B7 Electrical Svc Upgrade & 2nd Floor Structural Spt
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- N40085-20-B-2531
- Agency
- Naval Facilities Engineering Command Department of the Navy, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236210 Industrial Building Construction
- Place of performance
- Kittery ME 03904 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks a contractor to complete electrical service upgrades and second floor structural support repairs at Building 7 of the Portsmouth Naval Shipyard in Kittery, Maine. The Naval Facilities Engineering Command seeks to award a firm fixed price contract to provide all labor, equipment, materials, transportation, and supervision necessary for the project. Key requirements include upgrading the electrical service from 1600A to 1200A, installing new switchgear and transformers, and providing temporary and permanent structural support at six locations of the second floor. Proposals were due by May 22, 2020. Amendments to the solicitation were issued on April 27, May 13, and May 19, 2020.
The opportunity is set aside for total small business concerns with a NAICS code of 236210 for electrical contractors and facilities support services and size standard of $39.5 million or less. The estimated value is between $500,000 to $1,000,000. The place of performance is the Portsmouth Naval Shipyard in Kittery, Maine. Eight contractors submitted bids ranging from $494,267.28 to $791,619 by the May 22nd opening date. The selected contractor must complete all work within 210 calendar days with an estimated 90 days for on-site performance.
Notice text
5 versions
Update #5 · Latest ·
BID SYNOPSIS - RESULTS POST
Attachment 1419 B7 Electric Svc & 2nd Flr
------------------------------------------------------------------------------------------------------------------------------------------------------------
AMENDMENT 3 - POST RFI #2 RESPONSE
1. RFI #2 with NAVFAC response dated 19 May 20.Im in the office (I leave at 1430).
See Attached: N4008520B2531 0003
------------------------------------------------------------------------------------------------------------------------------------------------------------
AMENDMENT 2 - ADD/POST THE FOLLOWING SOLICITATION DOCUMENTS
1. RFIs with NAVFAC response dated 13 May 20.
2. Site Visit Sign-In Sheet.
See Attached: N4008520B2531 0002
------------------------------------------------------------------------------------------------------------------------------------------------------------
AMENDMENT 1 - UPDATE SOLICITATION DATES & CLAUSE 52.211-10
1. RFI Suspense is hereby changed From: 9 May 2020, To: 8 May 2020
2. Bid Delivery Suspense is hereby changed From: 23 May 2020, To: 22 May 2020.
3. Clause 52.211-10 edited to read "(a) commence w ork w ithin 15 calendar days after the date the Contractor receives the notice of aw ard"
See Attached: N4008520B2531 0001
------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Description: The project includes providing all labor, equipment , materials, transportation, and supervision to complete electrical service upgrades and 2nd floor structural support repairs for B7 at Portsmouth Naval Shipyard (PNSY) in Kittery Maine.
Update #4 ·
AMENDMENT 3 - POST RFI #2 RESPONSE
1. RFI #2 with NAVFAC response dated 19 May 20.
See Attached: N4008520B2531 0003
------------------------------------------------------------------------------------------------------------------------------------------------------------
AMENDMENT 2 - ADD/POST THE FOLLOWING SOLICITATION DOCUMENTS
1. RFIs with NAVFAC response dated 13 May 20.
2. Site Visit Sign-In Sheet.
See Attached: N4008520B2531 0002
------------------------------------------------------------------------------------------------------------------------------------------------------------
AMENDMENT 1 - UPDATE SOLICITATION DATES & CLAUSE 52.211-10
1. RFI Suspense is hereby changed From: 9 May 2020, To: 8 May 2020
2. Bid Delivery Suspense is hereby changed From: 23 May 2020, To: 22 May 2020.
3. Clause 52.211-10 edited to read "(a) commence w ork w ithin 15 calendar days after the date the Contractor receives the notice of aw ard"
See Attached: N4008520B2531 0001
------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Description: The project includes providing all labor, equipment , materials, transportation, and supervision to complete electrical service upgrades and 2nd floor structural support repairs for B7 at Portsmouth Naval Shipyard (PNSY) in Kittery Maine.
Update #3 ·
AMENDMENT 2 - ADD/POST THE FOLLOWING SOLICITATION DOCUMENTS
1. RFIs with NAVFAC response dated 13 May 20.
2. Site Visit Sign-In Sheet.
See Attached: N4008520B2531 0002
------------------------------------------------------------------------------------------------------------------------------------------------------------
AMENDMENT 1 - UPDATE SOLICITATION DATES & CLAUSE 52.211-10
1. RFI Suspense is hereby changed From: 9 May 2020, To: 8 May 2020
2. Bid Delivery Suspense is hereby changed From: 23 May 2020, To: 22 May 2020.
3. Clause 52.211-10 edited to read "(a) commence w ork w ithin 15 calendar days after the date the Contractor receives the notice of aw ard"
See Attached: N4008520B2531 0001
------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Description: The project includes providing all labor, equipment , materials, transportation, and supervision to complete electrical service upgrades and 2nd floor structural support repairs for B7 at Portsmouth Naval Shipyard (PNSY) in Kittery Maine.
Update #2 ·
AMENDMENT 1 - UPDATE SOLICITATION DATES & CLAUSE 52.211-10
1. RFI Suspense is hereby changed From: 9 May 2020, To: 8 May 2020
2. Bid Delivery Suspense is hereby changed From: 23 May 2020, To: 22 May 2020.
3. Clause 52.211-10 edited to read "(a) commence w ork w ithin 15 calendar days after the date the Contractor receives the notice of aw ard"
See Attached: N4008520B2531 0001
------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Description: The project includes providing all labor, equipment , materials, transportation, and supervision to complete electrical service upgrades and 2nd floor structural support repairs for B7 at Portsmouth Naval Shipyard (PNSY) in Kittery Maine.
Update #1 ·
Project Description: The project includes providing all labor, equipment , materials, transportation, and supervision to complete electrical service upgrades and 2nd floor structural support repairs for B7 at Portsmouth Naval Shipyard (PNSY) in Kittery Maine.
Attachments
Show all 19
Notice history
| Notice | Type | Posted |
|---|---|---|
| B7 Electrical Svc Upgrade & 2nd Floor Structural Spt | Award Notice | |
| B7 Electrical Svc Upgrade & 2nd Floor Structural Spt | Solicitation | |
| B7 Electrical Svc Upgrade & 2nd Floor Structural Spt | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity