves, installation, testing, certifications, inspections, and acceptance. The Contractor is responsible for coordinating all FFE-LVS activities. Refer to section entitled Qualifications: Equipment, Qualifications: Interior Design, Qualifications: Communications.

Submittals: FFE-LVS Submittal Procedures Provide the submittals within the time constraints outlined in Schedule Constraints. Include content listed below. Submittals must comply with applicable , , and . Refer to the Attachment: Project Status Report (PSR) for distribution requirements. Refer to DHA-FE Examples for expected level of submittal development. In addition to electronic updates, provide hard copy updates since the last submittal. Provide a cover sheet for each binder section summarizing the changes within that section.

Prior to mobilization include provisions required in the Health Insurance Portability and Accountable Act (HIPAA). NOTE: If there are submittal discrepancies between what is listed in the in the table(s) and the then requirements listed in the UFCs apply.

Government Furnished Documents Any government furnished document is designated with a (G) (e.g., Project Room Contents (PRC) lists, existing inventory list, etc.). Documentation updated and maintained by the contractor is designated with a (C).

Furniture, Fixtures, and Equipment (FFE) Package Provide a Furniture, Fixtures, and Equipment (FFE) Package in a single binder. Include content outlined in the table below. The table outlines whether the contractor is responsible for developing the design submittal and/or updating the submittal. Include narratives, lists, color boards, forms, and specifications/product data. Do not include pricing. Large presentation boards and drawings may be provided under separate cover. For additional information refer also to Division 10: Specialties, Division 11: Equipment, and Division 12: Furnishings.

#
CONTENT
REFERENCE
FFE DESIGN SUBMITTALS
UPDATE ACCEPTED DESIGN SUBMITTAL*
1
Table of Contents (3-Level)
DOR
IOT
2
Narrative: Design Analysis (Furniture & Fixtures)
UFC 3-120-10 Interior Design
DOR
IOT
3
List: Point of Contacts (Project Team)
UFC 3-120-10 Interior Design
IOT
IOT
4
List: Cost Data (FFE)
UFC 3-120-10 Interior Design; UFC 4-510-01 Design: Military Medical Facilities
DOR
IOT
5
List: Item Code Legend (aka PP JSN Summary)
UFC 3-120-10 Interior Design
DOR
IOT
6
List: Project Room Contents (FFE) (Temp/Final spaces)
UFC 4-510-01 Design: Military Medical Facilities
DOR
IOT
7
List: Manufacturer Source List
UFC 3-120-10 Interior Design
DOR
IOT
8
Documents: Best Value Determination
UFC 3-120-10 Interior Design
IOT
IOT
9
Color Boards: Furniture Material Boards (8-1/2 x 11)
UFC 3-120-10 Interior Design
IOT
IOT
11
Drawings: Equipment Drawings (FFE)
UFC 4-510-01 Design: Military Medical Facilities
DOR
IOT
12
Drawings: Architectural Plans w/ FFE
UFC 3-120-10 Interior Design
DOR
IOT
13
Drawings: Room-by-Room Plans (FFE)
UFC 3-120-10 Interior Design
IOT
IOT
14
Drawings: Typical (FFE)
UFC 3-120-10 Interior Design
DOR
IOT
16
Drawings: Artwork Placement Plans
UFC 3-120-10 Interior Design
DOR
IOT
17
Specifications: Data Sheets (per Item JSN, Contract & Manufacturer/Make/Model Info, Qty, Cost)
UFC 3-120-10 Interior Design
DOR
IOT
18
Specifications: Equipment Data and Catalog Cut Sheets
UFC 4-510-01 Design: Military Medical Facilities
DOR
IOT
19
Specifications: Installation Instructions (FFE)
UFGS 12 50 00.13 10 Furniture Installation
IOT
IOT
20
Specifications: Warranty information
IOT
IOT
21
Specifications: Contact information for repairs
IOT
IOT
22
Specifications: Qualification of installers and inspectors
IOT
IOT
23
Specifications: Performance Verification & Acceptance Testing Docs
IOT
IOT
24
Specifications: Operations & Maintenance Data
IOT
IOT
25
Forms: Property Transfer Documentation (i.e., DD Form 250s)
DD Form 250 Material Inspection & Receiving Report
IOT
IOT
26
Documentation: Cybersecurity (Equipment Related)

This is the start of the file's text. The full file is on GovTribe.