012900 payment procedures.pdf

PDF 10 KB Posted

Attached to
CONSTRUCT USPFO WAREHOUSE
Solicitation number
W91364-09-B-0003
Issued by

About this file

012900 payment procedures.pdf

View the file

Other files

File Type Posted
ADDENDUM NO 02 CSMS PH II Narrative SENT.pdf PDF
USPFO_M001W.pdf PDF
019313 operation and maintenance manuals.pdf PDF
001 Binder Cover Specs Vol 1.pdf PDF
USPFO_S301W.pdf PDF
083613 sectional doors.pdf PDF
E001.pdf PDF
321313 concrete pavement surfacing.pdf PDF
USPFO_F601W.pdf PDF
260548 vibration and seismic controls for elec systems.pdf PDF
OHARNG-USPFO-A-254W .pdf PDF
C607.pdf PDF
051200 structural steel framing.pdf PDF
USPFO_S253W.pdf PDF
053100 steel decking.pdf PDF
344116 traffic control.pdf PDF
013300c attachment substitution request.pdf PDF
105626.13 mobile aisle storage shelving.pdf PDF
C700.pdf PDF
054000 cold-formed metal framing.pdf PDF
260553 electrical identification.pdf PDF
OHARNG-USPFO-A-001W .pdf PDF
E804.pdf PDF
USPFO_M204W.pdf PDF
221116 domestic water piping.pdf PDF
260529 hangers and supports for electrical systems.pdf PDF
274133 cable antenna television system.pdf PDF
264113 lightning protection for structures.pdf PDF
011000 summary —
OHARNG_USPFO_Q601W.pdf PDF
OHARNG-USPFO-G-001W .pdf PDF
C100.pdf PDF
211313 wet-pipe sprinkler systems.pdf PDF
231123 facility natural gas piping.pdf PDF
OHARNG-USPFO-G-110W .pdf PDF
013233 photographic documentation.pdf PDF
260923 lighting control devices .pdf PDF
C605.pdf PDF
087113 automatic door operators.pdf PDF
087100 door hardware.pdf PDF
USPFO_S001W.pdf PDF
312000 earthwork.pdf PDF
220500 common work results for plumbing.pdf PDF
USPFO_M202W.pdf PDF
OHARNG-USPFO-A-720W .pdf PDF
USPFO_M303W.pdf PDF
USPFO_P302W.pdf PDF
USPFO_S254W.pdf PDF
OHARNG-USPFO-G-116W .pdf PDF
010001 affirmative procurement.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F5W61608 USPFO Warehouse Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

PAYMENT PROCEDURES 012900 - 1

SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.2 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Application for Payment forms with Continuation Sheets and Submittals Schedule.

2. Submit the Schedule of Values to Contact Officer at earliest possible date but no later than seven days before the date scheduled for submittal. Contact Officer shall approve the schedule of values.

3. Subschedules: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values correlated with each phase of payment.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Project name and location.

b. Name of Architect.

c. Architect's project number.

d. Contractor's name and address.

e. Date of submittal.

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate.

3. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

4. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

PAYMENT PROCEDURES 012900 - 2

5. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

6. Allowances: Provide a separate line item in the Schedule of Values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.

7. Each item in the Schedule of Values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

8. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by the Contracting Officer and paid for by Owner.

1. Initial Application for Payment and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.

C. Payment Application Forms: Use Governments standard form.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. The Contracting Officer will return incomplete applications without action.

1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made.

2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

E. Transmittal: Submit 3 signed and notarized original copies of each Application for Payment to Contracting Officer by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

PAYMENT PROCEDURES 012900 - 3

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

F. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of Values.

3. Contractor's Construction Schedule (preliminary if not final).

4. Schedule of unit prices.

5. Submittals Schedule (preliminary if not final).

6. List of Contractor's staff assignments.

7. List of Contractor's principal consultants.

8. Copies of building permits.

9. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

10. Initial progress report.

11. Report of preconstruction conference.

12. Certificates of insurance and insurance policies.

G. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. Evidence that claims have been settled.

5. Final meter readings for utilities, a measured record of stored fuel, and similar data when Owner took possession of and assumed responsibility for corresponding elements of the Work.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01290